IR 05000213/1981013

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-213/81-13 on 811005-10.No Noncompliance Noted.Major Areas Inspected:Refueling Activities,Outage Maint & Followup on Unresolved Items
ML20032D411
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 10/26/1981
From: Bettenhausen, Petrone C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20032D405 List:
References
50-213-81-13, NUDOCS 8111130746
Download: ML20032D411 (5)


Text

-

.

U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT Region I Report No.

81-13 Docket No.

50-213 License No.

DPR-Cl Priority Cat 3 gory C

--

Licensee:

Connecticut Yankee Atomic Power Company P. O. Box 270 Hartford, Connecticut 06101 Facility Name: Haddam Neck Plant Inspection at:

Haddam, Connecticut Inspection conducted:

October 5-10, 1981 a[M/

Inspectors:

$/d #

a U. U. Petrone, Reactor Inspector

'date signed

.

date signed date signed Approved by: NN'dNd%e

/o/2//B/

L. H. Bettenhausen, Ph.D., Chief date signed Test Program Section, Engineering Inspection Branch Inspection Summary:

Inspection on October 5-10,1981 (Report No. 50-213/81-13)

Areas inspected:

Routine, unannounced onsite regular and backshift inspection of refueling activities, outage maintenance, and followup on unresolved items. The inspection involved 39 inspector-hours on site by one NRC region based inspector.

Results: No items of noncompliance were identified.

gjj!!307[ojffgo Region I Form 12 G

ADoc (Rev. April 77)

PbR3

.

.-

DETAILS 1.

Persons dontacted R. Beganski, Engineer G. Bouchard, Maintenance Supervisor N. Burnett, Engineering Supervisor Assistant

  • R. Eppinger, Reactor Engineer J. Ferguson, Unit Superintendent
  • R. Graves, Station Superintenderm M. Hadfield, Senior Reactor Operator R. Reeves, Senior Reactor Operator R. Rogozinski, Associate Engineer
  • R. Test, Engineering Supervisor The inspector also interviewed cther licensee personnel including control room operators and contractor personnel.
  • Denotes those present at exit interview on October 10, 1981.

2.

Licensee Action on Previous Inspection Findings (Closed) Inspector Follow Item (50-213/80-CI-21); " Regulation of Refueling Crews". Review of FP-CYW-R1D, " Refueling Procedures for Cycle X-XI, Connecticut Yankee", fadicated that the requirements of IEC 80-21 were being satisfied. This item is closed.

<

(Closed) Unresolved Item (50-213/80-24-02) " Control Rod. Drop Times". The hot rod drop time tests were conducted with three reactor coclant pumps operating instead of four pumps. The licensee used a 0.05 second correction to account for three pump operation. The correction was derived from earlier test results which were not available for review during the previous inspection.

The inspector reviewed these test results; the use of the 0.05 second correction was justified.

The inspector had no further questions regarding this item.

(Closed) Noncompliance (50-213/80-24-01) " Failure to Review and Approve Startup Test Procedure SUR 5.3-6, Computational Errors therein and in calculation of Moderator Temperature Coefficient." The licensee representative has reviewed and corrected the test results.

In addition, Revision 5 to SUR 5.3-6 has since been issued which provides detailed instructions on how tu calculate the Moderator Temperature Coefficient.

This item is close..

.

---

c

.

,

.

,

.

3.

Maintenance Activities l

a.

Documents Reviewed Connecticut Yankee (CY) Quality Assurance Procedure QA 1.2-2.4,

'

--

Revision 7, " Housekeeping Requirements," dated August 8, 1980.

--

CY QA 1.2-5.1, Revision 14, " Maintenance / Work Requests and Work Permits," dated September 24, 1981.

.

--

CY Preventive Maintenance Procedure No. PM 9.5-36, Revision 6,

-

" Preventive Maintenance of the Emergency Diesels," dated August 20, 1981.

--

Work Permit No. MA 2633, " Emergency Diesel. Generator #2A Periodic Maintenance."

Work Permit No. MA 2636, " Emergency Diesel Generator #2B

--

Periodic Maintenance."

--

CY M 8.5-40, Revision 3, " Maintenance of Steam Generator Auxiliary Feed Pumps'," dated March 13, 1981.

--

CY M 8.5-23, Revision 1, " Rod Drive Mechanisms," dated October 3, 1975.

--

CY QA 1.2-10.1, Revision 6, " Installation Inspections," dated October 23, 1980.

--

CY QA 1.2-11.3, Revision 7, " Retest / Test Requirements," dated March 17, 1980.

b.

Maintenance Witnessed The inspector witnessed the performance of maintenance on Emergency

^

Diesel Generator (EDG) 2A. The work was being performed in accordance with procedure PM 9.5-36 which included:

--

administrative approvals for removing the system from service and returning it to service;

--

appropriate hold points for inspection, audit and signoff by QA or other licensee personnel; provisions for operational readiness inspections following

--

maintenance; provisions for assuring that LCO requirements of the technical

--

specifications were satisfied during the repair period;

..

_ - _ _ _ _ - _ _ - _ - - - _ _ _ _ -

-

.

'

-

.-

I.

.

--

provisions for the control of housekeeping;

'

--

provisions for cleaning safety related systems and components

'

following maintenance; and

'

provisions for assuring that system valves, breakers, etc., are

--

aligned for normal service.

The inspector verified that the reactor operators were aware that EDG l

2A was tagged out of service, that the tools and gauges being used by the technicians had current calibration certifications, that the work'

was being performed by experienced and knowledgeable technicians, that the required tagouts had been performed in accordance Nith the procedure, and that all prerequisites in the procedure had been signed off.

In addition the inspector reviewed the completed, signed procedure (PM 9.5-36) and work permit (W.P. No. MA 2633) for EDG 28.~The. preventive maintenance on this generator had been completed the previous week.

All appropriate verifications had been signed off.

In addition the inspector toured the EDG 2B room and verified that tagouts had been removed and the work area had been carefully cleaned. The reactor operator reported that EDG 2B had been tested and verified to be operational.

c.

Findings No items of noncompliance were identified.

,

4.

Refueling Activities a.

Documents Reviewed

--

FP-CYW-R10, " Refueling Procedures for Cycle X-XI, Connecticut Yankee," Dated September 18, 1981.

--

Work Permit EN 0658, " Fuel Movement."

The inspector reviewed these documents against the Technical Specifi-cations and verified that they were approved and technically acceptable procedures.

b.

The inspector observed refueling activities on the day and evening shifts, both in the control room and on the refueling floor and verified, based on these observations, that:

--

Fuel handling activities were being performed in accordance with FP-CYW-R1 __.

.,

..

s

-, 4

,

~.i.

The licensee's staffing during refueling was in accordance with

--

.

, Technical Specifications, approved procedures, and the guidance

?'

of IE Circular 80-21.

Good housekeeping was being maintained in the refueling area.

--

--

Completed checkoff sheets indicated that the refueling machine i

had been checked out, indexed, and that a dry run using a dummy

,

module had been performed prior to actual fuel movement.

--

Fuelaccountabilitywasbeingmaintainedinacbordancewit'

,

.g established procedures.

--

Neutron monitoring was being performed and a 1/M plot was being

maintained.

--

The boron concentration was being monitored.

--

Communications were being maintained between the control room and the refueling floor crew.

--

Water level in the refueling cavity was being maintained above 23

<?

feet, as required, and was being monitored on the refueling floor and in the control room.

e--

--

Refueling floor radiation monitors were in place and operating.

--

Precautions were bei..g taken to prevent foreign objects from falling into the reactor vessel.

'

A review of checkoff sheets indicated that all surveillance

--:

testing required by Technical Specifications and licensee pro-cedures had been performed prior to fuel handling.

c.

Findings

'

No iters of noncompliance were identified.

,

'

-

,

n.

5.

Exit Interview (

The inspector met with licensee representatives (see detail 1 for attendees) at the conclusion of the inspection on October 10, 1981. The

,

inspector summarized the scope and findings of the inspection at that time.

l i

I>

.

t t

I

-

,....,,

.-

.