MONTHYEARBVY-99-127, Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-112, Monthly Operating Rept for Aug 1999 for Vermont Yankee.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Vermont Yankee.With BVY-99-102, Monthly Operating Rept for July 1999 for Vermont Yankee. with1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Vermont Yankee. with BVY-99-090, Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-077, Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-068, Monthly Operating Rept for Apr 1999 for Vynp.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Vynp.With BVY-99-046, Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-035, Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With BVY-99-001, Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station BVY-98-163, Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-154, Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-149, Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-135, Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-122, Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station BVY-98-098, Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station1998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station BVY-98-081, Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station1998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station BVY-98-068, Monthly Operating Rept for Apr 1998 for Vermont Yankee Nuclear Power Station1998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Vermont Yankee Nuclear Power Station BVY-98-053, Monthly Statistical Rept for Mar 1998 for Vynp1998-03-31031 March 1998 Monthly Statistical Rept for Mar 1998 for Vynp ML20248L1581998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Vermont Yankee Nuclear Power Station ML20217M7801998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Vynp Station ML20198L6111997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Vynp Station BVY-97-161, Monthly Operating Rept for Nov 1997 for Vermont Yankee Nuclear Power Station1997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Vermont Yankee Nuclear Power Station BVY-97-145, Monthly Operating Rept for Oct 1997 for Vermont Yankee Nuclear Power Station1997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Vermont Yankee Nuclear Power Station BVY-97-126, Monthly Operating Rept for Sept 1997 for Vermont Yankee Nuclear Power Station1997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Vermont Yankee Nuclear Power Station BVY-97-111, Monthly Operating Rept for Aug 1997 for Vermont Yankee Nuclear Power Station1997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Vermont Yankee Nuclear Power Station BVY-97-098, Monthly Operating Rept for Jul 1997 for Vermont Yankee Nuclear Power Station1997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Vermont Yankee Nuclear Power Station BVY-97-088, Monthly Operating Rept for June 1997 for Nynps1997-06-30030 June 1997 Monthly Operating Rept for June 1997 for Nynps BVY-97-074, Monthly Operating Rept for May 1997 for Vermont Yankee Nuclear Power Station1997-05-31031 May 1997 Monthly Operating Rept for May 1997 for Vermont Yankee Nuclear Power Station BVY-97-059, Monthly Operating Rept for Apr 1997 for Vermont Yankee Nuclear Station1997-04-30030 April 1997 Monthly Operating Rept for Apr 1997 for Vermont Yankee Nuclear Station BVY-97-042, Monthly Operating Rept for Mar 1997 for Vermont Yankee Nuclear Power Station1997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for Vermont Yankee Nuclear Power Station BVY-97-033, Monthly Operating Rept for Feb 1997 for Vermont Yankee Power Station1997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Vermont Yankee Power Station BVY-97-021, Monthly Operating Rept for Jan 1997 for VYNPS1997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for VYNPS BVY-97-001, Monthly Operating Rept for Dec 1996 for Vermont Yankee Nuclear Power Station1996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Vermont Yankee Nuclear Power Station BVY-96-154, Monthly Operating Rept for Nov 1996 for Vermont Yankee Nuclear Power Station1996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Vermont Yankee Nuclear Power Station BVY-96-138, Monthly Operating Rept for Oct 1996 for Vermont Yankee Nuclear Power Station1996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Vermont Yankee Nuclear Power Station BVY-96-114, Monthly Operating Rept for Sept 1996 for Vynp1996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Vynp BVY-96-103, Monthly Operating Rept for Aug 1996 for Vermont Yankee Nuclear Power Station1996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Vermont Yankee Nuclear Power Station BVY-96-095, Monthly Operating Rept for July 1996 for VT Yankee Nuclear Power Station1996-07-31031 July 1996 Monthly Operating Rept for July 1996 for VT Yankee Nuclear Power Station BVY-96-087, Monthly Operating Rept for June 1996 for Vermont Yankee Nuclear Power Station1996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Vermont Yankee Nuclear Power Station BVY-96-072, Monthly Operating Rept for May 1996 for Vermont Yankee Nuclear Power Station1996-05-31031 May 1996 Monthly Operating Rept for May 1996 for Vermont Yankee Nuclear Power Station BVY-96-057, Monthly Operating Rept for Apr 1996 for VT Yankee Power Station1996-04-30030 April 1996 Monthly Operating Rept for Apr 1996 for VT Yankee Power Station BVY-96-041, Monthly Operating Rept for Mar 1996 for Vynp1996-03-31031 March 1996 Monthly Operating Rept for Mar 1996 for Vynp BVY-96-018, Monthly Statistical Rept for Feb 1996 for VT Yankee Nuclear Power Station1996-02-29029 February 1996 Monthly Statistical Rept for Feb 1996 for VT Yankee Nuclear Power Station BVY-96-009, Monthly Operating Rept for Jan 1996 for Vermont Yankee Nuclear Power Station1996-01-31031 January 1996 Monthly Operating Rept for Jan 1996 for Vermont Yankee Nuclear Power Station BVY-96-001, Monthly Operating Rept for Dec 1995 for Vermont Yankee Nuclear Power Station1995-12-31031 December 1995 Monthly Operating Rept for Dec 1995 for Vermont Yankee Nuclear Power Station ML20095F6601995-11-30030 November 1995 Last Page of Monthly Operating Rept for Nov 1995 for Vermont Yankee BVY-95-131, Monthly Operating Rept for Nov 1995 for Vermont Yankee Nuclear Power Station1995-11-30030 November 1995 Monthly Operating Rept for Nov 1995 for Vermont Yankee Nuclear Power Station BVY-95-118, Monthly Operating Rept for Oct 1995 for Vynp1995-10-31031 October 1995 Monthly Operating Rept for Oct 1995 for Vynp BVY-95-106, Monthly Operating Rept for Sept 1995 for Vynp1995-09-30030 September 1995 Monthly Operating Rept for Sept 1995 for Vynp ML20092F5901995-08-31031 August 1995 Monthly Operating Rept for Aug 1995 for Vermont Yankee Nuclear Station 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217L8831999-10-21021 October 1999 Safety Evaluation Supporting Proposed Alternatives to Code Requirements Described in RR-V17 & RR-V18 ML20217G2041999-10-13013 October 1999 Safety Evaluation Supporting Amend 179 to License DPR-28 BVY-99-127, Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With ML20212C2551999-09-17017 September 1999 Safety Evaluation Supporting Amend 175 to License DPR-28 BVY-99-112, Monthly Operating Rept for Aug 1999 for Vermont Yankee.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Vermont Yankee.With BVY-99-109, Ro:On 990812,stack Ng Effluent Instrumentation for PAM Was Declared Oos.Caused by Instrument Drift Due to Electronic Components Based on Insps by Instrumentation & Controls Dept.Detector & Preamplifier Will Be Replaced on 9908311999-08-19019 August 1999 Ro:On 990812,stack Ng Effluent Instrumentation for PAM Was Declared Oos.Caused by Instrument Drift Due to Electronic Components Based on Insps by Instrumentation & Controls Dept.Detector & Preamplifier Will Be Replaced on 990831 BVY-99-102, Monthly Operating Rept for July 1999 for Vermont Yankee. with1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Vermont Yankee. with ML20209J0081999-07-14014 July 1999 Special Rept:On 990615,diesel Driven Fire Pump Failed to Achieve Rated Flow of 2500 Gallons Per Minute.Pump Was Inoperable for Greater than 7 Days.Corrective Maint Was Performed to Reset Pump Lift Setting BVY-99-090, Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With ML20196G5071999-06-23023 June 1999 Vynp Assessment of On-Site Disposal of Contaminated Soil by Land Spreading BVY-99-077, Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-068, Monthly Operating Rept for Apr 1999 for Vynp.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Vynp.With ML20206E8741999-04-29029 April 1999 SER Determined That Flaw Evaluation Meets Rules of ASME Code & Assumed Crack Growth Rate Adequate for Application ML20206D9301999-04-27027 April 1999 1999 Emergency Preparedness Exercise 990427 Exercise Manual (Plume Portion) ML20205S4211999-04-16016 April 1999 Non-proprietary Version of Revised Page 4-3 of HI-981932 Technical Rept for Vermont Yankee Spent Fuel Pool Storage Expansion ML20205K7581999-04-0707 April 1999 Safety Evaluation Supporting Alternative Proposal for Reexamination of Circumferential Welds with Detected Flaw Indications in Plant RPV BVY-99-046, Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With ML20205F6631999-03-0404 March 1999 Jet Pump Riser Weld Leakage Evaluation BVY-99-035, Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With ML20205P8241999-02-28028 February 1999 Rev 2 to Vermont Yankee Cycle 20 Colr ML20203H9881999-02-18018 February 1999 SER Accepting Alternative to 10CFR50.55a(g)(6)(ii)(A) Augmented Reactor Vessel Exam at Vermont Yankee Nuclear Power Station.Technical Ltr Rept Encl ML20203A6951999-02-0404 February 1999 Revised Rev 2,App B to Vermont Yankee Operational QA Manual (Voqam) ML20199K7151999-01-21021 January 1999 Corrected Safety Evaluation Supporting Amend 163 Issued to FOL DPR-28.Pages 2 & 3 Required Correction & Clarification ML20199K6991999-01-20020 January 1999 Safety Evaluation Concluding That Request to Use YAEC-1339, Yankee Atomic Electric Co Application of FIBWR2 Core Hydraulics Code to BWR Reload Analysis, at Vermont Yankee Acceptable ML20199L5951999-01-14014 January 1999 Safety Evaluation Accepting Licensee Proposed Alternative to Code Requirement,Described in Rev 2 to Pump Relief Request RR-P10 Pursuant to 10CFR50.55a(a)(3)(i) BVY-99-071, Corp 1998 Annual Rept. with1998-12-31031 December 1998 Corp 1998 Annual Rept. with BVY-99-001, Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station ML20198H5481998-12-23023 December 1998 Rev 2 to Vermont Operational QA Manual,Voqam ML20196H8641998-12-0101 December 1998 Cycle 19 Operating Rept BVY-98-163, Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With ML20195C4161998-11-0909 November 1998 SER Accepting Request That NRC Approve ASME Code Case N-560, Alternative Exam Requirement for Class 1,Category B-J Piping Welds BVY-98-154, Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With ML20155B6471998-10-26026 October 1998 Safety Evaluation Accepting Jet Pump Riser Insp Results & Flaw Evaluation,Conducted During 1998 Refueling Outage ML20154N0891998-10-16016 October 1998 Rev 1 to Vermont Operational QA Program Manual (Voqam) ML20154B6951998-10-0101 October 1998 SER Re Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Vermont Yankee Nuclear Power Station BVY-98-149, Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With ML20239A1361998-09-0202 September 1998 SER Re License Request for NRC Review & Concurrence W/Changes to NRC-approved Fire Protection Program BVY-98-135, Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With ML20151U0361998-08-28028 August 1998 Non-proprietary Rev 1 to Holtec Rept HI-981932, Vermont Yankee Nuclear Power Station Spent Storage Expansion Project ML20237E9221998-08-20020 August 1998 Vynp 1998 Form NIS-1 Owners Summary Rept for ISI, 961103-980603 BVY-98-122, Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station ML20205F6491998-07-31031 July 1998 Rev 1 to GE-NE-B13-01935-02, Jet Pump Assembly Welds Flaw Evaluation Handbook for Vermont Yankee ML20236G0011998-06-30030 June 1998 Individual Plant Exam External Events BVY-98-098, Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station1998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station ML20248C5081998-05-31031 May 1998 Rev 2 to 24A5416, Supplemental Reload Licensing Rept for Vermont Yankee Nuclear Power Station Reload 19 Cycle 20 ML20248C4951998-05-31031 May 1998 Rev 1 to Vermont Yankee Nuclear Power Station Cycle 20 Colr BVY-98-081, Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station1998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station ML20247J8341998-05-31031 May 1998 Peak Suppression Pool Temp Analyses for Large Break LOCA Scenarios, for May 1998 ML20247G4001998-05-12012 May 1998 Interview Rept of Ej Massey ML20247E6351998-04-30030 April 1998 Rev 1 to GE-NE-B13-01935-LTR, Jet Pump Riser Welds Allowable Flaw Sizes Ltr Rept for Vermont Yankee 1999-09-30
[Table view] |
Text
E
- l VERMONT YANKEE NUCLEAR POWER CORPORATION P.O. Box 157, Govemor Hunt Road .' l Vemon, Vermont 05354-0157 j (802) 257-7711 j l.
J June 10,1999 I BVY-99-077 )
United States Nuclear Regulatory Commission
- ATTN: DocumentControlDesk Washington, D.C. 20555 i
Reference (a) License No. DPR-28 (Docket No. 50-271)'
In accordance with sechon 6.7. A.3 of the Vermont Yankee Technical Specifications, submitted herewith is the Monthly Statistical Report for the Vermont Yankee Nucleu .
Power Station for the month of May.1999. ~
Sincerely,
. VERMONT YANKEE NUCtEAR POWER CORPORATION
- g- 1 M' A. Balduzzi !/ ,
l Plant Manager
/j ec: 'USNRCRegionI Administrator. !
USNRC Rendent Inspector-VYNPS
.USNRC Project Manager-VYNPS /[,
Vermont Department ofPublic Service (
,40J[
n 1 p160M[
PDR A PDR271at i R
VERMONT YANKEE NUCLEAR POWER STATION MONTHLY STATISTICAL REPORT 99-05 FOR THE MONTH OF MAY 1999 l
l 1
c, *,
', OPERATING DATA REPORT DATE 990610 COMPLETED BY G.A. WALLIN l- TELEPHONE (802)258-5414 OPERATING STATUS
- 1. Unit Name: Vermont Yankee
- 2. Reporting Period: May
- 3. Licensed Thermal Power (MWt): 1593
- 4. Nameplate Rating (Gross MWe): 540
- 5. Design Electrical Rating (Net MWe): 522
- 6. Maximum, Dependable Capacity (Gross MWe): 535
- 7. Maximum Dependable Capacity (Net NWe): 510
- 8. If changes, occur in capacity ratings (Items Number 3 through 7) since last report, give reasons:
- 9. Power level to which restricted, if any(Net MWe): N/A
- 10. Reasons for restrictions, if any: N/A I This Month Yr-to-Date Cumulative
- 11. Hours in Reporting Period 744.00 3623.00 231527.00 l
- 12. Number Of Hours Reactor was Critical 744.00 3623.00 193824.16
- 13. Reactor Reserve Shutdown Hours 0.00 0.00 0.00
- 14. Hours Generator On-Line 744.00 3623.00 190347.00 l
- 15. Unit Reserve Shutdown Hours 0.00 0.00 0.00
- 16. Gross Thermal Energy Generated (MWH) 1176983.50 5732752.20 286812413.70
- 17. Gross Electrical Energy Generated (MWH). 402956.00 1974574.00 96016771.00 l 18.' Net Electrical Energy Generated (MWH) 383797.00 1895255.00 91336706.00
- 19. Unit Service Factor 100.00 100.00_ 81.1.0
- 20. Unit Availability Factor 100.00 100.00 81.10
- 21. Unit Capacity Factor (Using MDC Net) 101.10 102.60 77.10
- 22. Unit Capacity Factor (Using DER Net) 98.80 100.20 75.50
- 23. Unit Forced Cut *ge Rate 0.00 0.00 4.45
- 24. Shutdowns scheouled over next 6 months (Type, Date, and Duration of Each: 1999 Refueling Outage scheduled to begin on October 29,1999 and end on November 30, 1999.
- 25. If shut down at end of report period, estimated date of_startup: N/A
- 26. Units In Test Status (prior to commercial operation): N/A Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION VYDPF 0411.01 (Sample)
DP 0411 Rev. 7 Page 1 of 1 RT No. 13.F01.19F
n-- ,
', AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-271 UNIT Vermont Yankee DATE 990610 COMPLETED BY G.A. WALLIN TELEPHONE (802)258-5414 MONTH May DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net)
- 1. 526 17. 511
- 2. 526 18. 505
- 3. 525 19. 506
- 4. 524 20. 516
- 5. 524 21. 519
- 6. 524 22. 519
- 7. 524 s 23. 519
- 8. 524 24. 516
- 9. 512 25. 431 10, 516 26. 515
- 11. 522 27. 517
- 12. 519 28. 521
- 13. 521 29. 520 ,
- 14. 526 30. 513
- 15. 525 31. 513 i
- 16. 513 l INSTRUCTIONS:
On this format, list the average daily unit power level in MWE-Net for each day in the reporting month. Compute to the nearest whole megawatt.
I VYDPF 0411.02 (Sample) J DP 0411 Rev. 7 Page 1 of 1 RT No. 13.F01.18V I
d n
,a e e vg e 4 l n k 1- .
aie n n 4 vtg a i 5 e sn Y l -
v sea l 8 i sth e t a 5 tt a c sase e 1 n 0 W 2 cn pmx ntnl c 7 o 1 )
ee yae oaei r 2 m 6 . 2 rv br iDcF u
- r 0 A. 8 0 re ,cn t i o 0 e 9 or esr cfL) S 5 V 9G ( CP n e uo R e idt r rE e OEEYE doc bot tnoL m NMTBN ntn rra p sof( a AA O a e u ni S TNDDH nr Itst)
E KT EP TE eor T,le d at r1 reo6 siu Vgo CI EL utc I nr G a e p1 I ON LE ace Si ph e 0 DU PT CAR Msa teSR t M ir G i O bPytE b _
C t i rnR i -
n hrteU h e xonvN x n D EfEE( E o O 4 5 5pe R md N m) oo O an CC C ri mca aSl m r p e ccx t e B SiE 4 sd R t(
yo ll a SC aamr uuoe S e daaut oMMAO nnth N s t A h O ntr / t - - - -
I eno N e -
T cep M1234 C ive e U LER 3 g D n E
R h a -
f ) ) c R og n nx E n r i ie W Y di o a a O A 3ot t 4 l l n P M htnc p n pr tuwa x od xe D ehoe E i n Et N H MSDR
( t tan ( t A T s c o a N ee i gi rp S O n rT rnt o _
N M o
W O T s H, l r snnero 2a i o e ii v E r D R e B a Ram i T O R Fe ratl -
U P c yT x a a H E tngr Ern)
S R n) nanor t on _
os 0 enit oesii T i r 0 mel at sita -
I : pt el annal N tu ninuureirp U ao 0 ouif gecmex rh s q a e e pi d pE u( aEMRROLAO(
D e- - - - - - - -
RABCDE FGH e
p S 2.
1 y T
d 5 e 7 2 l 3 e 5 du 0 .
t 0 ed v1 a 9 ce 1 e D 9 rh 1Rf oc 4 o FS 01 3 11 0 : : F4
. - FS P0 e o 9 D _g N 9 YPa 1 VDP
T. g , f.,
Yb *
- DOCKET NO. 50-271 DATE 990610 x
COMPLETED BY G.A. WALLIN TELEPHONE (802)258-5414 REPORT. MONTH May
SUMMARY
OF OPERATING EXPERIENCES'
- Highlights'
~ Vermont Yankee < operated at 99.3% of rated thermal power'for the month,-
Gross electricalfgeneration was- 402,956 MWHe or 99.2% design electrical capacity.
-Operating Summary LTherfollowing is'a chronological. description of plant operations including other pertinent' items'of interest for the month:
,A7 :,he beginning of the reporting' period the plant was operating at 99.9%
Lof rated thermal power.
-990525 At 0140 hours0.00162 days <br />0.0389 hours <br />2.314815e-4 weeks <br />5.327e-5 months <br />,-reducing power to minimum recirculation flow to perform. scheduled maintenance,.surveillances, single rod scram testing, and a rod' pattern exchange. (See Unit Shutdowns and Power Reductions).
990525 -At 0240 hours0.00278 days <br />0.0667 hours <br />3.968254e-4 weeks <br />9.132e-5 months <br />, initiated MSIV full closure and Turbine bypass
-valve testing.
990525 At 0320 hours0.0037 days <br />0.0889 hours <br />5.291005e-4 weeks <br />1.2176e-4 months <br />, completed MSIV full closure and Turbine bypass valve testing.
990525 1At-.0335 hours0.00388 days <br />0.0931 hours <br />5.539021e-4 weeks <br />1.274675e-4 months <br />,-initiated single rod scram testing.
990525L1At 0445' hours,. initiated a rod pattern exchange.
.990525~ At 1013 hours0.0117 days <br />0.281 hours <br />0.00167 weeks <br />3.854465e-4 months <br />, completed /the rod pattern exchange and single rod scram' testing.
990525 <At.;1042 hours0.0121 days <br />0.289 hours <br />0.00172 weeks <br />3.96481e-4 months <br />,-initiated:a return to full power.
At the end of the reportin'g period the plant was' operating at 99.9%~of rated thermal power.
-VYDPF:0411.04 (Sample)~
DP-0411 Rev.'7.
Page 1 of 1 RT No. 13.F01.18X L_' .