MONTHYEARDCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System DCL-23-092, Material Status Report for the Period Ending August 31, 20232023-09-28028 September 2023 Material Status Report for the Period Ending August 31, 2023 DCL-23-077, License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-27027 September 2023 License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors DCL-23-083, Upcoming Meeting with Nuclear Security and Incident Response Staff2023-09-13013 September 2023 Upcoming Meeting with Nuclear Security and Incident Response Staff DCL-23-078, Nuclear Material Transaction Report for New Fuel2023-09-0606 September 2023 Nuclear Material Transaction Report for New Fuel DCL-23-070, Withdrawal of Request Regarding Senior Reactor Operator License Application2023-08-16016 August 2023 Withdrawal of Request Regarding Senior Reactor Operator License Application DCL-23-068, Nuclear Material Transaction Report for New Fuel2023-08-0909 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-066, Nuclear Material Transaction Report for New Fuel2023-08-0303 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-065, Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure2023-07-27027 July 2023 Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure DCL-23-064, Nuclear Material Transaction Report for New Fuel2023-07-26026 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-054, License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-07-13013 July 2023 License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-055, Nuclear Material Transaction Report for New Fuel2023-07-0606 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-042, Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 02023-05-24024 May 2023 Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 0 DCL-23-032, Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program2023-05-22022 May 2023 Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program DCL-23-041, 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 20222023-05-22022 May 2023 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 2022 DCL-23-038, Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule2023-05-15015 May 2023 Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule DCL-23-034, 2022 Annual Nonradiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Nonradiological Environmental Operating Report DCL-23-036, 2022 Annual Radiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Radiological Environmental Operating Report DCL-23-025, 2022 Annual Radioactive Effluent Release Report2023-05-0101 May 2023 2022 Annual Radioactive Effluent Release Report DCL-2023-512, Submittal of Receiving Water Monitoring Program 2022 Annual Report2023-04-27027 April 2023 Submittal of Receiving Water Monitoring Program 2022 Annual Report DCL-23-035, Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application2023-04-24024 April 2023 Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application DCL-23-028, Technical Specification Bases, Revision 142023-04-24024 April 2023 Technical Specification Bases, Revision 14 DCL-2023-511, Report on Discharge Monitoring for the First Quarter of 20232023-04-20020 April 2023 Report on Discharge Monitoring for the First Quarter of 2023 DCL-23-031, Submittal of Annual Report of Occupational Radiation Exposure for 20222023-04-19019 April 2023 Submittal of Annual Report of Occupational Radiation Exposure for 2022 DCL-23-024, Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System2023-04-0404 April 2023 Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System DCL-23-022, 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant2023-03-29029 March 2023 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-23-021, Independent Spent Fuel Storage Installation, Emergency Plan Update2023-03-23023 March 2023 Independent Spent Fuel Storage Installation, Emergency Plan Update DCL-23-020, Responses to NRC Questions Regarding License Renewal Efforts2023-03-17017 March 2023 Responses to NRC Questions Regarding License Renewal Efforts DCL-23-009, Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage2023-02-22022 February 2023 Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage DCL-23-008, Request Regarding Senior Reactor Operator License Application2023-02-22022 February 2023 Request Regarding Senior Reactor Operator License Application DCL-2023-503, Annual Sea Turtle Report2023-01-26026 January 2023 Annual Sea Turtle Report DCL-2023-502, (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring2023-01-18018 January 2023 (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring DCL-22-091, Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage2022-12-20020 December 2022 Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage DCL-22-089, Core Operating Limits Report for Unit 2 Cycle 242022-12-20020 December 2022 Core Operating Limits Report for Unit 2 Cycle 24 DCL-22-085, Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application2022-10-31031 October 2022 Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 2024-01-29
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24036A3382024-02-0505 February 2024 Environmental Scoping Meeting for the Diablo Canyon License Renewal Application - February 8 Meeting Slides ML24030A4672024-01-30030 January 2024 Environmental Scoping Meeting for the Diablo Canyon License Renewal Application - February 1 Meeting Slides ML23255A0012023-09-13013 September 2023 PG&E Slides for 9/13 Public Meeting Related to Diablo Canyon License Renewal ML23249A1592023-09-13013 September 2023 License Renewal Application Pre-Application Meeting: September 13, 2023 ML23174A0562023-06-26026 June 2023 Slides for TSTF-505 Pre-Submittal Public Teleconference 6-26-2023 ML23143A0882023-05-24024 May 2023 May 24, 2023, Public Meeting Slides Related to Diablo Canyon License Renewal ML23118A0902023-05-0303 May 2023 May 3, 2023, Diablo Public Meeting Slides ML23143A0952023-05-0303 May 2023 May 3, 2023, Diablo Public Meeting Slides for PG&E Presentation ML23079A0452023-03-16016 March 2023 RIC 2023 Slides - Maureen Zawalick TH19 ML22339A1022022-12-0505 December 2022 Pg_E Presentation for NRC Public Meeting ML22236A5472022-08-24024 August 2022 NRC Slides for Decommissioning Engagement Panel 8-24-2022 Meeting ML22200A0712022-07-21021 July 2022 Post-Shutdown Decommissioning Activities Report Public Meeting Slides - July 21, 2022 ML22200A0722022-07-21021 July 2022 PG&E Slides for Post-Shutdown Decommissioning Activities Report Public Meeting, Site-Specific Decommissioning Cost Estimate, and Irradiated Fuel Management Plan - July 21, 2022 ML21223A0842021-08-11011 August 2021 Slides for Post Shutdown EP pre-submittal Public Teleconference 8-30-2021 ML20310A2792020-11-0505 November 2020 Slides for Defueled TS Pre-Submittal Public Teleconference November 24, 2020 (L-2020-LRM-0101) ML21060B1872020-01-26026 January 2020 Enclosure 3 - 1-26-21 Diablo Canyon Renewal pre-app Meeting Slides ML19233A0722019-08-27027 August 2019 NEIMA Meeting Slides Public ML18295A0732018-10-24024 October 2018 Final Diablo Canyon Decommissioning Engagement Panel Meeting Oct 24 2018 ML17296A2222017-08-29029 August 2017 Presentation on Reactor Decommissioning for the August 29, 2017 at Congressman Salud Carbajal'S Public Meeting at San Luis Obispo Near Diablo Canyon ML16335A4392016-11-30030 November 2016 PG&E Reg Conference Presentation - NRC-11152016 ML15232A0102015-08-0404 August 2015 Diablo Canyon Power Plant - Risk-Informed Technical Specification Completion Times (TSTF-505) License Amendment Request: August 4, 2015 ML15216A4112015-08-0404 August 2015 TSTF-505: August 4, 2015 Public Meeting ML15216A4082015-08-0404 August 2015 Diablo Canyon Power Plant - Risk-Informed Technical Specification Completion Times (TSTF-505) License Amendment Request: August 4, 2015 ML15209A9442015-07-28028 July 2015 June 24, 2015, Summary of Annual Assessment Meeting with Pacific Gas and Electric and Public Open House Regarding Diablo Canyon Power Plant 2014 Performance ML15202A0982015-07-21021 July 2015 Slides for the August 5, 2015 Diablo Canyon Power Plant License Renewal Application Public Scoping Meeting ML15117A2262015-04-28028 April 2015 Nuclear Regulatory Commission April 28, 2015, Public Meeting Slides for Diablo Canyon Seismic Hazard Reevaluation ML15117A0692015-04-28028 April 2015 Pacific Gas and Electric Co. April 28, 2015, Public Meeting Slides for Diablo Canyon Seismic Hazard Reevaluation ML15035A0062015-02-0404 February 2015 Meeting Presentation, Diablo Canyon Power Plant Process Protection System Replacement Lessons Learned Using ISG 6 NRC Meeting on Digital I&C. ML15029A0942015-02-0303 February 2015 Alternate Source Term Pre- Submittal Meeting on February 3, 2015 (TAC Nos. MF5596 and MF5597). AST LAR NRC Meeting Presentation ML15014A2232015-01-14014 January 2015 Slides Regulatory Conference - January 14, 2015 ML14195A3742014-07-10010 July 2014 Update of Industry Actions Related to Diablo Canyon OE ML14188A9702014-07-0808 July 2014 14-07-08 ISG-06 Experience Presentation July 8 2014 Digital IC Meeting ML14155A3742014-06-0404 June 2014 May 22, 2014, Summary of Annual Assessment Meeting with Pacific Gas and Electric Regarding Diablo Canyon Power Plant 2013 Performance ML14077A2872014-03-18018 March 2014 Transcript of the 612th ACRS Meeting, March 6, 2014 (Open) Pages 1-317 ML13150A1712013-11-19019 November 2013 1978 - Rhrp Cavitation ML13150A1812013-11-19019 November 2013 Trade-Off Between Tank Vortexing Margin and ECCS Function ML13274A5142013-10-0202 October 2013 License Slides, 10/2/13 Pre-Application Meeting with Pacific Gas and Electric Company to Discuss Upcoming Structural Weld Overlay Relief Request to Use an Alternative to Disposition Detected Laminar Indications at Diablo Canyon, Unit 2 (TAC ML13269A0052013-09-26026 September 2013 Licensee Slides for 9/26/13 Meeting to Discuss Amendment Request to Adopt Technical Specifications Task Force TSTF-505, Provide Risk-Informed Extended Completion Times, RITSTF Initiative 4B ML13268A0022013-09-25025 September 2013 Slide Presentation for 9/25/13 Preapplication Meeting - Use of Leak-before-break for Fuel Structural Analyses and Coolable Geometry ML13268A0052013-09-24024 September 2013 Slide Presentation for 9/24/13 Pre-application Meeting, Diesel Generator License Amendment Request ML13159A0092013-06-0404 June 2013 Notable Failures in Nondustructive Testing - June 4, 2013 Public Meeting ML13066A7402013-03-0707 March 2013 Licensee Slides from 3/7/13 Pre-Application Meeting with Pacific Gas and Electric Company(Tac MF0687 & MF0688) ML13044A7352013-02-12012 February 2013 Licensee Slides from 2/12/13 Public Meeting to Discuss License Amendment Requests for Degraded Voltage Protection and Control Room Dose Analysis of Record at Diablo Canyon, Units 1 and 2 ML13024A4052013-01-24024 January 2013 Licensee Slides from 1/24/13 Meeting to Discuss Offsite Power ML13018A1342013-01-15015 January 2013 Pacific Gas and Electric Handouts from January 15, 2013 Meeting Regarding Pending License Amendment Request Related to Diesel Generator Technical Specifications ML12355A1612012-12-18018 December 2012 PG&E Handouts from the December 18, 2012, Meeting with the NRC Related to Emergency Core Cooling System Evaluations (TAC Nos. MF0313 and MF0315) ML12311A0492012-09-18018 September 2012 Part 26 Public Meeting NEI Presentation Slides ML12226A2552012-08-0707 August 2012 License Slides from 8/7/12 Meeting with Pacific Gas and Electric Regarding Future License Amendment Associated with Diesel Generator Technical Specifications ML12193A1412012-07-25025 July 2012 6/28/2012 Summary of Meeting with Pacific Gas and Electric to Discuss Digital Replacement of Process Protection System at Diablo Canyon, Units 1 and 2 and Presubmittal of TSTF-493 Option B License Amendment Request (TAC ME7522-ME7523, ME851 ML12157A2722012-06-11011 June 2012 5/31/2012 Summary of Telephone Conference with Licensees Regarding Near Term Task Force Recommendation 2.1 Seismic Reevaluations - Diablo Canyon, 1 and 2, San Onofre, Units 2 and 3, Columbia Generating Station, and Palo Verde, Units 1, 2, a 2024-02-05
[Table view] |
Text
PacificGas and Electric Company James R.Becker Diablo Canyon Power Plant Site Vice President Mail Code 104/5/601 P. . Box 56 Avila Beach, CA 93424 805.545.3462 June 11, 2010 Internal: 691.3462 Fax: 805.545.6445 PG&E Letter No. DCL-10-064 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Diablo Canyon Power Plant Licensinq Basis Verification Proiect
Dear Commissioners and Staff:
On May 7, 2010, representatives from Pacific Gas and Electric Company (PG&E) met with the NRC. The purpose of this meeting was to discuss a voluntary initiative by PG&E to conduct verification activities for the Diablo Canyon Power Plant (DCPP) Licensing Basis.
The attached enclosure outlines PG&E commitment to perform the DCPP Licensing Basis Verification Project (LBVP). Questions concerning the DCPP LVBP should be directed to Mr. Eric Nelson at (805) 545-4777.
Sinc ely, James R. Becker swh/50317991 Enclosure cc: Elmo C. Collins, NRC Region IV Eric Nelson Michael S. Peck, DCPP NRC Resident Loren Sharp Alan B. Wang, NRR 7430(
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
- Diablo Canyon e Palo Verde °San Onofre e South Texas Project
Enclosure PG&E Letter DCL-10-064 DIABLO CANYON POWER PLANT LICENSING BASIS VERIFICATION PROJECT NRC REGION IV PRESENTATION Dated May 7, 2010 A member of the STARS (Strategic Teaming and Resource Sharing) Alliance CallawAy o Comanche Peak
- Diablo Canyon o Palo Verde eSan Onofre
Diablo Canyon Power Plant Licensing Basis Verification Project NRC Region IV Presentation Meeting Conducted May 7, 2010 I
Project Overview oSummary of Guidance and Methodology NRR Office Instruction LIC- 100, Rev. 1, ,'Control of Licensing Bases" o] "Vertical Slice" Type Audit (Attributes in NRC Inspection Procedure 93801)
[ Project Focus o] Review and Evaluation of Licensing, Design, and Analysis Changes from the Original FSAR (Amendment 85) to present o] Correction of Current Licensing Basis (CLB) deficiencies identified.
o] Perform a review modeled after Component Design Basis Reviews for Eight Risk-Significant Systems after system licensing basis is verified o] Correct any identified deficiencies in the licensing basis searchable document databases o Check and Adjust Scope and Schedule based on CLB Issues 2 Identified while completing FSAR systems/topical changes
Project Benefits-DCPP-Benefits (list. is not exhaustive or all-inclusive) o] Enhanced Quality DCPP Current Licensing Basis (CLB) o] Enhancements in Content and Correction of Deficiencies in the FSAR Update o Enhancements in the Content of the CLB Electronic Document Databases and Associated Full-Text Search Capabilities o Enhanced 10 CFR 50.59 Screens and Evaluations Supporting Proposed Plant and Analysis Changes Enhanced CLB Maintenance Processes for Future 3
Project Scope
[] Phaise I (February - December 2010) 0 Review, Evaluate, and Document Findings for Component Cooling Water (CCW) and Auxiliary Feed Water (AFW) Systems 0 Review CLB Databases, Identify Specific Deficiencies, and Define the Desired Capabilities of an Improved Full-Text Search Tool 0 Perform the Following:
[] Develop Methodology for Review of Remaining License Based Changes Not Addressed in System Reviews (i.e. Chap 15) o] Review the Balance of the SER, SSER's, License Amendment Safety Evaluations, and all incoming/outgoing NRC correspondence, etc for CCW and AFW systems o] Identify all 10 CFR 50.59 Evaluations and a subset of the 50.59 Screens for review o] Review identified 10CFR 50.59 evaluations/screens for CCW &AFW o] PG&E Management Review of Phase I Findings and Recommendations
- September 15, 2010 o] Perform review modeled after Component Design Basis Review, CDBR, (using NRC Inspection Procedure 71111.21 as a guide) on Component Cooling Water system. - December 31, 2010.
Phase I funding has been approved.
Project Scope El Phase II (September 2010 - December 2014)
Implement Authorized Phase I Recommendations (including any outstanding actions from Phase I) o] Review and Evaluate Remaining Systems/Topical Material in the FSAR ri Review remaining 10 CFR 50.59 Evaluations/Screens identified o Perform reviews modeled after Component Design Basis Reviews, CDBRs, (using NRC Inspection Procedure 71111.21 as a guide) on Seven Risk-Significant Systems
" Systems for review (One or Two Per Year - AFW, SSPS, RHR, ASW, 230kV, 500kV, EDGs)
" Adjust scope and schedule if identified issues warrant o Correct Deficiencies identified in CLB Document Databases (e.g., Non-Searchable pdf Documents; Missing Documents, Enclosures, and Attachments)
Phase II funding is pending.
5
Project Organization Licensing Basis Verification Project Organization Chart 6
Phase I Tasks and Evaluations CCw and AFW Systems Information Compilation Primary Sources Original FSAR (Amendment 85) through Current Living FSAR Update Design Criteria Memoranda (DCM) 10 CFR 50.59 Evaluations Justifying Changes Correspondence to / from NRC License Amendment Requests, License Amendments, and Related Safety Evaluations Original Safety Evaluation Report and Supplemental SER's 7
- 1 Phase I Continued General Design Criteria and Regulatory Guide Compliance Commitments Licensing Basis Source Documents Codes and Standards o] Technical Specifications and Bases Eo Quality Evaluations, Nonconformance Reports, and NRC Violations Corrective Action Documents (Action Requests and SAP Notifications) o Three Mile Island Commitments -'NUREG-0578 and NUREG-0737 Licensing Position Whitepapers 8
Phase I Continued Information Evaluation Compare FSAR with DCMs o Compare FSAR with RG 1.70 Rev. 1 Requirements, Design Change Packages, Analysis Changes, and Change Justifications (50.59's)
Eo Compare Information with Identified Source Documents
[] Project Review and Evaluation of Findings o] Review Board Evaluation of Potential Licensing Issues o Issue SAP Notifications for Resolution of Confirmed Licensing Issues Issue-Systems Summary Report and Phase II Recommendations 9
LBVP Discovery/Problem Identification Process LBVP Discovery/Problem Identification Process 10
FSAR and DCM Enhancements w FSAR Enhancements Clarify General Design Criteria Compliance by System Clarify Regulatory Guide Compliance by System Hyperlink to System Descriptions in DCM and Source Documents Review Changes to the FSAR and Correct Identified Deficiencies w DCM Enhancements E] Enhance Licensing Basis Discussion Hyperlink to Licensing Basis Source Documents 11
Summary & Conclusions Project Benefits
[] Overall Enhancements in Quality and Access to the DCPP Current Licensing Basis (CLB) o] Enhancements in Content and Correction of Identified Deficiencies in the FSAR Update
[] Enhancements in the Content of the CLB Electronic Document Databases
[] Enhanced CLB and Databases will Result in Enhanced 10 CFR 50.59 Screens and Evaluations Supporting Proposed Plant and Analysis Changes
[] Enhancements in CLB Maintenance Processes will Ensure Continued CLB Quality
- 12
LBVP Milestones
" Periodic updates (2-3 per year) to Region IV on status and findings o September 15, 2010 PG&E Management Review of LBVP Phase I Findings and Recommendations o September 2010 Initiate Phase II o October 2010 Propose Status Mtg NRC Region IV ro December 2010 Complete Phase I CCW CDBR o March 2011 Complete Upgrade of CLB Electronic Document Databases o December 2014 Completion of Phase II 13