E910-05-054, Rev. 0 to Calculation E900-03-014, Shonka Line Shack & Warehouse/Garage Pads FSS Survey Design, Appendix a to Final Status Survey Report for Saxton Nuclear Experimental Corporation Structural Surfaces - Small Penelec Garage GA1-1.

From kanterella
Jump to navigation Jump to search
Rev. 0 to Calculation E900-03-014, Shonka Line Shack & Warehouse/Garage Pads FSS Survey Design, Appendix a to Final Status Survey Report for Saxton Nuclear Experimental Corporation Structural Surfaces - Small Penelec Garage GA1-1.
ML052140178
Person / Time
Site: Saxton File:GPU Nuclear icon.png
Issue date: 07/21/2003
From: Donnachie P
FirstEnergy Corp
To:
Office of Nuclear Reactor Regulation
References
E910-05-054 E900-03-014, Rev 0
Download: ML052140178 (83)


Text

Appendix A SCM Survey Design

ORIGINAL SNEC CALCULATION COVER SHEET

'.-..'.CALCULATION DESCRIPTION I.h.cA - .. i 'J Calculation Number Revision Number Eff Page Number ES00-03-014 01//4 1 of 5 Subject Shonka Line Shack & Warehouse/Garage Pads FSS Survey Design Question I - Is this calculation defined as 'in QA Scope-? Refer to definition 3.5. Yes 0 No a Question 2 - Is this calculation defined as a Design Calculation? Refer to definitions 3.2 and 3.3. Yes ED No C Question 3 - Does the calculation have the potential to affect an SSC as described in the USAR? Yes El No 0 NOTES: If a 'Yes answer is obtained for Question 1, the calculation must meet the requirements of the SNEC Facility Decommissioning Quality Assurance Plan. If a 'Yes answer Is obtained for Question 2, the Calculation Originator's Immediate supervisor should not review the calculation as the Technical Reviewer. If a 'YES answer is obtained for Question 3, SNEC Management approval is required to Implement the calculation. Calculations that do not have the potential to affect SSCs may be Implemented by the TR.

DESCRIPTION OF REVISION '.;

.,r,: _: s ?.. .:. J., ' - a+.,. . -..

-1 i , . ,, , . - ;_tT; .. '.-

Calculation Originator Date _719,11 a Technical Reviewer Additional Review Additional Review SNEC Management Approval

SNEC CALCULATION SHEET Calculation Number Revision Number Page Number E900-03-014 0 Page 2 of 5_

Subject Shonka Line Shack & Warehouse/Garage Pads FSS Survey Design 1.0 PURPOSE 1.1 The purpose of this calculation is to provide the survey design guidance to be followed for conducting final status surveys (FSS) in the Penelec Line Shack and on the concrete pads where the SNEC Warehouse and Garage were formerly located.

1.2 Shonka Research Associates (SRA) will conduct scan surveys using procedures reviewed and approved by SNEC. These procedures are attached as Appendices.

2.0

SUMMARY

OF RESULTS 2.1 The following information will be used to conduct the applicable FSS for this survey design:

2.1.1 The Line Shack area is divided into four (4) Class 2 and one (1) Class 3 survey units.

2.1.2 The Line Shack Survey Unit (SU) Numbers are as follows:

SU Number Area Description Classification Area (mZ)

LS1-1 Floors 2 290 LS1-2 Interior walls up to 2 meters 2 177 LS2-1 Interior upper walls & ceiling 2 603 LS3 Exterior walls 3 343 LS4 Roof 2 324 2.1.3 The Warehouse and Garage Pads areas are divided into two (2) Class 2 survey units.

2.1.4 The Survey Unit Numbers for these Pads are as follows:

SU Number Area Description Classification Area (mi)

WA1-1 Warehouse Pad Floor and 2 450 sides GA1-1 Garage Pad 2 109 2.1.5 The number of static measurement points will be developed after SRA completes their survey and results are reviewed by the FSS group.

2.1.6 The minimum scan coverage for Class 2 areas will be 50% and for Class 3 areas, 10-50%.

2.1.7 Scan speed will be set in accordance with SRA procedures and the SNEC MDCscan value calculated for structure surfaces.

2.1.8 The surface DCGLW for this design is determined to be 21,000 dpm/lOO cm2 based on the NRC default value for Cs-137 and application of SNEC's practice of applying a 75% administrative limit.

2.1.9 The DCGL,,,,, will use the Cs-137 surface area factor for a 1-m2 area equal to 11.

SNEC CALCULATION SHEET Calculation Number Revision Number Page Number E900-03-014 0 Page 3 of_5_

Subject Shonka Line Shack & WarehouselGarage Pads FSS Survey Design 2.1.10 The MDC,,an value for this design that SRA must achieve is 10,500 dpml/100 cm2.

2.1.11 Areas greater than the DCGL, must be identified, documented, marked, and bounded to include an area estimate.

2.1.12 Remediation is indicated when any area exceeds 3 x the DCGLW for any scan measurement or when the value for any area of -1 square meter is greater than the DCGLC. Note: If remediation is performed this survey design is void.

2.1.13 Gas flow proportional counter (GFPC) will be used IAW SRA procedures.

3.0 REFERENCES

3.1 SNEC Facility License Termination Plan.

3.2 Procedure E900-IMP-4500.59, "Final Site Survey Planning and DQA".

3.3 SNEC procedure E900-IMP-4520.04, "Survey Methodology to Support SNEC License Termination".

3.4 SNEC procedure E900-IMP-4520.06, "Survey Unit Inspection in Support of FSS Design".

3.5 NUREG-1575, "Multi-Agency Radiation Survey and Site Investigation Manual", August 2000.

3.6 SRA Procedures - See Appendix Section 6.0.

4.0 ASSUMPTIONS AND BASIC DATA 4.1 SRA procedures to be used to perform scan surveys.

4.2 Remediation History Demolition of the SNEC Warehouse and Garage was performed in 2002. Only the foundation pads for these buildings remained after demolition.

4.3 This survey design uses the NRC default gross activity DCGLW, value for Cs-137. This value was used since only Cs-137 was detected in samples obtained from the respective survey units. A 25% reduction to the gross activity DCGLw was performed to address de-listed radionuclides. The SNEC facility has instituted an administrative limit of 75% for the allowable dose for all measurement results. The de-listed radionuclide dose is accounted for within the 75% administrative limit. The 75% administrative limit is then applied as follows: 0.75 x 28,000 dpm/100 cm2 = 21,000 dpm/100 cm2.

4.4 The MDCSC 2n calculation is determined based on LTP section 5.5.2.5. The calculation consists of the following: 28,000 dpm/100 cm2 x 0.75 x 0.5 = 10,500 dpm/100 cm2.

4.5 Special measurements including gamma-ray spectroscopy are not included in this survey design.

4.6 Static and other survey measurements will be conducted after review of the SRA survey is completed. This design will be revised to incorporate these surveys as determined by the FSS group.

4.7 The survey design checklist is listed in Attachment 1.

SNEC CALCULATION SHEET Calculation Number Revision Number Page Number E900-03-014 0 Page 4 of_5_

Subject Shonka Line Shack & Warehouse/Garage Pads FSS Survey Design 5.0 CALCULATIONS

- The required DCGLw = 28,000 x 0.75=21,000 dpm/100 cm2 .

  • The MDCSCan = 21,000 xO.5 = 10,500 dpm/100 cm2.
  • DCGLnc for1 m2 =21,OOOXAFof 11 =231,000 dpm/100 cm2.

6.0 APPENDICES 6.1 Attachment 1, Survey Design Checklist.

6.2 Attachment 2, SRA SCM Procedure 001, Rev 6, Confirmation and Calibration of the Incremental Encoder.

6.3 Attachment 3. SRA SCM Procedure 005, Rev 6, Requirements for Completion of the Survey Using the SCM.

6.4 Attachment 4, SRA SCM Procedure 006, Rev 4, Performance of a Position Calibration on a PSPC.

6.5 Attachment 5, SRA SCM Procedure 007, Rev 7, Source Response Check and Performance Based Check of any PSPC Detector Configuration Installed on the SCM.

6.6 Attachment 6, SRA SCM Procedure 008, Rev 3, Conduct of Operations for Surveys Using the SCM/SIMS.

6.7 Attachment 7, SRA SCM Procedure 011, Rev 1, Survey Naming Convention when Using the SCM.

t . SNEC CALCULATION SHEET Calculation Number Revision Number Page Number E900-03-014 0 Page 5 of&

Subject Shonka Line Shack & Warehouse/Garage Pads FSS Survey Design Exhibit I Survey Design Checklist A if Calculation No. Location Code go- kaD/C t$eJW - .

6900-03. I cA 2^, zV'1, OeVS : C& G _ ra/_

1 /

Status Reviewer ITEMREVEW Fcus(Circle One) InItials & Date I Has a survey design calculation number been assigned and is a survey design summary /9 "'\UA 2 Are drawings/diagrams adequate description provided?

for the subject area (drawings should have compass headings)?,

Ye N/A hW ?1;li3 3 Are boundaries properly identified and is the survey area classification clearly Indicated? (YesN/A lD 4 Has the survey area(s) been properly divided into survey units lAW EXHIBIT 10 Yes A - 3 5 Are physical characteristics of the area/location or system documented? Yes N/A -

6 Is a remediation effectiveness discussion Included? Yes, A 7 Have characterization survey and/or sampling results been converted to units that are e A 1 comparable to applicable DCGL values? /o a Is survey and/or sampling data that was used for determining survey unit variance Included? Yes, N/A/3 Is a description of the background reference areas (or materials) and their survey and/or / )N/A sampling results Included along with a lustification for their selection? 7/.21.3

(\U2) 10 Are applicable survey and/or sampling data that was used to determine variability Included? Yes, N/A h 11 Will the condition of the survey area have an impact on the survey design, and has the e N/A 2 ,i/

probable impact been considered In the design? e_,_______

Has any special area characteristic Including any additional residual radioactivity (notv 12 previously noted during characterization) been Identified along with its Impact on survey Yes N/A ) ,'

design? L 7 /;(/i0 13 Are all necessary supporting calculations and/or site procedures referenced or Included? N/A r X 14 Has an effective DCGLw been Identified for the survey unit(s)? FesN/A; 15 Was the appropriate DCGLMc Included In the survey design calulation? A l 16 Has the statistical tests that will be used to evaluate the data been Identified? Ye A l ,o}

17 Has an elevated measurement comparison been performed (Class 1 Area)? es N/A 18 Has the decision error levels been identified and are the necessary justifications provided? Yes, A 19 Has scan Instrumentation been identified along with the assigned scanning methodology? es N/A 20 Has the scan rate been Identified, and Is the MDCscan adequate for the survey design? e N/A ) /

21 Are special measurements e.g., In-situ gamma-ray spectroscopy required under this design, Yes,(i9 and is the survey methodology, and evaluation methods described? 7 22 Issurvey Instrumentation calibration data Included and are detection sensitivities adequate? SN/A 4 8 23 Have the assigned sample and/or measurement locations been clearly Identified on a diagram A or CAD drawing of the survey area(s) along with their coordinates? (I/;/oX2 24 Are Investigation levels and administrative limits adequate, and are any associated actionsN/A clearly Indicated? e 11l10 25 For sample analysis, have the required MDA values been determined.? Yes, N/A 26 Has any special sampling methodology been Identified other than provided In Reference 6.3? Ye, A NOTE: a copy of this completed form or equivalent, shall be included within the survey design calculation.

.4 -1A-4 e-e nLC4'ir I Control Copy #_ _

Shonka Research Associates, Inc.

4939 Lower Roswell Road, Suite 106 Marietta GA 30068 770-509-7606 Surface Contamination Monitor SCM Procedure 001, Rev6 Confirmation and Calibration of the Incremental Encoder

SCM PROCEDURE 001, REV6 DATE: 9/1701 PAGE 2 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF.THE INCREMENTAL ENCODER Table A 1. Revision Table REVIEWED BY: D. DEBORD REVISION AUTHOR(S) BRIEF

SUMMARY

OF REVIEWER(S) DATE Added details on how to 006 M. Marcial  ; o 9/7/01 name the survey name that is X also the SCM filename.

QA REVIEW BY: D. SHONKA I DATE:

- ?4N S. k-. 1 917101 EFFECTIVE DATE: 917/01

SCM PROCEDURE 001, REV6 DATE: 917101 PAGE 3 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER

1. Purpose This procedure establishes the methods for calibration and verification of the incremental encoder included on the SCM.
2. Scope and Limitations This procedure applies to version 2.0 or later of the process software. Any SCM used to conduct a rolling survey must have completed a valid encoder confirmation. Perform a new encoder confirmation if any of the following occur.
1. Maintenance on the encoder
2. Disassembly/re-assembly of the cart
3. Adding a new computer, software, or encoder to the cart.
4. 24 months since last confirmation
5. Operator notices anomalies inthe reported strip length Perform a calibration whenever the mean of an encoder confirmation exceeds 1%error.
3. Definitions and Acronyms

~~.......... Table 1. Definitions and Acronyms.

ITEM DESCRIPTION The Surface Contamination Monitor isa mobile platform SCM containing detectors, support electronics, and data logger used for conducting radiological surveys.

Incremental Encoder Electronic device used to measure rotation.

SMaximum survey speed determined to support required Target Survey SpeedMDA

............................... .. m MDA I Minimnum Detectable Activity

4. General Information The incremental encoder provides a method of determining the distance traveled by the SCM. The encoder turns and generates TTL level pulses at regular intervals. A calibration factor in pulses per inch allows the SCM to determine distance by number of pulses. This calibration factor could be determined by dividing the pulses per rotation by the circumference of the wheeL To reduce the impact of measurement error this procedure determines the calibration factor by rolling the cart a known distance and dividing by the pulses received by the counter card in the SCM to get a pulse/in factor.

SCM PROCEDURE 001, REVS DATE: 917101 PAGE 4 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER The user must be cautious to operate the SCM in straight lines parallel to the measuring tape. Failure to do so can result in distance errors of more than 1%.

5. Materials, Equipment, and Supplies Table 2. Materials, Equipment, and Supplies.

ITEM SPECIFICATION SCM Model 3 SCM Process Software Version 2.0 or later I Tape Measure 30 ft. 10 m, or longer

.... ~~~~~.... . .. . ............. . . .................... ............... A.............. ....... ..... ......... .... ....................... . ..... .. ... ..........

Tape must be suitable for securing tape measure to floor

. Tape . surface such as electrical tape.

6. Responsibilities 6.1. Operator 6.1.1. Reads and becomes familiar with this procedure before performing calibration.

6.1.2. Has successfully completed SCM I training.

6.1.3. Performs measurements in accordance to this procedure.

7. Procedure NOTE: Any means that is suitablefor securing the tape measure to thefloor may be substitutedforelectricaltape.

7.1. Confirmation of encoder for use in US mode 7.1.1. Secure the tape measure to the floor with a piece of electrical tape at the zero inch mark.

7.1.2. Extend the tape measure and secure it to the floor at a distance not less than 30 feet with a second piece of electrical tape.

7.1.3. Record the distance in inches on the "Incremental Encoder Calibration Verification Data Sheet for Use in Inch Mode" provided in Appendix A.

7.1.4. If the SCM is powered off, turn on the system and launch the process software.

SCM PROCEDURE 001, REVS DATE: 97101 PAGE 5 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER 7.1.5. If the target survey speed is less than 2 in/sec, set the motor controller to 2 in/sec, else set the motor controller to the target _

survey speed.

7.1.6. Enter a new survey name. See SCM Procedure 011.

7.1.7. Position the SCM at either piece of electrical tape.

7.1.8. Initiate the measurement by pressing the <Enter> key.

7.1.9. Roll the cart forward until and line up with the opposite piece of electrical tape.

NOTE: The cart must be kept traveling in a straightline. 77Te operatormay use the tape measure and a fixed point on the frame to guide the cart. In addition, take care when aligning the cart to the tape to avoidparallax error.

7.1. 10. Complete the measurement by pressing the <Enter> key.

7.1.11. Record the reported strip length in inches on the "Incremental Encoder Calibration Verification Data Sheet for Use in Inch Mode" provided in Appendix A.

7.1.12. Follow the software prompts and repeat steps 7.1.7- 7.1.1 I two additional times.

7.1.13. Proceed to Section 8.1 and perform acceptance criteria calculations.

7.2. Confirmation of encoder for use in metric mode 7.2.1. Secure the tape measure to the floor with a piece of electrical tape at the zero meter mark.

7.2.2. Extend the tape measure and secure it to the floor at a distance of 10 meters or more with a second piece of electrical-tape.

7.2.3. Record the distance in meters in the "Actual Distance" blank on the "Incremental Encoder Calibration Verification Data Sheet for Use in Metric Mode" provided in Appendix B.

7.2.4. If the SCM is powered off, turn on the system and launch the process software.

7.2.5. If the target survey speed is less than 2 in/sec, set the motor controller to 2 in/sec, else set the motor controller to the target survey speed.

7.2.6. Enter a new survey name. See SCM Procedure 011, "Survey Naming Convention when Using the SCM".

7.2.7. Position the SCMl at either piece of electrical tape.

7.2.8. Initiate the measurement by pressing the <Enter> key.

SCM PROCEDURE 001, REV6 DATE: 917101 PAGE 6 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER 7.2.9. Roll the cart forward and line up with the opposite piece of electrical tape.

NOTE: The cart must be kept traveling in a straightline. The operatormay use the tape measure and a fixed point on the frame to guide the cart. In addition, take care when aligningthe cart to the tape to avoid parallaxerror.

7.2.10. Complete the measurement by pressing the <Enter> key.

7.2.11. Record the reported strip lengths in inches in the Strip Distance Table on the form "Metric Mode Incremental Encoder Calibration Verification Form" provided in Appendix B.

7.2.12. Follow the software prompts and repeat steps 7.2.7- 7.2.1 1 two additional times.

7.2.13. Proceed to Section 8.2 and perform acceptance criteria calculations.

7.3. Encoder Calibration This section uses the "Encoder Calibration Data Sheet" provided in Appendix C.

7.3.1. Perform confirmation measurements outlined in 7.1 or 7.2 depending on mode of operation.

7.3.2. Record the mean of the three confirmation measurements in the "Distanceold- blank.

7.3.3. Record the old encoder calibration constant (found on line 7 of the FM.DEF file) in the "ConstantOld" blank.

7.3.4. Record the target distance in the "DistanceT argt"blank. For US mode the target distance will be the actual distance traveled. Use Equation 4 to calculate the target distance for Metric mode.

7.3.5. Calculate the new encoder constant using Equation 1.

Equation 1. Calculation for encoder constant.

CONS TANTO1,d

  • DISTANCEO1d

,CONSTANTN,, =,STANCE,,AC, 7.3.6. Record the new encoder constant in the "ConstantNCW" blank.

7.3.7. Update Line 7 of FM.DEF with the new encoder constant.

7.3.8. Perform encoder confirmation in steps 7.1 or 7.2 depending on mode of operation.

SCM PROCEDURE 001, REVS DATE: 917101 PAGE 7 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER

8. Aceptance Criteria 8.1. Acceptance Criteria for US mode 8.1.1. Calculate the mean of the three measurements and ensure that it is within 1% of the actual distance traveled by the SCM.

8.1.2. Calculate the percent deviation from the mean for each of the three measurements using equation 2 and ensure that the deviation for each measurement is below 3%.

Equation 2. Calculation for percent deviation from the mean.

D MeanifCh - Measurementin~h Deviation%= Mean,,Ch 8.1.3. Record the mean and percent deviation from the mean for each measurement on the "Incremental Encoder Calibration Verification Data Sheet for Use in Inch Mode" provided in Appendix A.

8.1.4. If the deviation from the mean is larger than 3% for any measurement, repeat the confirmation test or troubleshoot encoder system.

8.1.5. If the mean of the three measurements differs from the actual distance by more than 1%, proceed to 7.3 and perform calibration.

8.2. Acceptance Criteria for Metric mode 8.2.1. Convert the Actual Distance in meters to Target Distance in inches using Equation 4. Equation 3 provides the derivation.

Equation 3. Target distance in inches derivation.

'Target~stance 100"cm imeter

= ActualDistanceerX 2 iTargetDistancejh¢ x Xinch/piz;l i m cm I pixel Equation 4. Calculation of target distance in inches.

TargetDistance.nc = ActualDistanceei, X40imchimeter-8.2.2. Record target distance on the form "Incremental Encoder Calibration Verification Data Sheet for Use in Metric Mode" provided in Appendix B.

8.2.3. Record the mean and percent deviation from the mean for each measurement on the "Incremental Encoder Calibration Verification Data Sheet for Use in Metric Mode" provided in Appendix B.

8.2.4. Calculate the mean of the three measurements and ensure that it is within 1% of the target distance.

SCM PROCEDURE 001, REV6 DATE: 917101 PAGE 8 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER Equation 5. Calculation for percent deviation from the mean for metric mode.

Deviation, = Meanich - Measuremeftffl 8.2.5. Calculate the percent deviation from the mean for each of the three measurements using Equation 5 and ensure that the deviation for each measurement is below 3%.

8.2.6. If the deviation from the mean is larger than 3% for any measurement, repeat the confirmation test or troubleshoot encoder.

8.2.7. If the mean of the three measurements differs from the target distance by more than 1%, proceed to 7.3 and perform calibration.

9. References 9.1. NIA
10. Required Records 10.1. Incremental Encoder Calibration Verification Form 10.2. SCM Procedure 011, "Survey Naming Convention when Using the SCM"
11. Appendices 11.1. Appendix A: Incremental Encoder Calibration Verification Data Sheet for Use in Inch Mode 11.2. Appendix B: Incremental Encoder Calibration Verification Data Sheet for Use in Metric Mode 11.3. Appendix C: Encoder Calibration Data Sheet

SCM PROCEDURE 001, REV6 DATE: 9/7101 PAGE 9 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER Appendix A Incremental Encoder Calibration Verification Data Sheet for Use in Inch Mode

SCM PROCEDURE 001, REV6 DATE: 917101 PAGE 10 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER Inch Mode Incremental Encoder Calibration Vetification Fonn DATE: SCM SERIALNUMBER:

SCM SPEED: ACTUAL INISEC DISTANCE: IN No;teA6i.g'<:^'Perfgii.hi~f' ; ttr~e ;Xntxnde suve speev'ne>.;< f6thXs:uveXspe$ d isve, Table 3. Strip lengths.

MEASUREMENT DISTANCE (INCHES) DEVIATION FROM MEAN (%)

I 2

3 MEAN XXXXXXXX MEAN VARIANCE FROM ACTUAL DISTANCE:  %

INITIALS MEAN VARIANCE FROM ACTUAL DISTANCE LESS THAN 1%

INITIALS DEVIATION FROM MEAN FOR EACH MEASUREMENT WITHIN 3% OF THE ACTUAL MEASUREMENTS INITIALS PASSED INITIALS FAILED WHY:

PERFORMED BY: DATE:

REVIEWED BY: DATE:

SCM PROCEDURE 001, REV6 DATE: 9/7101 PAGE 11 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER Appendix B Incremental Encoder Calibration Verification Data Sheet for Use in Metric Mode

SCM PROCEDURE 001, REV6 DATE: 9/7101 PAGE 12 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER Metric Mode Incremental Encoder Calibration Verification Form DATE: SCM SERIALNUMBER:

SCM SPEED: INISEC ACTUAL DISTANCE: METERS TARGET DISTANCE: -INCHES Note: P0<Ferfonathis~tet 'at the intended .suirvey speedE ulesth.suhfsre~y spieed s Table 4. Strip lengths.

MEASUREMENT DISTANCE (INCHES) DEVIATION FROM MEAN (%)

I 2

3 MEAN XXXXXXXX MEAN VARIANCE FROM ACTUAL DISTANCE:  %

INITIALS MEAN VARIANCE FROM ACTUAL DISTANCE LESS THAN 1%

INITIALS DEVIATION FROM MEAN FOR EACH MEASUREMENT WITHIN 3% OF THE ACTUAL MEASUREMENTS INITIALS PASSED INITIALS FAILED WHY:

PERFORMED BY: DATE:

REVIEWED BY: DATE:

SCM PROCEDURE 001, REV6 DATE: 9/7/01 PAGE 13 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER Appendix C Encoder Calibration Data Sheet

SCM PROCEDURE 001, REV6 DATE: 917101 PAGE 14 OF 14 TITLE: CONFIRMATION AND CALIBRATION OF THE INCREMENTAL ENCODER Encoder Calibration Form DATE: - SCM SERIALNUMBER:

SCM SPEED: INISEC ACTUAL DISTANCE: INCH DISTANCE 0 w INCH (MEAN OF 3 DISTANCE MEASUREMENTS): -

CONSTANTw, PULSEIINCH (LINE 7 OF FM.DEF):

DISTANCETzcs INCH (US -ACTUAL DISTANCE I METRIC -TARGET DISTANCE):

ConstantOld

  • DistanceOld Constant,,,- = .

TargetDistance CONSTANTw,: .

INITIALS LINE 7 OF FM.DEF UPDATED WITH CONSTANT,,w INITIALS PERFORM ENCODER CONFIRMATION INITIALS _ PASSED IMlIralI Faii =n wuv-PERFORMED BY: DATE: _

REVIEWED BY: __DATE:

Control Copy __

Shonka Rcscarch Associates, Inc.

4939 Lower Roswell Road, Suitc 106 Marietta GA 30068 770-509-7606 Surface Contamination Monitor SCM Procedure 005, Rev6 Requirements for Completion of a Survey Using the SCM

SCM PROCEDURE 005, REV6 DATE: 7117/03 PAGE 2 OF 9 TITLE: REQUIREMENTS FOR COMPLETION OF A SURVEY USING THE SCM Table A 1. Revision Table REVIEWED REVIEWED BYAU S BRIEF

SUMMARY

OF REVISION AUTHOR(S) CHANGES REVIEWER(S) DATE Updated responsibility section, general typos, made 005 M. Marcial 9/7/01 references to response and daily checks uniform, added reference to SCM Procedure 006 and 011.

Added text that references 006 J. Kelley D. DeBord 7/17/03 the MDCs set for by the

. K. client to sections 4.1 and 7.4.5 QA REVIEW BY: D. SHONKA DATE:

IQg AWAA)- 7/17/03 EFFECTIVE DATE: 7/17/03

SCM PROCEDURE 005, REV6 DATE: 7/17103 PAGE 3 OF 9 TITLE: REQUIREMENTS FOR COMPLETION OF A SURVEY USING THE SCM

1. Purpose This procedure details the requirements for completion of a survey using the SCMl.
2. Scope and Limitations This procedure applies to version 2.0 or later of the SCM process software.
3. Definitions and Acronyms Table 1. Definitions and Acronyms.

ITEM DESCRIPTION l The Surface Contamination Monitor is a mobile platform SCM icontaining detectors, support electronics, and data logger used for conducting radiological surveys.

Survey Information Management System - SIMS is flexible and I comprehensive interfacing software for the SRA SCM. SIMS processes the SCM instrument data with a sophisticated data parser, integrated spreadsheet, and powerful special functions such SIMS 'as spatial data filters. SIMS provides the most flexible reporting system available for printing survey records or complete stand-alone survey reports. SIMS contains all the tools needed to meaningfully communicate between the SCM and the data analysisX team.

Position Sensitive Proportional Counter - This is a radiation I detector that is capable of establishing where alongithe detector a pulse is sensed (the system is described in NUREGCR-6450).

PSPC The detectors are similar in efficiency to other counters, but have backgrounds associated with small area detectors (5cxm5crn)._ _

This results in improved sensitivity, due to low background, and specific identification of the location of the radioactivity. The PSPCs may be fabricated in any length.

Source Response Check - Determines if the system is operating the!

same from day-to-day. J Performance Based Check - Determines the system efficiency and l PBC performance.

SCM PROCEDURE 005, REV6 DATE: 7/17103 PAGE 4 OF 9 TITLE: REQUIREMENTS FOR COMPLETION OF A SURVEY USING THE SCM

4. General Information 4.1. Rolling Mode Check the wheel encoder upon arrival on site per "SCM Procedure 001". Check the PSPC per "SCM Procedure 007".

The Project Manager establishes the survey speed based on the isotopes of concern and the desired sensitivities set forth by the client. The SCM system is capable of concurrent alpha, beta and gamma surveys.

An SCM survey uses the concept of survey strips. SIMS reassembles the strips to provide complete documentation of a survey without requiring any manual transfer of data. The operator makes a crude sketch of the area and indicates the direction and start point of each strip. Record the filename of the survey on the sketch and, if available, note a reference coordinate for one of the comers of the survey area. The surface does not need to be pre-gridded. Mark the surface into survey lanes using a chalk line or other markings. The wheel encoder enables tracking of distance down each lane.

Markings on the detector housing allow the operator to align the detector to the lane.

Each lane is twice as wide as the detector. Typical survey lanes are about 12 feet wide.

Start the SCM software if it is not already active and enter the survey parameters:

  • Survey Name (Filename),
  • Room ID, and
  • Equipment ID.

Use the speed indicator on the computer display to adjusted to the proper survey speed.

After establishing the speed, disengaged the motor and positioni the SCM with the. front of the first PSPC at least 10 cm before the start of the first survey lane. Start the motor and begin logging data as the leading edge of the first PSPC enters the survey lane by pressing the <Record> button. The motor maintains a constant speed, while the- .

operator guides the cart down the lane unless using the fly-by-wire or autonomous carts. Upon reaching the end of the lane, press the <Stop> button on the SCM screen and optionally disengaged the motor. Position the cart to record the next lane. Repeat this process until completing the survey.

Change the filename and optionally the Room ID to prepare the instrument for the next survey area. The display provides infonnation during the survey process, such as, survey name, strip number, distance traveled in strip, target speed and current speed, alarm set points, and detector data. Two different display types for the detector data exist in the SCM process software. For a pixilated image of the flux from the floor with color corresponding to intensity, select the visualization screen. For a more

SCM PROCEDURE 005, REV6 DATE: 7117103 PAGE 5 OF 9 TITLE: REQUIREMENTS FOR COMPLETION OF A SURVEY USING THE SCM traditional feel, select the bar graph screen that has rows corresponding to roughly 4-inch bins across the detector. Thle system also provides visual and audible alarms to the user to indicate problems with operating parameters such as speed. The SCM logs data to the disk drive from any combination ofthe detectors while the <Record> key is active. This permits reassembly of the data in the SIMS application.

4.2. Corner Mode Use the comer detector operated in a data-logging mode to survey areas not accessible with the SCM attached to the motor driven cart. The output of comer mode is compatible with SIMS. The comer detector is a PSPC operated in a similar fashion to the SCM rolling survey, but with a fixed time interval for each detector placement and data acquisition. The Project Manager establishes the time interval to provide a sensitivity that is consistent with that established for the rolling mode.

Measure out 10 cm strips along the surface being measured. Start the SCM softvare if it is not already active and enter the survey parameters: Survey Name (Filename),

Room ID, and Equipment ID. Position the detector between the first set of marks and press <Record> button in the SCM process softvare. At the end of the preset time interval, the system stops recording. Move the detector into the next position, and record the next strip. Repeat this process until completing the survey.

5. Materials, Equipment, and Supplies Table 2. Materials, Equipment, and Supplies.

I ITEM i SPECIFICATION ISCM Mvodel 3 l SCM Process SoftwvLre Version 2.0 or later P.SPC jTypical lengths include 0.9 and 1.8 meter

' Tape Measure 3 0 ft. 10 m, or longer f_ . .. ...-.. .

':Chalk Line 1_30 ft. I10 m, or longer depending on survey lane length '

i- -- _ _ _ _ _

.i Check Source 1 Alpha, beta or gamma as appropriate

6. Responsibilities 6.1. Project Manager 6.1.1. Reads and becomes familiar with this procedure.
6. 1.2. Ensures all surveys are perfori-ed according to this procedure.

SCM PROCEDURE 005, REV6 DATE: 7117103 PAGE 6 OF 9 TITLE: REQUIREMENTS FOR COMPLETION OF A SURVEY USING THE SCM 6.1.3. Establishes the rolling mode speed and detector height.

6.1.4. Establishes the comer mode count time and detector height.

6.2. Operator 6.2.1. Reads and becomes familiar with this procedure before performing calibration.

6.2.2. Performs all surveys according to this procedure.

6.2.3. Operates the SCM during the survey.

6.2.4. Guides and monitors the SCM's speed throughout the surveys.

6.2.5. Has successfully completed SCM I training.

7. Procedure 7.1. SCM Preparation 7.1.1. Remove the protective cover from the detector housing.

7.1.2. Set the detector housing to the proper height for the survey.

Perform alpha surveys with the detector set at 1/4" above the surface or as directed by the Project Manager. Beta surveys may vary from 1/4" to 3/4" depending on the isotope. Verify the setting with the Project Manager.

7.1.3. Set the high voltage control on the electronics module to "Alpha" for alpha surveys and "Beta" for beta surveys.

7.1.4. Power on the GM Rate Meter, if conducting a concurrent GM survey.

7.1.5. Purge the detector and insure that P-1O gas flow is indicated on the outlet flow gauges.

7.1.6. If this is the initial project survey, perform steps 7.2; else proceed to step7.3.

7.2. Confirmation of Operation (Performed at beginning of project and as required by referenced procedures) 7.2.1. Launch SCM process software.

7.2.2. Verify PSPC position response. In addition, if required, perform a position calibration in accordance with "SCM Procedure 006".

SCM PROCEDURE 005, REV6 DATE: 7117/03 PAGE 7 OF 9 TITLE: REQUIREMENTS FOR COMPLETION OF A SURVEY USING THE SCM 7.2.3. Perform encoder calibration per "SCM Procedure 001". Perform the encoder calibration at the beginning of each project, and after maintenance affecting the encoder wheel.

7.3. Survey Setup 7.3.1. If this is the beginning of a shift, perform PSPC daily source response check (SRC) per "SCM Procedure 007". Perform the SRC at the beginning of each shift. Perform periodic performance based response checks (PBC) during the survey in accordance with "SCM Procedure 007".

7.3.2. Make a crude sketch of the survey area including distances, if a CAD drawing is not available.

7.3.3. Identify and mark survey lanes using a tape measure and chalk line or other markings.

7.3.4. Indicate strip locations and directions on sketch with arrows.

7.3.5. Record the filename of the survey on the sketch.

7.3.6. Identify SW corner on drawing and if available provide a reference coordinate.

7.4. Rolling Survey Operations 7.4.1. When prompted, enter a survey name and record the name on the sketch. See "SCM Procedure 011" for survey naming conventions.

7.4.2. Confirm the PSPC detector in the "Supervisor/Select Detectors" screen.

7.4.3. Confirm the operation mode is set to "Encoder".

7.4.4. Return to the operations screen.

7.4.5. Set the survey speed in the "Operator/Alarm Set Points" screen.

Survey speed for alpha surveys is normally I"/sec. Beta survey speeds may vary from 2"/sec. to 6"/sec. Verify the speed for-the - - -

survey with the Project Manager who will determine one that meets the survey MDCs.

7.4.6. Engage the motor and adjust the speed.

7.4.7. Disengage the motor.

7.4.8. Select the "Visualization" Screen.

7.4.9. Position the SCM with the front of the first PSPC at least 10 cm before the start of the first survey lane.

7.4.10. Start the motor and begin logging data as the leading edge of the first PSPC enters the survey lane by pressing the <Record> button.

SCM PROCEDURE 0051 REV6 DATE: 7117103 PAGE 8 OF 9 TITLE: REQUIREMENTS FOR COMPLETION OF A SURVEY USING THE SCM 7.4.1 1. Guide the SCM down the strip.

7.4.12. Upon reaching the end of the strip, disengage the motor.

NOTE:

Any deviationfrom the survey lane (strip pathi) will result in errors in the mnapping of strface activity.

7.4.13. Press the <Stop> button on the operations screen.

7.4.14. Position the detector at the beginning of the next strip aligning the markings on the detector housing with the chalk lines on the floor.

The detector housing is typically marked 10cm from each end.

7.4.15. Repeat steps 7.4:9 to 7.4.14 for all strips in the survey.

7.4.16. Perform performance based checks in accordance with "SCM Procedure 007".

7.5. Comer Detector Operations 7.5.1. Use the Corner detectors to acquire data in areas that are normally not accessible to the SCM used with the motor driven cart.

7.5.2. Set up of the corner detectors for binning constants, high voltage settings, and baseline source response checks is the same as other PSPCs.

7.5.3. Confirm the operation mode is set to "Comer".

7.5.4. Set the timer for the time necessary to obtain count times consistent with the speed of the motor driven SCM for the same area. The timer should be set for a value eqcual to the width of the detector, typically 10 cm, divided by the travel speed. Verify the timer setting with the Project Manager.

7.5.5. If a survey name has not been provided, enter a survey name that reflects the area (consistent with the survey name used with the motor driven cart). The "SCM Procedure 011" details the naming of surveys.

7.5.6. Draw a sketch of the area, if a CAD drawing is not available.

7.5.7. Denote the location of each strip taken with the corner detector, including any overlaps with other strips.

7.5.8. Press the <Enter> key on the keyboard or press the remoted pendant <Record> button to acquire a strip. The count will complete at the end of the preset time.

SCM PROCEDURE 005, REV6 DATE: 7/17103 PAGE 9 OF 9 TITLE: REQUIREMENTS FOR COMPLETION OF A SURVEY USING THE SCM 7.5.9. Perform performance based checks in accordance with SCM Procedure 007.

8. Acceptance Criteria None - Specific procedures provide acceptance criteria for calibration activities.
9. References 9.1. SCM Procedure 001 "Confirmation and Calibration of the Incremental Encoder on Encoder Equipped Models of the SCM".

9.2. SCM Procedure 007 "Source Response Check and Performance based Checks of any PSPC Detector Configuration Installed on the SCM".

9.3. SCM Procedure 008 "Conduct of Operations for Surveys Using the SCMISIMS". SCM Procedure 011 "Survey Naming Convention when Using the SCM".

10. Required Records All data acquired during the survey is transferred to SIMS for processing. The "SCM Procedure 008" details the maintenance of all survey records.
11. Appendices N/A

Iq 14L-CA mMe14 X J /7 Control Copy __

Shonka Research Associates, Inc.

4939 Lower Roswell Road, Suite 106 Marietta GA 30068 770-509-7606 Surface Contamination Monitor SCM Procedure 006, Rev4 Performance of a Position Calibration on a PSPC

SCM PROCEDURE 006, REV4 DATE: 917101 PACE 2 OF 6 TITLE: PERFORMANCE OF A POSITION CALIBRATION ON A PSPC TableA 1. Revision Table REVIEWED BY: D. DEBORD BRIEF

SUMMARY

OF REVISION AUTHOR(S) CHANGES REVIEWER(S) DATE 004 M. Marcial 9f l01 Added cover sheet and revision sheet.

QA REVIEW BY: D. SHONKA DATE:

, a 9/7/01 EFFECTIVE DATE: 917/01

SCM PROCEDURE 006, REV4 DATE: 917101 PAGE 3 OF 6 TITLE: PERFORMANCE OF A POSITION CALIBRATION ON A PSPC

1. Purpose This procedure details the requirements for performing a position calibration of a PSPC detector array.
2. Scope and Limitations This procedure applies to version 2.0 or later of the Surface Contamination Monitor process software.
3. Definitions and Acronyms Table 1. Definitions and Acronyms.

ITEM DESCRIPTION

. The Surface Contamination Monitor is a mobile platform containing SCM I detectors, support electronics, and data logger used for conducting i radiological surveys. .

Survey Information Management System - SIMS is flexible and comprehensive interfacing software for the SRA SCM. SIMS processes the SCM instrument data with a sophisticated data SIMS parser, integrated spreadsheet, and powerful special functions such as spatial data filters. SIMS provides the most flexible reporting system available for printing survey records or complete stand-alone survey reports. SIMS contains all the tools needed to meaningfully communicate between the SCM and the data analysis team.

1 Position Sensitive Proportional Counter - This is a radiation detector that is capable of establishing where along the detector a I i pulse is sensed (the system is described in NUREG/CR-6450). The PSPC l detectors are similar in efficiency to other cbunters, but have PP backgrounds associated with small area detectors (5cm x 5cm).

!Thisresults in improved sensitivity, due to low background, and specific identification of the location of the radioactivity. The manufacturer of PSPCs makes them in any length.

diTe channel that is halfway between the maximum and minimum of I Peak Edg , the peak on the side of the peak facing the nearest MHV connector. I

...._J

4. General Information The design of the SCM acquisition system allows several detector configurations. To this end, the acquisition engine and software provides for adjustments to allow for the differences between the attributes of the different detector configurations. The most important of these adjustments is the position calibration.

SCM PROCEDURE 006, REV4 DATE: 917101 PAGE 4 OF 6 TITLE: PERFORMANCE OF A POSITION CALIBRATION ON A PSPC The position calibration allows the software to take the recorded information by the The position calibration allows the software to take the recorded information by the acquisition system and map it to a position on the detector.

5. Materials, Equipment, and Software Table 2. Materials, Equipment, and Software.

ITEM SPECIFICATION SCM Model 3 SCM Process Software Version 2.0 or later PSPC Typical lengths include 0.9 and 1.8 meter A......_..... . .. ~....................................... . ... . _................... .. ...... ......

Check Source Collimated alpha source or other source if collimated alpha

. is not available STITCHER Version 3.0 or later VISUSPECT Version 3.0 or later

6. Responsibilities 6.1. Operator 6.1.1. Reads and becomes familiar with this procedure before performing calibration.

6.1.2. Performs all measurements according to this procedure.

6.1.3. Has successfully completed SCM I and SCM II Training.

7. Procedure 7.1. Perform Confirmation of Position Calibration 7.1.1. Connect a pre-amp module to each end of the detector array.

7.1.2. Place the source at the end of the intended active area of the array.

7.1.3. Press the <Acquire> button in the SCM process software to start a one-minute acquisition.

7.1.4. Verify that the peak occurs at the outer edges of the display screen.

7.1.5. If the peak does not occur at the outer edge'of the display, perform steps 7.2.

7.1.6. Repeat steps 7.1.2 to 7.1.5 for the left end of the intended active area of the array.

7.1.7. Return to the operations screen.

SCM PROCEDURE 006, REV4 DATE: 917101 PAGE 5 OF C TITLE: PERFORMANCE OF A POSITION CALIBRATION ON A PSPC 7.2. Set Binning Constants 7.2.1. Press the <Setup> button.

7.2.2. Press the <Supervisor> button.

7.2.3. Press the <Calibrations> button.

7.2.4. Press the <Detector Position> button.

7.2.5. Enter the position analyzer by pressing <Use Position Analyzer>

button.

7.2.5.1. Edit Detector Binning Constants using the following steps:

7.2.5.2. Place a high-count rate, collimated alpha source at the far left end (as you are looking at the detector from the operator's position). When using a recount detector, place the source at the left end of the primary (rear) detector. Detector ends are normally marked with tape and are inboard of the MHV connectors. Typically, detector ends are 10 cm from the outside edge of the PSPC.

7.2.5.3. Press the (Binning Constants) button.

7.2.5.4. Press the <L> button to start an acquisition. This function positions the cursor near the left peak.

7.2.5.5. Use the left or right arrows as necessary to position the cursor at the peak edge.

7.2.5.6. When the cursor is set, move the source to the right end of the detector. For a recount assembly, place the source under the left edge of the recount (front) detector.

7.2.5.7. Press the <L> button again to set the left channel. This action causes the cursor to move to the right peak.

7.2.5.8. Use the left or right arrows as necessary to position the.

cursor at the peak edge.

7.2.5.9. Press the <R> button to set the right channel.

7.2.5.10. Press the <ESC> key to return to the position analyzer screen.

7.2.6. The computer will calculate the slope and intercept using the left and right channels identified by the peaks.

7.2.7. If the detector array contains more than I detector, perform step 7.3.

7.3. Set Detector Endpoints using the Following Steps:

7.3.1. Press the <Acquire> button to start a one-minute acquisition.

7.3.2. Move a high-count rate, collomated alpha source to each end of each detector.

SCM PROCEDURE 006, REV4 DATE: 917101 PAGE 6 OF 6 TITLE: PERFORMANCE OF A POSITION CALIBRATION ON A PSPC 7.3.3. Record the peak edge of each peak.

7.3.4. Press the <Quit> button to exit the position analyzer.

7.3.5. Press the <Set Detector End Points> button to edit the detector endpoints.

7.3.6. Enter the endpoint for each detector.

7.3.7. Press the <Save> button.

7.3.8. Press the <Return to Operations> button.

8. Acceptance Criteria End point verification indicates that the peak from the collimated source appears at the outer edges of the computer display screen.
9. Appendices 9.1. None

Control Copy # -

Shonka Research Associatcs, Inc.

4939 Lowcr Roswcll Road, Suitc 106 Marietta GA 30068 770-509-7606 Surface Contamination Monitor SCM Procedure 007, Rev7 Source Response Check and Perfonnance Based Check of any PSPC Detector Configuration Installed on the SCM

SCM PROCEDURE 007, REV7 DATE: 7117103 PAGE 2 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON THE SCM Table A 1. Revision Table REVIEWED BY: D. DEBORD REVISION AUTHOR(S) CHANGES REVIEWER(S) DATE Added cover sheet, revision sheet, Project Manager responsibilities, made uniform the naming of checks and added reference 006 M. Marcial 9/7/01 SCM Procedure 011. Added sigma evaluation to acceptance criteria. Quality Control >> Performance Based Added action upon failure to meet acceptance criteria.

Section 8.1.2 and 8.2.1 007 J. Kelley D. DeBord 7/17/03 include the changes. In step 7.1.10 the steps to repeat are 7.1.7 to 7.1.9 not 7.1.5 to 7.1.7. Formatting was added to section 8.

QA REVIEW BY: D. SHONKA DATE:

{I ( 7/17103 EFFECTIVE DATE: 7/17/03

SCM PROCEDURE 007, REV7 DATE: 7117103 PAGE 3 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON THE SCM

1. Purpose This procedure details the requirements for baseline source response checks (SRC),

daily SRCs and Performance Based Checks (PBC) of any PSPC detector configuration installed on the SCM.

2. Scope and Limitations This procedure applies to version 2.0 or later of the SCM process software.
3. Definitions and Acronyms Table 1. Definitions and Acronyms.

ITEM DESCRIPTION The Surface Contamination Monitor is a mobile platform SCM containing detectors, support electronics, and data logger used for conducting radiological surveys.

Survey Information Management System - SIMS is flexible and j comprehensive interfacing software for the SRA SCM. SIMS processes the SCM instrument data with a sophisticated data parser, integrated spreadsheet, and powerful special functions such SIMS as spatial data filters. SIMS provides the most flexible reporting system available for printing survey records or complete stand-alone survey reports. SIMS contains all the tools needed to meaningfully communicate between the SCM and the data analysis

..team.

iPositionSensitiveProportionalCounter-Thisisaradiation l detector that is capable of establishing where along the detector a pulse is sensed (the system is described in NUREG/CR-6450).

PSPC The detectors are similar in efficiency to other counters, but have backgrounds associated with small area detectors (5cm x 5cm).

This results in improved sensitivity, due to low background, and specific identification of the location of the radioactivity. The PSPCs may be fabricated in any length.

Source Response Check - Determines if the system is operating the same from day-to-day.

Performance Based Check - Determines the system efficiency and I performance.

.. L_.._._.................... ._

SCM PROCEDURE 007, REV7 DATE. 7117103 PAGE 4 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON THE SCM

4. General Information Normal operation of the SCM with a PSPC requires daily SRCs to assure that the PSPC is performing within acceptable limits. Perform this procedure at the beginning and end of each shift for each detector in use. Compare the results to the results of the daily SRC to the baseline SRC for this project. Use the initial daily SRC for a project as the baseline SRC.

Any time a system parameter changes, take a new baseline SRC for comparison with proceeding days. Examples of altered parameters would be:

1. Change in high voltage.
2. Calibration source changed.

Perform Performance Based Checks (PBC) frequently through out the course of the survey. The PBCs establish the system performance during the survey and are the basis for the detector efficiency. Moreover, the PBCs affect the reported surface activity output by SNMS.

5. Materials, Equipment, and Supplies Table 2. Materials, Equipment, and Supplies.

ITEM SPECIFICATION I SCM Model 3 l SCM Process Software Version 2.0 or later PSPC

_ Typical lengths include 0.9 and 1.8 meter NIST traceable source for PBCs used to establish I efficiency. Use the same source for all comparisons Check Source i between the baseline SRC and the daily SRC (need not be NIST traceable).

6. Responsibilities 6.1. Project Manager 6.1.1. Reads and becomes familiarwith this procedure.

6.1.2. Evaluates SRCs that fail the acceptance criteria.

6.2. Operator 6.2.1. Reads and becomes familiar with this procedure before performing calibration.

6.2.2. Performs all measurements are according to this procedure.

6.2.3. Has successfully completed SCM Level I training.

SCM PROCEDURE 007, REV7 DATE: 7117103 PAGE 5 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON THE SCM

7. Procedure 7.1. Source Response Check Measurement.

7.1.1. If this is a baseline SRC, use the form in Appendix A, "Baseline Source Response Check Form"; otherwise, use the form in Appendix B, "Daily Source Response Check Form". Use this procedure for all detectors regardless of configuration. Perform all source response checks with the detector and source stationary. If desired, use a source holder so that the placement of the source to the detector is repeatable.

7.1.2. Enter the Energy/Position analyzer by following these steps:

7.1.2.1. Press the <Setup> button.

7.1.2.2. Press the <Supervisor> button.

7.1.2.3. Press the <Calibrations> button.

7.1.2.4. Press the <Detector Position> button.

7.1.2.5. Press the <Use Position Analyzer> button.

7.1.3. Make sure that there are no sources under the detector.

7.1.4. Start Acquisition by pressing the <Acquire> button.

7.1.5. When the i-minute timed acquisition ends, integrate the entire spectrum and record the measured background for the entire spectrum.

7.1.6. Record the measured background on the appropriate form in the.

column labeled "Total Counts" and the row labeled "Background for Entire Array".

7.1.7. Place calibration source under the center of the detector or in contact with mylar or protective screen. When the SCM is setup for rolling mode, it is often quicker to place the source on the ground and roll the cart to position the source under the detector. When surveying in comer mode, it is often quicker to turn the PSPC over and place the source directly on the mylar or protective screen. In any case, assure that the source to detector geometry is the same as when the baseline SRC was taken.

7.1.8. Start Acquisition by pressing the <Acquire> button.

7.1.9. When the 1-minute count is complete, record the count with calibration source on the data table in the appropriate row for the given detector of the appropriate form in the column labeled "Total Counts".

SCM PROCEDURE 007, REV7 DATE: 7117/03 PAGE 6 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON THE SCM 7.1.10. Repeat Steps 7.1.7-7.1.9 for each detector in the PSPC array.

7.2. Source Response Check Evaluation 7.2.1. For each detector, subtract the recorded background entered in the data table in the row labeled "Background for Entire Array" from the recorded "Total Counts" for each detector. Enter the result in the block "Total Background Subtracted Counts".

Note: If this procedure is being done to establish a baseline, it is now complete.

If this is a comparison to baselinc,proceed to step 7.2.2 7.2.2. Copy values in the column labeled "Total Background Subtracted Counts" from the baseline form for each detector onto the form "Daily Source Response Check Form" in the column labeled "Total Baseline Background Subtracted Counts" provided in Appendix B.

7.2.3. For each detector perform the calculation shown in Equation I and record the value in the block "Percent Difference from Baseline Measurement" on the form in Appendix B.

Equation 1. Calculation of percent difference from baseline.

ITotal Background Subtracted Cotunts -Total Baseline Background Subtracted Corsets 100 x Total Baseline Background Subtractedl Counts 7.2.4. Compare these values with the acceptance criteria contained in Step 8.1.2. If the value is greater than the acceptance criteria, notify the Project Manager.

7.3. Performance Based Check Note: Perform the Petformance Based Check (PBC) with the detectors operatingin the mode iniiwhich the surveys bounded by the PerfornzanceBased Checks will be performed.

7.3.1. Perform periodic PBCs throughout the course of the survey. Perform PBCs at the beginning of the shift, at least once per 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> of surveying, and at the completion of each shift.

7.3.2. Perform all PBCs using the same source. The source used for efficiency determination is acceptable but not required to be used.

7.3.3. Obtain PBCs in the same performance manner as normal surveys, i.e.

SCM speed and detector height, or timer setting and height for comer detectors.

7.3.4. Establish a survey file name for the Performance Based Checks. See SCM Procedure 011 for file naming conventions.

SCM PROCEDURE 007, REV7 DATE: 7117103 PAGE 7 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON THE SCM 7.3.5. Place the source on the floor and perform a survey of the area, operating the SCM in accordance with SRA Procedure 005. For rolling surveys, center the source along the PSPC axis 1.0 m from the leading edge of the first detector before rolling the cart over the source. For comer surveys place source on detector mylar or protective screen.

7.3.6. For corner surveys, press the <Record> button and wait until acquisition is complete. For rolling surveys press record, then start motor. Continue strip until last detector is 1.0 m past the source.

7.3.7. Repeat the survey 3 times for each PBC.

7.3.8. Record the time, filename, strip numbers, and the source used in the logbook or survey form.

7.3.9. Evaluation of the PBCs for the duration of the survey occurs in the survey report issued upon completion of the survey.

8. Acceptance Critera 8.1. SRCs 8.1.1. For baseline SRCs, there is no acceptance criteria.

8.1.2. Daily SRCs are acceptable if all "Percent Difference from Baseline Measurement" values are less than 20%. If a system fails to meet the acceptance criteria, all survey data taken since the last acceptable PBC or SRC will be rejected. Also, the system should be removed from service until the failure is resolved.

8.2. PBCs 8.2.1. Use SIMS software to process the PBC data files. Establish a control chart indicating the mean and "2-sigma" and "3-sigma" values.

Evaluate subsequent PBCs against the "2-sigma" and "3-sigma" criteria and for indications of adverse trends. If more than 1 of the 3 measurements obtained during a PBC is greater than the "2-sigma" or if any measurement is greater than "3-sigma", the PBC fails. Surveys bounded by a failed PBC are considered invalid. If a system fails to meet the acceptance criteria, all survey data taken since the last acceptable PBC or SRC will be rejected. Also, the system should be removed from service until the failure is resolved.

SCM PROCEDURE 007, REV7 DATE: 7117103 PAGE 8 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON THE SCM

9. References 9.1. SCM Procedure 005 "Requirements for Completion of a Survey Using the SCM".

9.2. SCM Procedure 011 "Survey Naming Convention when using the SCM".

10. Required Records None.
11. Appendices 11.1. Appendix A, Baseline Source Response Check Measurements Form 11.2. Appendix B, Daily Source Response Check Measurements Form

SCM PROCEDURE 007, REV7 DATE: 7117103 PAGE 9 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON THE SCM Appendix A Baseline Source Response Check Form e

i

SCM PROCEDURE 007, REV7 DATE: 7117103 PAGE 10 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON THE SCM Baseline Source Response Check Form SCM CONFIGURATION: SCM SERIALNUMBER:

HIGH VOLTAGE SETTING:

SOURCE SERIAL NUMBER OR ID: ISOTOPE:

TOTAL DETECTOR SERIAL NUMBER TOTAL COUNTS BACKGROUND SUBTRACTED COUNTS BACKGROUND FOR ENTIRE NIA NIA ARRAY DETECTOR #1 DETECTOR #2 DETECTOR #3 DETECTOR #4 DETECTOR #5 ENTER NIA FOR ALL NON-EXISTING DETECTORS PERFORMED BY: DATE:

REVIEWED BY: DATE:

SCM PROCEDURE 007, REV7 DATE: 7117103 PAGE 11 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON TalE SCM Appendix B Daily Source Response Check Form

SCM PROCEDURE 007, REV7 DATE: 7117103 PAGE 12 OF 12 TITLE: SOURCE RESPONSE CHECK AND PERFORMANCE BASED CHECK OF ANY PSPC DETECTOR CONFIGURATION INSTALLED ON THE SCM Daily Source Response Check Form

, DAILY SOURCE RESPONSE CHECK CONFIGURATION SCM CONFIGURATION: SCM SERIALNUMBER:

HIGH VOLTAGE SETTING:

SOURCE SERIAL NUMBER OR ID: ISOTOPE:O l BASELINE SOURCE RESPONSE CHECK CONFIGURATION DATE:_

SCM CONFIGURATION: SCM SERIALNUMBER:

HIGH VOLTAGE SETTING:

I SOURCE SERIAL NUMBER OR ID: ISOTOPE:-

TOTAL TOTAL PERCENT SERIAL TOTAL BACKGROUND BASELINE DIFFERENCE DETECTOR NUMBER COUNTS SUBTRACTED BACKGROUND FROM COUNTS U T SUBTRACTED BASELINE COUNTS MEASUREMENT BACKGROUND FOR N/A N/A N/A N/A ENTIRE ARRAY DETECTOR #1 DETECTOR #2 DETECTOR #3 DETECTOR #4 DETECTOR #5 ENTER N/A FOR ALL NON-EXISTING DETECTORS INITIALS_ NO MEASUREMENT VARIES MORE THAN 20% FROM BASELINE INITIALS PASSED INITIALS FAILED WHY:

PERFORMED BY: DATE:

REVIEWED BY: DATE:

Control Copy #

Shonka Research Associates, Inc.

4939 Lower Roswell Road, Suite 106 Marietta GA 30068 770-509-7606 Surface Contamination Monitor SCM Procedure 008, Rev3 Conduct of Operations for Surveys Using the SCM/SIMS

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 2 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS Table A 1. Revision Table REVIEWED BY: D. DEBORD BRIEF

SUMMARY

OF ICHANGES Updated survey documentation control form, added reference to SCM Procedure 01 1.

QA REVIEW BY: D. SHONKA I DATE:

Q2,%\ b I 9/7/01 EFFECTIVE DATE: 97/701

SCM PROCEDURE 008, REV3 DATE: 917)01 PAGE 3 OF 23 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS I.Purpose This procedure establishes guidance and requirements for processing, documenting, and archiving data in support of surveys conducted with the SCM/SIMS.

2. Scope and Limitations This procedure applies to version 2.0 or later of the SCM process software.

This procedure applies to all surveys performed by SRA to fulfill contractual obligations to clients or for in-house use.

This procedure does not apply to the documentation for clients that require use of their own data handling procedures; however, the requirements contained herein may still be appropriate for such instances if they do not conflict with client requirements.

3. Definitions and Acronyms Table 1. 3. Definitions and Acronyms.

ITEM DESCRIPTION The Surface Contamination Monitor is a mobile platform containing SCM detectors, support electronics, and data logger used for conducting

  • .radiological surveys.

Survey Information Management System - SIMS is flexible and c.comprehensive interfacing software for the SRA SCM. SIMS processes the SCM instrument data with a sophisticated data SIMS parser, integrated spreadsheet, and powerful special functions such as spatial data filters. SIMS provides the most flexible reporting I system available for printing survey records or complete stand-alone survey reports. SIMS contains all the tools needed to rneaningfulry

.... communicate between the SCM and the data analysis team.

IA data processing feature of SIMS that allows group processing of Bmultiple survey block files. A group of files may be saved as a Batch Processing File so that the batch may be run again at a later date.

I The DOS directory titled with the Project Name. This directory is

.SIMS Survey used to store all elements of the survey. A-detailed directory Directory structure is identified in this procedure.

SCM PROCEDURE 008, REV3 DATE: 9Ml01 PAGE 4 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS ITEM DESCRIPTION I IPosition Sensitive Proportional Counter -

detector that is capable of establishing where along the detector a This is a radiation i.pulse is sensed (the system is described in NUREG/CR-6450). The.

Idetectors are similar in efficiency to other counters, but have backgrounds associated with small area detectors (5cm x 5cm)

This results in improved sensitivity, due to low background, and specific identification of the location of the radioactivity. The PSPCs may be fabricated in any length.

Contact Sheet . A list of phone numbers and addresses.

iPacking List A detailed list of all items shipped or carried by survey team I . members in support of the survey.

A daily meeting attended by survey team members conducted prior of the Dy .to beginning any work. The meeting serves to assign tasks and Plan einform members of any operations by team members or by other I (PD teams that may affect survey activities. A daily safety meeting should be conducted as part of the Plan of Day meeting.

A detailed description of the contractual requirements for the IScope of W ork s r e ._ _ _ _ _ _ _ _ _ _ _ _ _ _

! survey.

I OOS I Out-of-scope work MSDS Material Safety Data Sheets

.......................... . ...................... Z.. ..................... .. . .. ........

QA I Quality Assurance (SRCs and PBCs) i CAD Computer Aided Design Master Drawing . A diagram, map, or other drawing of the survey areas.

IA daily record of survey activities maintained by the Survey Technician. The logbook contains any observations, problems, or

Logbook l obstacles encountered during the survey. If survey forms are not provided, it may be used to document survey sketches.

A notebook used to organize and provide quick access to logistical.

Survey Notebook E..

. procedural, and administrative survey documentation.

A survey is divided into sections called survey blocks. The size of Survey Block the survey block is typically limited for convenience to 15 meters by 15 meters or 20 meters by 10 meters.

The name assigned to the individual survey blocks. The name should be a valid DOS file name of no more than 8 characters as it Survey Name will be used to archive electronic files. See SCM Procedure 011 for file naming conventions.

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 5 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS ITEM

  • DESCRIPTION Auto Generated
  • Stylized survey records automatically generated by SIMS without I Survey Records operator intervention.

Ato G Text file automatically generated by SIMS without operator Iintervention. This file typically has the Survey Name, highest 100 Survey Table cm2 area, number of meters, number of meters exceeding 100 cm2 l Summary limit, highest microR/hr and PSPC efficiency.

j _.... . .... . .. . ...................... -.-

................................ .i ..

Master Survey A compilation of the Auto Generated Survey Table Summaries for I Table each section of thc survey.

The Survey Report Volume (SRV) serves to catalog the Auto 1 Generated Survey Records. The SRV will consist of one or more binders sectioned with dividers using the same structure as the sub-Survey Report directories in the SIMS data directory. Substitution of CD Volume presentation of the data instead of hard copy files in binders is a client option. The Master Survey Table should appear as the first page and an Auto Generated Survey Table Summary should be the first sheet for each survey section.

The act of reviewing, inspecting, testing, checking, auditing, or otherwise determining and documenting whether items, processes, services, or documents conformn to specified requirements. With

.respect to computer code development, verification is the process of evaluating the products of a software development phase to provide assurance that they meet the requirements defined for them

. by the previous phase. As applied to completed computer codes, verification means to demonstrate the capability of the code to

. produce valid results for test problems encompassing the range of

. permitted usage defined by the code's documentation.

4. General Information Performance of surveys requires designation of the following staff members:
1. Project Manager,
2. Survey Technicians,
3. Office Manager, and
4. Quality Assurance (QA) Reviewer.

The size of the survey dictates the number of Survey Technicians, but for small surveys the Project Manager may assume the responsibilities of the Survey Technician. Persons directly involved with the survey may not serve as Quality Assurance Reviewer.

The Project Manager is responsible for planning, organizing logistics, supervising survey performance, documenting the survey, and processing survey data. The Project Manager is responsible for choosing the methods and procedures needed to complete all

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 6 OF 23 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS deliverable items for the survey, for performing the required tasks, and for documenting the process in a manner that reflects high professional standards.

Survey Technicians are responsible for operation and maintenance of the SCM during the course of the survey. They perform surveys in accordance with SRA and local site procedures. Survey Technicians must complete the SRA training courses required for operation of the SCM. In the event more than one individual is involved in the accumulation of survey data, each individual shall be considered a Survey Technician.

For larger surveys the Project Manager may appoint a Survey Lead Technician. The Survey Lead Technician will assist the Project Manager in supervising and organizing survey activities.

The Office Manger assists the survey team by providing clerical and logistical support.

The Office Manager is responsible for maintaining controlled copies of any documents provided to the client. The Office Manager approves all revisions to any deliverable documents. Additionally, the Office Manager maintains the survey archive upon completion of the final deliverables of the survey. The Office Manager may function at the survey site, the home office, or at a remote location.

The QA reviewer insures completion of all required elements of the survey, that the completed survey is in accordance with all applicable procedures; and addresses all contractual survey items. In addition, the QA reviewer perforrns a final check on deliverable documents to ensure that there are no granummatical, spelling, or punctuation type errors; that page numbering is correct; that all tables agree with Auto Generated Survey Records; that all cross-references are correct; etc. Survey documentation must be completed and ready for delivery (i.e. resolution of comments must be finished) before QA review can take place.

5. Materals, Equipment and Supplies Table 2. Materials, Equipment, and Supplies.

ITEM SPECIFICATION .

SCM . Model 3 ISCM Process Software Version 2.0 or later PSPC. Typical lengths include 0.9 and 1.8 meter SIMS Workstation Capable of running the current version of SIMS SIMS Current Version I Removable Mediai.

Zip Disk or other removable disk media for use with the i

RIOMEGA Zip Drive or compatiable drive.

PKZIP or WINzip (current version) data compression

.FleCompression Software utilities. Software should be capable of creating self-extracting files. ..

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 7 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMSIMS ITEM SPECIFICATION B u H r dSeagate Backup (current version) - utility for transferring data to tape cartridges. Tape cartridges must be compatible S r .with tape drive.

. .. .............. . . ...................... ............................. A.... ............ ..... . _..A..........

Binders 3-ring or other binders for securing loose paper. J Logbooks Suitable for using in the field.

6. Responsibilities 6.1. Project Manager 6.1.1. Has completed SCM Level I and Level II training and SIMS Level I and Level II.

6.1.2. Reads and becomes familiar with this procedure.

6.1.3. Conducts planning of survey logistics and performance requirements.

6.1.4. Determines relevant procedures.

6.1.5. Coordinates survey logistics.

6.1.6. Assembles Survey Notebook.

6.1.7. Ensures that the survey is performed in accordance with SRA procedures.

6.1.8. Reads daily Survey Technician logs and compiles master log.

6.1.9. Distributes and collects daily QA documents.

6.1.10. Conducts daily Plan of Day meeting to each shift.

6.1. 11. Maintains Survey Notebook in accordance with this procedure.

6.1.12. Collects, maintains, and processes survey data using SIMS.

6.1.13. Transfers survey data and documents to Office Manager for storage upon completion of survey.

6.2. Survey Technician 6.2.1. Has completed SCM Level I training at a minimum.

6.2.2. Reads and becomes familiar with this procedure before conducting surveys.

6.2.3. Performs surveys in accordance with this procedure and procedures provided by the Project Manager.

6.2.4. Provides text and diagrams describing survey pattern for each survey block in accordance with this procedure.

6.2.5. Maintains daily logbook in accordance with this procedure.

6.2.6. Performs and documents daily QA checks.

SCM PROCEDURE 008, REV3 DATE: 9/7101 PAGE 8 OF 25 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCM/SIMS -

6.3. Office Manager 6.3.1. Transmits completed report and other deliverables to the client.

6.3.2. Maintains control of deliverable documents throughout the revision process.

6.3.3. Maintains the survey archive in accordance with this procedure.

6.4. Quality Assurance Reviewer 6.4.1. Reads and becomes familiar with this procedure before reviewing survey documentation.

6.4.2. Reviews completed survey documentation to insure completion of all required elements, that the completed survey is in accordance with all applicable procedures, and addresses all contractual items.

7. Procedure 7.1. Pre Deployment Preparation 7.1.1. Designate the Project Manager.

7.1.2. Choose a project name. SIMS uses this name to catalog documents in the SIMS directory structure. The project name should be a single word of no more than 8 characters.

7.1.3. The Project Manager creates a directory on the SIMS workstation using the Project Name.

7.1.3.1. The Project Manager maintains control of the documents in these directories during the course of the survey; however, control transfers to the Office Manager upon completion of the survey.

7.1.3.2. Any of the directories may include sub-directories to organize the stored data. For example, on large surveys a directory may contain multiple sub-directories for separate sections of the survey. The naming convention should aid in identification of the particular areas. For example, use directory names such as exterior, interior, bldgl, elevl, etc.

If using a Survey Identification Code, then use that code as the directory name. Typically, the "_QRaw" and "_SRaw" directories do not have sub-directories. Create at a minimum the following sub-directories under the Project name directory as shown in Table 3. Any references this procedure makes to the directories in Table 3 includes the sub-directories created under them.

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 9 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCM/SIMS Table 3. Directories on SIMS computer.

DIRECTORY NAME USAGE

-QRawStores all SCM Source Response Check and Performance Based Check files transferred from the SCM and not processed by SIMS.

,SRawStores all SCM survey files transferred from the SCM and not

_ a processed by SIMS.

CAD Site drawings and maps.

Admin Time sheets, expense reports, etc.

Correspondence Any correspondence between SRA staff and client.

Documents Completed Auto Generated Survey Records (ASGR) and tables.

This directory contains original AGSRs and tables before they were Documents\Backup revised. Copy original AGSRs here before generating new or revised reports or records. The backup directones should be numbered sequentially.

Data Use this directory to store survey data.

Pictures This directory contains digital images of the site and survey process.

This directory contains any reports or survey records issued internally or to a client. Reports may include status reports, final reports, Reports executive summaries, survey records, etc. Each type of report should have its own directory. For example, all alpha reports could go into the alpha sub-directory.

7.1.4. Develop the survey plan.

7.1.5. Compile a packing list to include both company and personnel items.

Management and all survey team members should review the initial draft. Management and each survey team member should receive a copy of the packing list prior to departure. Use the packing list in Appendix B, "Sample Packing List", as a guide.

7.1.6. Assemble a Survey Notebook as outlined in this section. The Survey Notebook shall contain at a minimum the following sections 7.1.6.1. Contact Sheet - The contact sheet provides an easily accessible list of phone numbers and addresses. Place the sheet on the cover or insert as the first page of the Survey Notebook. Appendix A, "Sample Contact Sheet", lists a sample contact sheet and should contain the following information at a minimum as shown in Table 4.

SCM PROCEDURE 008, REV3 DATE: 917101 PACE 10 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS Table 4. Contact sheet information in Survey Notebook.

ITEM Client phone number and address.

Emergency contact phone numbers for all team members. .

Hotel phone number and address.

Room numbers should be added as they become available.

Local internet access numbers.

Site phone number and address.

A contact number in the event that the notebook is found.

7.1.6.2. Maps and directions.

7.1.6.3. Scope of Work.

7.1.6.4. Safety - The safety section should at a minimum contain the following items as shown in Table 5.

Table 5. Safety Items in Survey Notebook.

ITEM Site Safety Plan.

Applicable MSDS Sheets.

Medical - Includes items such as immunization records, respirator qualification, staff medicines, etc.

7.1.6.5. Procedures - All SRA and site procedures to be used during survey.

7.1.6.6. Source Certification Documentation.

7.1.6.7. Training Records.

7.1.6.8. Packing List.

7.1.6.9. Shipping - The shipping section should at a minimum contain the following items as shown on Table 6.

SCM PROCEDURE 008, REV3 DATE: 9/7101 PAGE 11 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCM/SIMS Table 6. Shipping sheet information.

ITEM Blank Commercial Invoice Blank Shipper's Declaration for Dangerous Goods form Client shipping labels DOT Label with UN number Federal Express Airbill Federal Express Dangerous Goods Airbill Instructions for shipping P- I0 Insurance certificate NON-FLAMMABLE GAS labels SRA shipping labels 7.1.6.10. Parts and Expenses - Envelope for receipts.

7.1.6.1 1. Travel - Reservations, flight information, and envelope for tickets.

7.1.6.12. Backup copies of all software to be used on site.

7.1.7. Ensure that all items on the packing list have been shipped or prepared for transport.

7.2. Deployment 7.2.1. Arrival and Initial Start-up 7.2.1.1. Check in with site contact. Confirm requirements for security and disposition of check sources and P-10 cylinders.

7.2.1.2. Conduct Safety Meeting.

7.2.1.3. Conduct Plan of Day Meeting.

7.2.1.4. The Project Manager should distribute logbooks, initial QA forms, and daily QA forms.

7.2.1.5. Conduct a walk through inspection of the survey area to assess any needed adjustments to the survey plan.

7.2.1.6. Identify a staging area, a secure storage area, and an area to set up data processing (SIMS).

SCM PROCEDURE 008, REV3 DATE: 9)7101 PAGE 12 OF 21 TITLE: CONDUCT OF OPERA7IONS FOR SURVEYS USING THE SCM/SIMS 7.2.1.7. Place all shipped and hand carried equipment into the designated staging area and conduct an inventory check using the Packing List.

7.2.1.8. The Project Manager assembles the SIMS workstation and tests SIMS while the Survey Technicians assemble and perform required QA checks on the SCM(s).

7.2.1.9. As each SCM completes QA checks, the Project Manager will collect and verify the generated QA documentation.

7.2.1. 10. Create a directory titled "C:\FM5\Data\Transfer" in the SCM software directory of each SCM. If the directory already exists, delete its contents.

7.2.1.11. The Survey Team assures the SCM's is ready for field operations and assigns a survey area. The Project Manager ensures the Survey Technician(s) understand the survey naming convention and orientation.

7.2.2. Daily Startup 7.2.2. 1. Conduct Safety Meeting 7.2.2.2. Conduct Plan of Day Meeting 7.2.2.3. Distribute logbooks and daily QA forms.

7.2.2.4. As each SCM completes daily QA checks, the Project Manager collects and verifies its QA documentation.

7.2.3. Daily Survey Activities 7.2.3.1. Survey Technicians perform surveys in accordance with SRA Procedure 005. Direct any questions regarding procedures to the Project Manager.

7.2.3.2. Survey Technicians record in the logbook the sketch of each survey block detailing the pattern used to conduct the survey.

Use arrows to designate the start point, end point and direction of each survey strip. Place an asterisk in the southwest corner (or as designated by the Project Manager) of the survey block to identify the orientation of the survey block in SIMS. If the survey block is not oriented to the cardinal directions, provide another indication of orientation.

7.2.3.3. Maintain the logbook with the following formats as shown in Table 7.

SCM PROCEDURE 005, REV3 DATE: 917101 PAGE 13 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCM/SIMS Table 7. Logbook formats.

ITEM Each day should begin on a new page.

The date should appear in the upper right comer of each page.

Each morning the Survey Technician should note P- l() Gas level, time on site, and action items from the Plan of Day meeting..

The name and start time of each survey block should be noted in the left margin.

If survey forms are not provided, use the logbook to record the survey sketch.

Note any obstacles, problems, or unique observations in the logbook as they occur.

Each recorded observation should include time of day.

7.2.3.4. The Project Manager transfers survey data files from each SCM to SIMS periodically throughout the day. Files should be transferred a minimum of twice a day. Every SCM should participate in each transfer session. The individual file transfers should occur between survey blocks so as not to impede survey efforts. Each transfer should be conducted as shown in Table 8.

Table 8. Transfering data from the SCM to removable media*.

STEP DESCRIPTION 1 Label a floppy disk with each SCM serial number or ID.

2 Exit the SCM software.

3** Using file compression software, create a transfer file that contains all of the Survey Header Files (*.svy) and Survey Data Fles (*.O??) in the SCM directory.

4 Move the transfer file to the floppy disk.

5 Once the transfer file resides on the floppy disk, move all Survey Header Files and Survey Data Files to the "C:\FM5\Data\Transfer" directory.

6 Restart the SCM software and return control to the Survey Technician.

  • Repeat the steps in this table for each SCM.
    • The detector configuration files currently have a similar file extension as the Survey Data Files.

DO NOT transfer or delete the detector configuration files!

SCM PROCEDURE 008, REV3 DATE: 9/7101 PAGE 14 OF 25 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS Table 9. Transfer of data from removable media to SIMS.

STEP DESCRIPTION 1 Using file compression software, extract the Survey Header Files and Survey Data Files from each floppy into the "Data" directory of the SIMS Survey Directory.

2 If a removable media has not been prepared, insert a blank removable media into the removable media drive and create a directory labeled 'Transfer".

3 Copy the Survey Header Files and Survey Data Files from the "Data" directory of the SIMS Survey Directory into the 'Transfer" directory of the removable media. This serves as a temporary archive of survey data.

4 Move the Survey Header Files and Survey Data Files from the "Data" directory of the SIMS Survey Directory into their respective sub directories. Source Response Checks and Performance Based Checks survey files go into the "QRaw" directory. Survey files go into the "_SRaw" directory.

5 Erase the files from the removable media used to transfer SCM data to prepare them for the next file transfer.

7.2.3.5. Print and review Master Survey Table for comparison with reports and survey records.

7.2.3.6. If time and resources permit, compare values in Auto Generated Survey Records with corresponding values on Master Survey Tables.

NOTE: All reports and survey records should be printed and reviewed before demobilization.

7.2.4. Daily Data Processing 7.2.4.1. Update Survey Report Volume.

  • Verify Auto Generated Survey Table Summary (STS File) entries with values in the corresponding individual Auto Generated Survey Records (AGSRs).
  • Place AGSRs into the proper sections of the Survey Report Volume.
  • Place an updated copy of the Master Survey Table at the beginning of the Survey Report Volume.

7.2.4.2. Complete any outstanding data transfers.

7.2.4.3. Move completed Auto Generated Survey Records to the "Documents" directory.

SCM PROCEDURE 0051 REV3 DATE: 917101 PACE 15 OF 23 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS 7.2.4.4. Consolidate any tables created by Batch Processing into the Master Survey Table.

7.2.4.5. Process outstanding data files as described in Table 10.

Table 10. Steps to process data files.

STEP DESCRIPTION I Draw the survey block on the Master Drawing if available.

2 Label the grid with the Survey Name and place an asterisk in the lower left comer of the survey block as viewed in SIMS if available. The lower left comer typically represents the southwest comer.

3 Using SIMS and the survey sketch stitch the survey.

4 Repeat steps 1 through 3 for all transferred survey files.

5* Batch process Auto Generated Survey Records and tables for all recently stitched surveys. Apply appropriate background values to activity limits if backgrounds have been calculated.

6 Move completed Auto Generated Survey Records to the "Document" directory.

7 Consolidate any tables created by Batch Processing into the Master Survey Table.

8** Print and review Master Survey Table.

9 If time and resources permit, print any unprinted Auto Generated Survey Records.

10 If time and resources permit, compare values in AGSRs with corresponding values on Master Survey Tables.

  • The SIMS Batch Processor writes the auto-generated tables to the directory in which the Batch Processing File is stored.
    • AIl reports and survey records should be printed and reviewed before demobilization.

7.2.5. Revision of Auto Generated Survey Records 7.2.5.1. Create a backup sub-directory in the relevant "Document" directory.

7.2.5.2. Move current version of Auto Generated Survey Records into the backup directory. The backup directories should be numbered sequentially.

7.2.5.3. Follow steps 5 through 8 in Table 10 to regenerate records.

7.3. Post Deployment 7.3.1. Records

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 16 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS 7.3.1.1. The Office Manager maintains all controlled copies of any final record, report or executive summary.

7.3.1.2. The Office Manager may revise any controlled copies. The Office Manager distributes any revised document to the survey team members for comments.

7.3.1.3. Upon completion of the final revision, the Office Manager presents the report and other deliverables to the QA Reviewer for verification.

7.3.1.4. After QA approval of the report, the Office Manager conveys the report and other deliverables to the client.

7.3.2. Survey Archive 7.3.2.1. Upon completion of all reports, the Project Manager turns over all survey documentation and materials to the Office Manager.

7.3.2.2. The Office Manager places all finalized material into the survey archive that includes at a minimum the items shown in Table 11.

Table 11. Materials turned over and archived.

ITEM Logbook(s)

SIMS Software SIMS Survey Directory Master Drawing and other site drawings  ;

Contract paper work Survey Notebook Survey Report Volume (ie. printouts of Auto Generated Survey Records)

Video Tape(s), if taped Computer media containing survey data file backup Copies of any other paper work provided to the client 7.3.2.3. The SIMS Survey Directory should be archived to backup tape.

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 17 OF 23 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCM/SIMS 7.3.2.4. Secure all of the items listed in Table 11, the backup tape of the SIMS Survey Directory, and any other documentation pertaining to the survey in a document storage box labeled with the Project Name and date.

7.3.2.5. After QA review, the box should be stored in accordance with office document archive procedures.

7.3.2.6. Place a sign out sheet in the box. Log any removal of any material from the box.

7.4. Quality Assurance Review 7.4.1. As soon as is practical following the receipt of a survey for review, the Quality Assurance reviewer shall:

7.4.1.1. Verify general grammar, spelling, punctuation, etc. for correctness.

7.4.1.2. Verify that statements are clear and precise.

7.4.1.3. Recalculate numerical problems to insure that no "calculator type" errors have occurred (this includes verification of spreadsheet cell formulas).

7.4.1.4. Verify that all assumptions are clearly documented and are valid.

7.4.1.5. Verify that data tables are correct, valid and that table entries are consistent with the data from the Auto Generated Survey Records.

7.4.1.6. Verify that the survey documentation contains all of the information necessary for complete reconstruction at a later date.

7.4.1.7. Verify that the SIMS Survey Directory matches what was archived on the tape backup.

7.4.2. Upon full completion of the QA review, hold a meeting with the Project Manager and Office Manager to discuss comments and resolve issues if necessary.

7.4.3. Upon receipt of a revised survey, the QA reviewer shall first ascertain the scope of the revisions (major or minor).

7.4.4. If only minor edits (those that do not affect results or conclusions) have been made, then QA review should consist of a read through of the documentation to insure that the changes made were appropriate and that no more are necessary.

SCM PROCEDURE 008, REV3 DATE: 9)7/01 PAGE 18 OF 23 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS 7.4.5. If major changes have been made, then a full review as described in step 7.4.1 is required.

7.4.6. Once all issues have been resolved satisfactorily, complete and sign the Survey Documentation Control Sheet. (see Appendix C, "Survey Documentation Control Sheet").

7.4.7. Complete and sign the Survey QA Review Sheet. (see Appendix D, "Survey QA Review Sheet").

7.4.8. Return the survey documentation to the Office Manager.

8. Acceptance Criteria Survey Documentation Control Sheet and Survey QA Review Sheet (with signatures) are complete.

All survey documentation has been archived.

All voided/superseded survey revisions are marked as such on their respective Survey Document Control Sheets.

9. References 9.1. SRA Procedure 005 "Requirements for Completion of a Survey Using the SCM"
10. Required Records The following records shall be maintained for the life of the company as shown in Table
12. Record maintained upon completion the survey.

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 19 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS Table 12. Record maintained upon completion the survey.

ITEM All completed survey reports regardless of revision status Logbook SIMS Software Version used in survey SIMS Survey Directory Site Drawings Survey Notebook Survey Report Volume Video Tape or digital photos Computer media containing survey data file backup

11. Appendices 11.1. Appendix A, "Sample Contact Sheet" 11.2. Appendix B, "Sample Packing List" 11.3. Appendix C, "Survey Documentation Control Sheet' 11.4. Appendix D, "Survey OA Review Sheet"

SCM PROCEDURE 008, REV3 DATE: 9s7/01 PACE 20 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCM/SIMS Appendix A Sample Contact Sheet

SCM PROCEDURE 008, REV3 DATE: 9s7/10 PAGE 21 OF 21 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING, THE SCM/SIMS SRA CONTACT SHEET HANFORD DEPLOYMENT NAME PHONE NUMBER INTERNET ACCESS INFO National AOL Accesss Number (800) 245-0113 Local AOL Accesss Number (630) 435-1054 DON'S EMERGENCY CONTACTS Wife Cell (404) 351-1680 Home (770) 781-9292 Cell (404) 668-7606 BOB'S EMERGENCY CONTACTS Wife (770) 578-8362 Cell (678) 296-4815 CHARLIE'S EMERGENCY CONTACTS Wife (352) 628-5707 Cell (720) 841-5377 SITE INFO Marty Phalen (Job Site Contact) (Cell) (815) 263-9()01 SRA INFO Shonka Research Associates, Inc. (770) 509-7606 Hotel Address and Phone Site Address and Phone Client Address and Phone Number. Number. Number:

Holiday Inn 205 Rernmington Blvd.

Boling Brook IL 60440 Phone: (509)943-4400 If this notebook is found please contact Shonka Research Associates at (888) 509-7606

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 22 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS Appendix B Sample Packing List

SCM PROCEDURE 008, REV3 DATE: 9701 PAGE 23 OF 23 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCM/SIMS BONUS Packing List Don Toolbox, Electronics (Gray)

Knit Cap 37Pin Terminal Block Bag Alligator Leads (3)

Brief Case Connector. MHV (2)

Cold Weather Gear Connector. BNC (2)

Hard Hat Connector. BNC. T (I)

Hot Sauce Electrical Tape Leatherman GLPT. Red Organizer Liquid Tape Hotel # w/Confirmation (N.E. Power Rate!) Heat Gun Car Confirmation N Heat Shrink Map NIM Extended Cables Safety Glasses Pin extension leads Safety Shoes (Substantial Foot Wear) Q-Dope Shaving Kit Scotch Tape Solder Tie-Wraps (small. med, large)

Joe Tweeker Knit Cap Wire Bag Wire Strippers Cold Weather Gear Hard Hat Safety Glasses Toolbox, Mylar (Red)

Safety Shoes (Substantial Foot Wear) Anode Wire Roll (1)

Shaving Kit Mylar Roll (3)

Razzor Blades Scotch Tape SCM #1 Silver Solder Cables. BNC. HVPA-DLG (2) Solder Extractor Cables. DB37 (2) Soldering Iron Cable, DB9. Encoder cable. Uber Tape Roll (3)

Cables, Power. AC (2)

Detector Mounting Brackets (2)

Detector, Model 2 PSPC, 6' (2) Toolbox, SCM (Yellow)

Detector, Model 2 PSPC. 4' (2) Adapter, BNC Female to Banana Electronics (NIM. DLG. HVPA) Bottle Wrench Extension Cord (I) Bungy Cords (3)

Flow Gauge, Inlet Chalk. Powdered Flow Gauge. Outlet Chalk. Sticks or Paint Sticks Frame. SCM. Motorized Chalk Line Lunch Box PC Channel Locks Dasl402 Crescent Wrench (2)

CTR-5 Detector, Combustible Gas W/charger MHV Cables (2) Dykes Motor Exacto Knife Motor Controller Flash Light P-10 bottles (1) Hex Wrenches, ball ended (Metric)

Plug, gas, quick connect (3) Hex Wrenches, ball ended (US)

Regulator Measure Tape. 100' Surge Suppresser. ISOBAR. 120db Filter Pliers. Needle Nose Tubing. Tygon (3) Saew Driver, Philips (3>.

Screw Driver, Standard (2)

SCMNI #2 Socket Set Cables, BNC, HVPA-DLG (2) Source, Cs-137, 100 crr' Cables. DB37 (2) Spare BNC (I)

Cable, DB9, Encoder cable. Spare DB37 (1)

Cables. Power. AC (2) Tape. Scotch Detector Mounting Brackets (2) Teflon Tape Detector. Model 2 PSPC. 6' (2) Tie Wraps, Large (25)

Detector. Model 2 PSPC. 4' (2) Tweeker Electronics (NIM. DLG, HVPA)

Extension Cord (I!

SCM PROCEDURE 008, REV3 DATE: 917/01 PAGE 24 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SC.M/SIMs Flow Gauge. Inlet Flow Gauge. Outlet Test Equipment Frame, SCM. Motorized BNC cables (2)

Lunch Box PC Scope. Hand Held. Fluke 105B DasI402 Test Leads CTR-5 MHV Cables (2)

Motor Motor Controller Misc.

P-10 bottles (1) Clip Board (2)

Plug, gas, quick connect (3) Disk. 3.5" (I box)

Regulator Legal Pad Surge Suppresser. ISOBAR. 120db Filter Pencils (4)

Tubing. Tygon (3) Pers (4)

Batteries, C cell (6)

Batteriev, D cell (2)

GM Probe ESP.I1 Check Sources DB9-BNC Cable Soruce. Cs. 1OOcmA2 MHV Cable Cs Certificate Source, Am-24 1 Camera Software and Data Files Cable. BNC. Remote to DLG (I)

Camcorder Power supply and power cable Copy of New SCM version 4.x Camcorder Remote Copy of Bonus SCM version Camcorder Tapes (28) Copy of Visuspect 3.x Camcorder to Snappy Cable (Phono) Copy of Stitcher 3.x Camcorder W/case Camcorder wide angle lens Mount Plate. Tripod Documentation Logbook (2)

Snappy Marketing Folders (2)

Procedures Manual SIMS Rad Worker 11 CABLE. LAP LINK Respirator quallfit test Computer Survey Notebook Mouse Complete Set of Schematics Keyboard Phone Cable Monitor (21")

Spare Parts Cable. Power. AC Mini Isobar DAS 1402 Keyboard Leeson Motor Board Mouse, BSI P-10 Bottles (2)

Tubing (I Box)

Extension Cord (12 Guage)

' Hard Drives Removed and hand carried.

Shipping Containers Frame & 2' Detector Box # I Electronics Box #2 Tool Boxes Box #3 P-10 (4) Box #4 Detectors, 4' Box #5 Don's Suitcase Checked Luggable Carry-on

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 25 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCMISIMS Appendix C Survey Documentation Control Sheet

SCM PROCEDURE 008, REV3 DATE: 9701 PAGE 26 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCM/SIMS SHONKA RESEARCH ASSOCIATES, INC.

Survey Documentation Control Sheet DESCRIPTION VALUE CLIENT PROJECT I TASK NUMBER CLIENT TRACKING NUMBER DESCRIPTION EXAMPLE VALUE SURVEYAREA CODE A1000-B

= Z SURVEY UNIT CODE 00X U,

SURVEY LOCATION ELEMENT FZ00E SURVEY CLASSIFICATION ELEMENT 1 w w SURVEY REASON CODE FO I SURVEYMEDIA CODE CO(l SURVEYDETECTOR ELEMENT A-(B)1-251-0 SURVEY RECORD NUMBER OR SCM FILENAME AB604OIZ SURVEY MAP FILENAME AND REFERENCE Floorl.DXF COORDINATES IN (X, Y, Z ) IMETERS(.5, 12.5 0)

PERFORMED BY: _ DATE:

PERFORMED BY: DATE:

REVIEWED BY: DATE:

THIS SURVEY HAS BEEN VOIDED OR SUPERSEDED BY:

(SURVEY IDENTIFICATION CODE)

SCM PROCEDURE 008, REV3 DATE: 9/7/01 PAGE 27 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCM/SIMS Appendix D Survey QA Review Sheet

SCM PROCEDURE 008, REV3 DATE: 917101 PAGE 23 OF 28 TITLE: CONDUCT OF OPERATIONS FOR SURVEYS USING THE SCM/SIMS SHONKA RESEARCH ASSOCIATES, INCa Survey QA Review Sheet THE UNDERSIGNED HAS REVIEWED THIS SURVEY IN ACCORDANCE WITH THE METHOD(S) INDICATED BELOW.

1. SURVEY REPORT Review to determine that the data tables are consistent with the Auto Generated Survey A Records.

B Review report to ensure that backgrounds have been considered and applied.

c Review body of report and verify that general grammar, spelling, punctuation, etc. are correct D Other:

2. DOCUMENTATION Review to deterniine that the survey documentation has been validated, meets all A requirements for deliverable items, and that the documentation contains all necessary information for reconstruction at a later date.

B Review to verify that the tape backup is complete.

c Ensure that the Survey Archive has been performed.

D Other:

3. DELIVERABLE ITEMS A Ensure that all deliverable items due the client have been completed.

B Ensure that all deliverable items are prepared for transmission to client.

C Other:

4. OTHER REVIEWED BY: DATE:

/q4-1v-'c~bmeMJ `7 Control Copy #_ _

pi Shonka Research Associates, Inc.

4939 Lower Roswell Road, Suite 106 Marietta GA 30068 770-509-7606 Surface Contamination Monitor SCM Procedure 011, Revi Survey Naming Convention when Using the SCM

SCM PROCEDURE 011, REVI DATE: 9/7101 PAGE 2 OF 8 TITLE: SURVEY NAMING CONVENTION WHEN USING THE SCM Table A 1. Revision Table REVIEWED BY: D. DEBORD BRIEF

SUMMARY

OF CHANGES Initial write.

QA REVIEW BY: D. SHONKA . DATE:

EF V T: 9907/01 EFFECTIVE DATE: 9/7/1

SCM PROCEDURE 011, REVI DATE: 917/01 PAGE 3 OF a TITLE: SURVEY NAMING CONVENTION WHEN USING THE SCM

1. Purpose This procedure establishes the methods for naming surveys when using the SCM. The SCM saves data to a filename that is identical to the survey name entered by the SCM operator into the process software. Therefore, the survey name is currently limited to 8 alphanumerics.
2. Scope and Limitations This procedure applies to any use of the SCM when logging data.
3. Definitions and Acronyms Table 1. Definitions and Acronyms.

ITEM DESCRIPTION The Surface Contamination Monitor is a mobile platform SCM containing detectors, support electronics, and data logger

. used for conducting radiological surveys.

Survey Measurement Type This code identifies the type of survey: alpha, beta, gamma, Code quality assurance, etc.

Survey Operating Mode This code identifies the operating mode: rolling, comer or Code merged.

SCM ID Code This code identifies the SCM serial number.

This code identifies the survey number. This number starts Survey Sequence Code !at I and increments throughout the survey for a given Survey Measurement Type Code, Survey Operating Mode

. Code, and SCM ID Code. ....................... ...... :.. . ......... ._.._

This code identifies when a survey relates to another previous survey of the same survey block.

  • SurveyIdentification Code. ..

Sury I(S d o C This code provides a naming convention for surveys.

(SIC)

The defined objects are: Survey Measurement Type Code,_

SCM SIC Objects I Survey Operating Mode Code, SCM ID Code, Survey

_ _ _ _ i Sequence Code, and the Survey Interrelated Code.

SCM SIC Fundamental I The SIC is made up of elements and numbers. An element Objects is an alphanumeric.

Fundamental Object Data Each SCM SIC Fundamental Object has a data type defined !

Type as I alphanumeric or 1 digit.

Survey Strip iA continuous data set logged by the SCM.

SCM PROCEDURE 011, REVI DATE: 9/7101 PAGE 4 OF 8 TITLE: SURVEY NAMING CONVENTION WHEN USING THE SCM ITEM DESCRIPTION I Survey Stitch iA process of assembling survey strips into on file for data I analysis.

Survey Block A group of survey strips stitched into one spatial image. I

4. General Information The survey name holds values to help the SIMS data processor immediately identify the file. The survey name is made up of SCM Survey Identification Code (SIC) objects: Survey Measurement Type Code, Survey Operating Mode Code, SCM ID Code, Survey Sequence Code, and the Survey Interrelated Code.
5. Materials, Equipment, and Supplies Table 2. Materials, Equipment, and Supplies.

ITEM = SPECIFICATION SCM Model 3 SCM Process Software Version 2.0 or later

6. Responsibilities 6.1. Operator 6.1.1. Reads and becomes familiar with this procedure before performing an SCM survey.

6.1.2. Has successfully completed SCM I training.

7. Procedure 7.1. Survey Naming Convention The diagram in Appendix A, "SCM 8-Character.SICiagram" shows the SCM SIC._ ___

7.1.1. The first two characters designate the Survey Measurement Type and Purpose. Table 3 shows the allowed values.

SCM PROCEDURE 011, REVI DATE: 917101 PAGE 5 OF B TITLE: SURVEY NAMING CONVENTION WHEN USING THE SCM Table 3. Allowed values for the Survey Measurement Type and Purpose.

SURVEY PURPOSE CODE DESCRIPTION R Source Response Check P Performance Based Check C Calibration Check S Survey B Background Survey Z Informational Survey A Alpha Survey SURVEY MEASUREMENT DESCRIPTION TYPE CODE A Alpha Survey B Beta Survey G Gamma Survey N Nuetron Survey X Alpha Beta and Gamma Survey Y Alpha and Beta Survey W Wheel Encoder Confirmation 7.1.2. The third character designates as the Survey Operating Mode Code. Table 4 shows the allowed values. Use the merged code when combining the survey strips in a rolling survey with the survey strips of a comer survey.

Table 4. Allowed values for the Survey Operating Mode Code.

SURVEY OPERATING MODE DESCRIPTION CODE R Rolling or scanning survey.

C Comer or static measurement survey.-

M A merged survey.

7.1.3. The fourth character designates as the SCM ID Code. This code is the serial number of the SCM and will be a digit from zero thru 9. When merging survey data from 2 different SCMs, then enter this object as '%".

SCM PROCEDURE 011, REV1 DATE: 917101 PAGE 6 OF 8 TITLE: SURVEY NAMING CONVENTION WHEN USING THE SCM Table 5. Allowed values for the SCM ID Code.

SCM ID CODE DESCRIPTION l 0-9 SCM serial number. I Z Use this code when merging data from 2 different SCMs that where used on the same survey block.

7.1.4. The fifth, sixth and seventh characters is designated as the Survey Sequence Code. This code is a sequentially incrementing number used for a given Survey Measurement Type Code, Survey Operating Mode Code, and SCM ID Code.

Table 6. Allowed values for the Survey Sequence Code.

SURVEY SEQUENCE DESCRIPTION CODE 000-999 Sequential survey number.

7.1.5. The eighth character designates the Survey Interrelated Code. Use this code when performing a repeat, investigation, or other survey of a previous survey.

Table 7. Allowed values for the SCM ID Code.

SCM ID CODE DESCRIPTION A thru Y A sequential character that increments for each repeated survey or related survey.

Z Use the "ZE code as a placeholder so that the SCM file names are all 8-characters long.

8. References 8.1. NIA
9. Required Records -

9.1. NIA

10. Appendices 10.1. Appendix A, "SCM 5-Character SIC Diagram'

SCM PROCEDURE 011, REVI DATE: 9/7101 PAGE 7 OF 8 TITLE: SURVEY NAMING CONVENTION WHEN USING THE SCM Appendix A SCM 8-Character SIC Diagram

SCM PROCEDURE 011, REVI DATE: 917101 PAGE 5 OF c TITLE: SURVEY NAMING CONVENTION WHEN USING THE SCM Figure 1. SCM 8-Character SIC.

SCU tiCharacter SIC I Format p l I d I _ _ _ _ _ _ I ' I 'I ii I i I fl = SRC IA . Alpha R

  • Rolling OlhruO Othru9 O hru 9 Olthru 9 IA hru Yelse ZI I

p = PeC I . Bel& C . Corner I C

  • Calibration I G - Gamma I
  • u Mrs led z Allowed S
  • Survey N
  • Neutron Values 9
  • Bkg Survey X
  • Alpha, Bela, Survey Uodo This elemonl becomes a 'Z' and Gamma beceuso the same SCiM was Z
  • Intormation r
  • Alphe and This element is used when a probably nol used.

fallilng survey Is stitched with jnolher survey Ihat may be W

  • Wheel another folling survey or a Encoder cornem survey.

II SCM B*CIIARACTER SIC

'. t Initial Design: MRM 0915/01 Last Modified: MRM 09105101 DRAWING3 Page I of I

.. Copyright 2001 Shonka Research Associates All Rights Reserved