IR 05000206/1988009

From kanterella
Jump to navigation Jump to search
Insp Rept 50-206/88-09 on 880314-0408.No Violations Noted. Major Areas Inspected:Containment Integrated Leak Rate Test & Followup on Open Items
ML13316B893
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 04/21/1988
From: Clark C, Richards S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML13316B892 List:
References
50-206-88-09, 50-206-88-9, GL-85-22, NUDOCS 8805060313
Download: ML13316B893 (7)


Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION V

Report No. 50-206/88-09 Docket No. 50-206 License No. DPR-13 Licensee: Southern California Edison Company P. 0. Box 800 2244 Walnut Grove Avenue Rosemead, California 91770 Facility Name:

San Onofre Nuclear Generating Station Unit 1 Inspection at:

San Clemente, California Inspection Conducted:

March 14 -

April 8, 1988 Inspector:

C. C

, Reactor Inspector Date Signed Approved by:

____

.1 /s S. Richards, Chief Date Signed Engineering Section Inspection During the Period March 14 - April 8, 1988 (Report No. 50-206/88-09)

Areas Inspected:

A routine announced inspection of Unit 1 activities relating to a containment Integrated Leak Rate Test (ILRT) and followup on open item The ILRT inspection included review of procedures and records, interviews with personnel, witnessing portions of the ILRT, inspection of the Containment Building, associated penetrations and piping systems. During this inspection, inspection procedures 30703, 70307, 70313 and 92701 were covere Results:

In the areas inspected, no violations of NRC requirements were identified:

8805060313 880421 PDR ADOCK 05000206 Q

DCD

DETAILS Persons Contacted Licensee C. Couser., Lead Compliance Engineer M. Zenker, Compliance Engineer

  • D. Irvine, Station Technical Supervisor S. Gosselin, Station Technical Supervisor
  • P. Blakeslee, ILRT Test Director Contractor Personnel (Bechtel Power Corporation)
  • B. Patel, ILRT Engineer Denotes those personnel in attendance at an exit meeting on March 21, 198 The inspector also held discussions with other licensee and contractor personnel involved with the ILR.

Containment Integrated Leak Rate Test (ILRT) Procedure Review The inspector reviewed the Unit 1 ILRT procedures as described in the licensee's Engineering Procedure SO1-V-1.3 Revision 13, TCN 13-1 of March 17, 1988 (and the Temporary Change Notices issued during this inspection) entitled, "Sphere Integrated Leakage Rate Test."

This review was to ascertain compliance with plant Technical Specifications, regulatory requirements, and applicable industrial standards as stated in the following documents:

o San Onofre Nuclear Generating Station, Unit 1, Final Safety Analysis Report (FSAR), Section 4.3, "Containment Sphere".

o San Onofre Nuclear Generating Station, Unit No. 1, Technical Specifications, Section 4.3.1, "Containment Testing" and 3/4.6.1.2, "Containment Leakage".

o Appendix J to 10 CFR 50, "Primary Reactor Containment Leakage Testing for Water Cooled Power Reactors."

o American National Standard, "Leakage-Rate Testing of Containment Structures for Nuclear Reactors," ANSI N45.4-197 o Topical Report BN-TOP-1, Revision 1, "Testing Criteria for-.

Integrated Leakage Rate Testing of Primary Containment Structures for Nuclear Power Plants," Bechtel Corporatio American National Standard, "Containment System Leakage Testing Requirements," ANSI/ANS-56.8-198 o IE Information Notice No. 85-71, "Containment Integrated Leak Rate Tests."

USNRC letter (R. Dudley to K. Baskin) to SCE, dated July 2, 1987, which provided authorization to utilize BN-TOP-1, Revision 1, 1972 for a Type A Tes During this procedure review, the inspector identified the following observations:

The Attachment 9 "Pressurization System", in the Unit 1 ILRT procedure did not provide the same detail information found in previous ILRT procedures used for performance of ILRT's on Units 2 and 3 containment The last Unit 2 ILRT was performed per Engineering Procedure S02-V-3.12, Revision 1, TCN No. 1-4, "Containment Integrated Leakage Rate Test".

Attachment 3 to the Unit 2 ILRT procedure provided detail information and figures, showing system installation and hookup of support systems such as cooling wate While this general procedure has been used to perform the Unit 1 ILRT several times, addition information on the pressurization/

depressurization system would help clarify installation of this system. During initial pressurization for this test, it was identified by the Atlas Copco air compressor operator that the cooling water supply to the after-cooler was connected to the outlet nozzle instead of the inlet nozzl While this was not a safety concern and did not delay the test, it did initially prevent the after cooler from reducing the temperature of the air going into containment down to its expected valve of 70'F. Instead the air was entering containment at approximately 80' No violations or deviations were identifie Review of Records The inspector reviewed calibration records for the instrumentation used in the ILRT. That is, the twenty-four resistance temperature detectors (RTDs), six dew point temperature sensors (dew cells), two pressure gauges used to measure containment air mass, and the flow element used to measure the induced leak during the verification portion of the ILRT. All instruments had been calibrated within the last six months with NBS traceability certificates available. The inspector also discussed the in situ check of the instrumentation with the licensee. It was noted that there was trouble with the in situ check of dew cell ME-5 (which performed acceptably later during the ILRT).

Both of the original flow meters installed in the ILRT data acquisition cabinet failed during check out of equipment and therefore alternate flow measuring equipment was installed on the

cabinet discharge lines for the verification flow tes The inspector reviewed the records to assure that the following required activities were performed prior to initial pressurization:

(1) Completion of all available identified local leakage rate testing and identification of leak rates prior to and after any repair (2) Removal or venting of items listed on the equipment protection and venting schedul (3) Inspection of interior and exterior containment surfaces and components for evidence of deterioration or damag (4) Containment sump water levels below high level mar (5) ILRT measurement system properly installed and functionally checke (6) Pressurization system in service. Three 900 cfm, one 1200 cfm and one 1500 cfm capacity air compressors were available for this ILR (7) Pressurization system tested, including proper operation of the air compressors, after-coolers, moisture separators, air dryers, pressurization system manifold and discharge spoo This system test did not identify that the cooling water to the after-cooler was connected up backwards, due to its short duration and minimum system informatio (8) Containment ventilation system adjustments complete (9) Valve lineups complete (10) Containment temperature survey to verify temperature sensor locations. A licensee survey was performed prior to the ILRT with some containment ventilation fans runnin No violations or deviations were identifie c. Observation of Work and Work Activities Prior to the ILRT, the regional inspector performed containment area surveys for pressurized components (such as tanks, fire extinguishers, etc.), valve lineups and instrument location assignments within the Containment Building. The purpose of the instrument survey was to locate and evaluate the placement of the temperature sensors and dewpoint sensors. This inspection revealed that the sensors were located within the tolerances of the installation procedures. The operation of the pressurization equipment (air compressors, after-coolers and air dryers) used for pressurization of the Containment Building was inspected to assure that procedures for prevention of potential problems were enforce This included evidence of checking the pressurizing air for indications of oil contamination, establishment of communications

between the ILRT control center and the pressurization station, adequate supply of cooling water to the after-coolers, and that control of the after-cooler air temperature was being maintained during pressurization. During initial pressurization, it was discovered that the cooling water supply to the after-cooler was incorrectly connected to the after-cooler discharge nozzle and the after-cooler was not adequately cooling the ai The cooling water supply was connected to the correct inlet nozzle and the expected after-cooler discharge air temperature was obtaine The inspector witnessed selected portions of the following ILRT activities listed below and noted the time expended to perform each:

(1) Initial pressurization to 51 psig (65.7 psia) + 0.4/-0 psig/psia. Approximately 15 hour1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br /> (2) ILRT stabilization. Approximately 6 hour6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> (3) ILRT data acquisitio (4) Performance of ILRT. Approximately 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> (5) Leak rate verification test stabilization. Approximately 1 hou (6) Leakage rate verification test. Approximately 6.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />, with an imposed leak rate of 4.4 standard cubic feet per minute (SCFM).

(7) Initial Containment Building depressurizatio Applicable electrical and mechanical penetrations were inspecte Applicable portions of the valve lineups were inspected to see that they were completed in accordance with procedure and that no unidentified artificial barriers were erecte The overall performance of the ILRT crew members was observed by the inspector. Attributes evaluated were:

availability of test procedures, test prerequisites being met, proper plant systems in service, special test equipment calibrated and in service, and crew action timely and correct. Crew members had received ILRT training prior to the test, and this appeared evident by satisfactory performance of their dutie The licensee's preliminary results for the twenty-four hour type A test, which did not include type B or C additions, was a total time calculated leakage rate of 0.041 wt. % per day with a 95% upper confidence limit (UCL) of 0.051 wt. % per day. The licensee's maximum allowable leak rate for this test was 0.090 wt. % per da For information only, a mass-point analysis provided a calculated leak rate of 0.049 wt. % per day with a 95% UCL of 0.051 wt. % per day. A six and one-half hour verification test was performed with an imposed leak rate of approximately 4.4 SCFM or 0.12% per day of containment air mass. The licensee verification test produced a

total time calculated leak rate of 0.147 wt. % per day. The total time analysis of the verification test leakage rate provided an acceptance criteria of 0.131 to 0.191 wt. % per da For information only, the mass point analysis of the verification test provided a calculated leak rate of 0.141 wt. % per day and an acceptance criteria of 0.139 to 0.199 wt. % per day. These preliminary results appear to be within the latest allowed acceptance criteri No violations or deviations were identifie.

Licensee Actions on Previous Inspection Findings (Closed) Followup Item 50-206/86-20-07:

Operability of Leaking Batteries This item identified a concern about the leaking condition of the number 1 battery in Unit 1. The NRC concurred that the leaking condition should not affect the functionality of the battery, but were concerned that final corrective action had not been initiate The licensee has performed weekly inspections and quarterly surveillance tests of this battery, to assure it is in a fully operable condition. The issuance of Nonconformance Report (NCR)

number SO1-P-5226, Revision 1 on October 14, 1987, directed the replacement of the twenty-six leaking cells per maintenance order no. 8505275200 (during the cycle X refueling outage).

The licensee has taken appropriate actions, therefore this item is close (Closed) Followup Item 50-206/87-05-03:

Recategorize 17 Check Valves as "AC" for IST Purposes This item identified that as the result of the Unit 1 water hammer event of November 21, 1985, 17 check valves in the feedwater system and auxiliary feedwater system had been replaced after the event and the IST program valve test requirements revised for those valve However the valves in question were still designated in the IST program as category "C" valves instead of as category "AC" valve The licensee issued Temporary Change Notice (TCN) No. 5-20 to Engineering Procedure SO1-V-2.15, Revision 5, "In Service Testing of Valves Program", on September 11, 1987 to recategorize the identified valve The licensee has taken appropriate actions, therefore this item is close (Closed) Followup Item 50-206/87-05-04:

Should Valve FCV-5051 be Included in IST Program This item questioned whether valves which can be controlled from the licensee's dedicated shutdown (DSD) panel should be included in the valve IST program. The licensee identified that only valve FCV-5051 had its position indicated on the DSD panel, and was not included in

the IST program. The licensee issued Problem Review Report (PRR)

SO-133-87 dated June 8, 1987 to review this concern on valve FCV-5051. The licensee obtained additional information from NRR, as identified in a memorandum from P. Croy to file (dated August 10, 1987), that stated "components which are installed only for compliance with Appendix "R" of 10 CFR 50, such as valve FCV-5051 in the Songs 1 dedicated and alternate shutdown systems, do not have to be included in the IST program".

Based on the above memorandum and review of references identified in this memorandum, valve FCV-5051 does not have to be in the IST program at this time, and this item is close (Closed) Followup Item 50-206/87-05-05:

Incorporation of Specific Valve Stroke Timing Method In Valve Test Procedures During a review of Unit 1 valve test procedures, it was noted that the method to be used for obtaining valve stroke times was not specified. The licensee issued TCN No. 6-6 to Revision 6 of Operating Instruction S01-12.4-2, "Operations In Service Valve Testing," dated August 4, 1987 to identify when "stroke time" starts and stop The licensee has identified that the above TCN fulfills their commitment to add a valve stroke time technique to appropriate procedures and ensure valve stroke timing consistency in accordance with the requirements of IWV-3413a of Section XI of the ASME Cod It appears the licensee has taken the action to clarify a valve stroke timing method, therefore this item is close.

Exit Meeting The inspector held a meeting with the licensee representatives denoted in paragraph 1, on March 21, 1988. The scope of the inspection and the inspector's findings up to the time of the meeting, as noted in this report, were discussed. At this meeting, the inspector also identified that additional information had been requested from Compliance on an open ite It was identified that this material would be reviewed in the Region V offices and the inspector's findings documented in this report. The inspection period for this report was extended to April 8, 1988, to provide the licensee's compliance organization additional time to provide information on what licensee actions were taken on Generic Letter N, "Potential for Loss of Post-LOCA Recirculation Capability Due to Insulation Debris Blockage."

Since additional information was not available by April 8, 1988, the licensee actions taken for this Generic Letter in Unit 1, will be covered in a future repor III