MONTHYEARDCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL DCL-24-054, LCO 3.0.3 Completion Time Limits2024-05-17017 May 2024 LCO 3.0.3 Completion Time Limits DCL-24-052, Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report2024-05-16016 May 2024 Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report DCL-24-051, One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage2024-05-0808 May 2024 One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage DCL-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Radiological Environmental Operating Report DCL-24-047, 2023 Annual Non-radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Non-radiological Environmental Operating Report DCL-24-048, O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 20232024-04-30030 April 2024 O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 2023 DCL-24-027, 2023 Annual Radioactive Effluent Release Report2024-04-28028 April 2024 2023 Annual Radioactive Effluent Release Report DCL-24-045, Annual Report of Occupational Radiation Exposure for 20232024-04-24024 April 2024 Annual Report of Occupational Radiation Exposure for 2023 DCL-24-042, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-04-17017 April 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations DCL-24-022, Notification of Changes to Decommissioning Schedule2024-04-0202 April 2024 Notification of Changes to Decommissioning Schedule DCL-24-023, Revised Certification of Permanent Cessation of Power Operations2024-04-0202 April 2024 Revised Certification of Permanent Cessation of Power Operations DCL-24-031, Decommissioning Funding Report2024-03-27027 March 2024 Decommissioning Funding Report DCL-24-032, 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant2024-03-27027 March 2024 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant DCL-24-028, Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability2024-03-21021 March 2024 Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability DCL-24-018, License Amendment Request 24-01 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2024-02-28028 February 2024 License Amendment Request 24-01 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) DCL-2024-507, 2023 Annual Report on Discharge Self-Monitoring2024-02-27027 February 2024 2023 Annual Report on Discharge Self-Monitoring DCL-24-020, Nuclear Material Transaction Report for New Fuel2024-02-21021 February 2024 Nuclear Material Transaction Report for New Fuel DCL-24-014, Owners Activity Report for Unit 1 Twenty-Fourth Refueling Outage2024-02-12012 February 2024 Owners Activity Report for Unit 1 Twenty-Fourth Refueling Outage DCL-24-013, Nuclear Material Transaction Report for New Fuel2024-02-0707 February 2024 Nuclear Material Transaction Report for New Fuel DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel DCL-2024-502, 2023 Annual Sea Turtle Report for Diablo Canyon Power Plant (DCPP)2024-01-25025 January 2024 2023 Annual Sea Turtle Report for Diablo Canyon Power Plant (DCPP) DCL-2024-501, Sea Turtle Stranding Report (Green Sea Turtle)2024-01-24024 January 2024 Sea Turtle Stranding Report (Green Sea Turtle) DCL-2024-500, Transmittal of the 4th Quarter of 2023 Report on Discharge Self-Monitoring2024-01-18018 January 2024 Transmittal of the 4th Quarter of 2023 Report on Discharge Self-Monitoring DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) 2024-09-09
[Table view] |
Text
m
- Electric Pacific Gas and 8
~ ~ Company Barry S. Allen Site Vice President Diablo Canyon Power Plant Mail Code 104/6 P. 0. Box 56 Avila Beach, CA 93424 805.545.4888 Internal: 691.4888 November 19, 2014 Fax: 805.545.6445 PG&E Letter DCL-14-107 U.S. Nuclear Regulatory Commission 10 CFR 50.4 ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Diablo Canyon Power Plant Licensing Basis Verification Project-Change in Commitment Regarding Component Design Basis Reviews
Reference:
- 1. PG&E Letter DCL-1 0-064, "Diablo Canyon Power Plant Licensing Basis Verification Project," dated June 11, 2010.
Dear Commissioners and Staff:
In Pacific Gas and Electric Company (PG&E) Letter DCL-10-064 (Reference 1),
PG&E provided the NRC with the scope of component design basis reviews (CDBRs) that would be completed as part of the Licensing Basis Verification Project (LBVP) Phase II. The CDBRs are modeled after the reviews conducted using NRC Inspection Procedure 71111.21, "Component Design Bases Inspection," as a guide.
In Reference 1, PG&E stated that the scope and schedule of the CDBRs would be adjusted if issues identified so warranted.
PG&E is revising the commitment regarding the number of CDBRs to be completed from eight to five. PG&E has completed CDBRs for the component cooling water system, the 230 kV system, the 500 kV system, the emergency diesel generator system, and the auxiliary feedwater system. The CDBRs identified in Reference 1 that will not be conducted are for the residual heat removal system, the solid state protection system, and the auxiliary saltwater system.
The scope of the LBVP for each system reviewed includes a verification of the licensing basis and a validation of the Final Safety Analysis Report, including implementing documents (e.g., plant procedures, design drawings, and calculations). CDBRs are then performed on the selected systems. As a result of this process, the CDBRs provide a deeper, more focused look at the *components because they benefit from the verification and validation of the licensing and design basis. The reviews to date have identified a number of issues and all have been entered into the Corrective Action Program. Although PG&E continues to evaluate A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
Document Control Desk PG&E Letter DCL-14-107 November 19, 2014 lrl Page 2
~&~
and address the findings from the CDBRs, no findings to date from the recent CDBRs have been concluded to be greater than low safety significance. As a result, PG&E has decided to reduce the scope from eight CDBRs to five.
This letter contains a change to the scope of the CDBRs being completed for a prior PG&E regulatory commitment to perform the Diablo Canyon Power Plant (DCPP)
LBVP.
Questions concerning the DCPP LBVP should be directed to Mr. Eric Nelson at (805) 545-4777.
Sincerely, 8~:1en .7. AIL-Site Vice President JY1 E/4609/50330504 cc: Marc L. Dapas, NRC Region IV Administrator Thomas R. Hipschman, NRC Senior Resident Inspector Ronald A. Kopriva, Senior Reactor Inspector Eric R. Oesterle, NRR Project Manager Eric P. Nelson, Senior Manager, LBVP A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway