BSEP 05-0079, Inservice Inspection Program for the Third Year Interval-Refueling Outage 16 Owner'S Activity Report

From kanterella
Jump to navigation Jump to search
Inservice Inspection Program for the Third Year Interval-Refueling Outage 16 Owner'S Activity Report
ML051950246
Person / Time
Site: Brunswick Duke Energy icon.png
Issue date: 07/08/2005
From: O'Neil E
Progress Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
BSEP 05-0079 B217R1
Download: ML051950246 (16)


Text

.: Progress Energy 10 CFR 50.55a JUL 0`8 2005 SERIAL: BSEP05-0079 U. S. Nuclear Regulatory Commission ATIN: Document Control Desk Washington, DC 20555-0001

Subject:

Brunswick Steam Electric Plant, Unit No. 2 Docket No. 50-324/License No. DPR-62 Inservice Inspection Program for the Third 10-Year Interval - Refueling Outage 16 Owner's Activity Report Ladies and Gentlemen:

Carolina Power & Light Company, now doing business as Progress Energy Carolinas, Inc.,

submits the enclosed American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, Form OAR-1 Owner's Activity Reports for the Brunswick Steam Electric Plant (BSEP), Unit No. 2. The enclosed Form OAR-1 Owner's Activity Reports cover inspection activities being credited for the second inspection period of the third 10-year inservice inspection interval. The second period of the third 10-year interval began May 11, 2001, and ended May 10, 2005.

On August 7, 2003, a revision to 10 CFR 50.55a went into effect which incorporates, by reference, NRC Regulatory Guide 1.147, Revision 13, "Inservice Inspection Code Case Acceptability, ASME Section XI, Division 1." This revision of Regulatory Guide 1.147 indicates that ASME Code Case N-532-1, "Alternative Requirements to Repair and Replacement Documentation Requirements and Inservice Summary Report Preparation and Submission as Required by IWA-4000 and IWA-6000,Section XI, Division 1," can be used provided the OAR-1 forms are submitted to the NRC within 90 days of the completion of the refueling outage. ASME Code Case N-532-1 requires an Owner's Activity Report Form OAR-1 to be prepared and certified upon completion of each refueling outage.

As specified by the ASME Code Case and Regulatory Guide 1.147, the Form OAR-1 Owner's Activity Report for BSEP, Unit 2 Refueling Outage 16 (i.e., B217R1) is provided in Enclosure 1. Enclosure 2 provides a copy of the Form OAR-1 Owner's Activity Report for the Unit 2 containment inspections performed in accordance with the ASME Code,Section XI, Subsections IWE and IWL, during Refueling Outage 16. Refueling Outage 16 for Unit 2 ended on April 9, 2005.

Progress Energy Carolinas. Inc.

Brunswick Nuclear Plant P.O. Box 10429 Southport, NC 28461

Document Control Desk BSEP 05-0079 / Page 2 No regulatory commitments are contained in this letter. Please refer any questions regarding this submittal to Mr. Leonard R. Beller, Supervisor - Licensing/Regulatory Programs, at (910) 457-2073.

Sincerely, Edward T. ONeil Manager - Support Services Brunswick Steam Electric Plant WRM/wrm

Enclosures:

1. Owner's Activity Report - OAR-i Report for B217R1 Refueling Outage, Revision 0
2. Owner's Activity Report - OAR-i Report for B217R1 Refueling Outage Containment Inspections

Document Control Desk BSEP 05-0079 / Page 3 cc (with enclosures):

U. S. Nuclear Regulatory Commission, Region II ATTN: Dr. William D. Travers, Regional Administrator Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, GA 30303-8931 U. S. Nuclear Regulatory Commission ATIN: Mr. Eugene M. DiPaolo, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 U. S. Nuclear Regulatory Commission (Electronic Copy Only)

ATTN: Ms. Brenda L. Mozafari (Mail Stop OWFN 8G9) 11555 Rockville Pike Rockville, MD 20852-2738 Ms. Jo A. Sanford Chair - North Carolina Utilities Commission P.O. Box 29510 Raleigh, NC 27626-0510 Mr. Jack Given, Bureau Chief North Carolina Department of Labor Boiler Safety Bureau 1101 Mail Service Center Raleigh, NC 27699-1101

BSEP 05-0079 Enclosure 1 Owner's Activity Report - OAR-1 Report for B217R1 Refueling Outage. Revision 0

Progress Energy BRUNSWICK STEAM ELECTRIC PLANT UNIT 2 OWNER'S ACTIVITY REPORT OAR-1 REPORT FOR B217R1 REFUELING OUTAGE REVISION 0 Prepared By: Date (,- -05 NDE / Snubber & Support Program Tanager Reviewed By: Date 4/6AL2O5

/ kepair/Replacement Program Manager Reviewed By: Date tol OS Independent Reviewr Reviewed By:

Az5W~o eist Sca AKuzhorized Nuclear Inservice Inspector Date

Revision Summary

  • Initial issue

INTRODUCTION This report represents a summary of the Inservice Inspection (ISI) activities performed at the Carolina Power and Light Company's Brunswick Steam Electric Plant (BSEP) Unit 2 during the Spring 2005 refueling outage.

The examinations and testing performed during this timeframe were for credit during the second inspection period of the Third Inspection Interval.

Examinations and testing were performed to satisfy the requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Inspection Program B, 1989 Edition with no addenda.

During the refueling outage, ASME Code Category B-D and R-A components were identified as having less than 90% coverage. A relief request will be submitted prior to the end of the Inspection Interval for examination coverage.

In accordance with requirements of Code Case N-532, which has been approved for use at the Brunswick Station, enclosed is the Owners Activity Report (OAR-I Report).

FORM OAR-I OWNER'S ACTIVITY REPORT Report number _ 2-05-B217RI Owncr __Carolina lower & Light Company, P'0 Box 1551, Raleigh, North Carolina (Name and Address of Owner)

Plant _Brunswick Stcam Electric Plant, PO Box 10429, Southport, North Carolina (Name and Address of Plant)

Unit No. 2_ Commercial Servicc Datc 11/3175 . . Refueling outage no. -B217RIA_

(if applicable)

Current inspection interval -3rd (I st. 2nd, 3rd, 4th, other)

^sanbn LurrclIL

nen2snn npr-rvl
  • fJ-tLAVII t-i11,

'I-A

_______5, (I1st. 2nd, 3rd)

Edition and Addenda of Section Xl applicable to the inspection plan _1989 edition with no addenda_

Date and revision of inspection plan February 23, 2005 _ISI Program Plan revision 12 Edition and Addenda of Section Xl applicable to repairs and replacements, if different than the inspection plan CERTIFICATE OF CONFORNMANCE I certify that the statements made in this Owner's Activity Report are correct and that the examinations, tests, repairs, replacements, evaluations and corrective measures represented by this report conform to the requirements of Section Xi.

Certificate of Authorization No. N( Expiration Date t'J A (if applicable)

Signed i IN9 Pr I Date (6-0s Owner or Oy r s Designee, Title CERTIFICATE OF INSERVICE INSPECTION 1,the under signed, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of -North Carolina_ _ and employed by .. Hartford Steam Boiler of

_ Connecticut have inspected the items described in the Owner's Activity Report during the period _8/26/03 to 5/10/05 and state that to the best of my knowledge and belief, the Owner has performed all of the activities represented by this report in accordance with the requirements of Section Xl.

By signing this certificate neither the Inspector nor his employer makes any wvarrantee, expressed or implied, concerning the tests, repairs, replacements. evaluations and corrective measures described this report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for an personal injury or property damage or a loss of any kind arising from or connected with this inspection.

Commissions NC-1433, A.N.I.B.C._

'y" Inspector's Signature National Board, State, Province and Endorsements Date 6 6

i TABLE 1 ABSTRACT OF EXAMINATIONS AND TESTS To~talf.. ' ..

ToTot' Total Tota Examina ions.

Examinations-. Examinations Examinations Creited %):

Exa ination Rqire

. . for .Credited for Credited (%) to Date for the iCategory.-.;." .. -the Interval This Peniod for the Perio'd . Interval Remarks-(see note 1) :-- -.- . ,-,-;'_

B-A 28 0 0 32 See note 2 B-D 70 19 27 56 See note 2 B-E 46 0 0 0 See note 2 B-G-1 320 0 0 0 See note 2 B-G-2 NA 6 NA NA See note 4, 5 B-K 13 8 61 61 See note 7 B-L-2 NA NA NA NA See note 4 B-M-2 NA 3 NA NA See note 4 B-N-1 3 1 33 66 B-N-2 32 0 0 0 See note 2 B-O 8 0 0 0 See note 2 C-A 3 1 33 66 C-B 2 2 100 100 See note 6 C-C 11 6 54 72 See note 7 C-F-2 31 8 26 65 D-A 6 2 33 67 See note 7 F-A 77 30 38 . 61 R-A 56 28 50 50 See note 3

TABLE 1 NOTES The following notes correspond to the numbers referenced in Table I of the OAR-1 Report:

1. Examination categories B-B, B-H, B-K-I, B-N-3, B-L-1, B-M-1, C-F-1, C-G, D-B, D-C do not apply to the Brunswick Station.

Examination categories B-K, C-C and D-A reflect Code Case N-409.

2. Some or all examinations in this category may be deferred until the end of the inspection interval.
3. Examination category B-F and B-J have been subsumed by Category R-A to reflect approval of a Class 1 Risk Informed ISI Program. This was implemented with the commencement of the Second Inspection Period and the total number of examinations for the remaining periods and interval reflect Relief Request RR-27 and NRC Safety Evaluation dated 2/17/2000.
4. The examinations under this examination category are event related. They are only required if a subject pump or valve is disassembled during a maintenance activity.
5. Item number B7.80 of this category includes a requirement to examine CRD bolting if a CRD is disassembled. In accordance with relief request RR-04 which implemented Code Case N-547, there is no longer a requirement to examine this bolting.
6. This category has only 2 items and is covered by Relief Request RR-21.
7. This category reflects adoption of code case N-409 during 2nd Inspection Period.

TABLE 2 ITEMS WTH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE Fla Flw o Rlevat Condition Fduiid Exam.ination Item item; ' -acDer - Scheduled Sction -XI uring ite or Number Description ':-IWA3300)  : Exanmination-or:Test(Yes orNo) =

D-B D2.10 SW Flange & bolting Evaluation for continued replacement per EC service per Code Case N- No 50480 due to through- 513 wall leak D-B D2.10 Through-wall leak SW Evaluation for continued No line 2-SW-103-24-157 service per Code Case N-513 D-B D2.10 Through-wall leak SW Evaluation for continued No line 2-SW-103-30-157 service per Code Case N-513 D-B D2.10 Through-wall leak SW Evaluation for continued No line 2-SW-142-30-157 service per Code Case N-513

+ 9

4. 9 9

.9. 1- t t

+ 4- 9 I

___________________ 1__________ I_________ ________________________ ________________________________

TABLE 3 ABSTRACT OF REPAIRS, REPLACEMENTS, OR CORRECTIVE MEASURES REQUIRED FOR CONTINUED SERVICE

- F~~aorReent' Q.Ciniin F6und"C.

Rpir, -3. .- P .Repai.,

Relciinor- e%

'6 X. . ,  ; Replacement

^sCIass .*;'JMeasur  :.. eDescption m -iiofWork

'. . . olet Installation of 2 Repair CRD Insert line mechanical No 3/18/05 592811-01 (30-43) clamp per Code Case N-523-2 Installation of 2 Repair CRD Insert line mechanical No 3/18/05 595039-01 (3443) clamp per Code Case N-523-2 2 Repair CRD Insert line Installation of (3843) mechanical No 3/18/05 595045-01 clamp per Code Case N-523-2 2 Repair CRD Insert line Installation of (2643) mechanical No 3/18/05 595563-01 clamp per Code Case N-523-2 3 Replacement SW Piping Replacement of No 1/7/03 322150-04 (2-SW-29-6-046) flange & bolting per EC 50480 on through-wall leak 3 Repair SW Piping Repair of No 3/16/03 191267-01 (2-SW-103-24-157) through-wall leak}

3 Replacement SW Piping Replacement of No 4/20/05 545165-01 (2-SW-103-30-157) piping due to through-wall leak .

3 Replacement SW Piping Flange No 4/21/05 502255-01

___ _ I I__

(2-SW-142-30-157) replacement I

BSEP 05-0079 Enclosure 2 Owner's ActivitY Report - OAR-I Report for B217R1 Refueling Outage Containment Inspections

ATTACHMENT 1 -

Page 1 of 2 Code Case N-532 Form OAR-1, Owner's Activity Report FORM OAR-1 OWNER'S ACTIVITY REPORT Report Number CIP-B217R1 Owner Carolina Power & Ught Company dflWa Progress Energy Carolinas, Inc.. PO Box 1551. Raleigh. North Carolina (Name and Address of Owner)

Plant Brunswick Steam Electric Plant, PO Box 10429, Southport, North Carolina (Name and Address of Plant)

Unit No. 2 Commercial Service Date November 1975 Refuelin g Outage No. B217R1 (if applicable)

Current Inspecton Interval First Containment Inspection Interval (Subsecton IWE & IWL Only)

(11", 2e, 3 d, 4, other)

Current Inspection Period 2"e Inspection Period (11",2d, 3d)

Edition and Addenda of Section XI Applicable to the Inspection Plan 1992 Edition w/ 1992 Addenda Date and Revision of Inspection Plan OBNP-TRO002 (R8-a'3Q'04)

Edition and Addenda of Section Xi Applicable to Repairs and Replacements, if different that the Inspection Plan N/A CERTIFICATE OF CONFORMANCE I certify that the statements made In this Owner's Activity Report are correct and that the examinations, tests, repairs, replacements, evaluations, and corrective measures represented by this report conform to the requirements of Section Xi.

Certificate of Authorization No. N/A Expiration Date NMA n , (if applicable)

Signed Ii1 L'k Materials Proarams Sunervisor Date J S Owner or Owner's Designee, Title CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission Issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of North Carolina and employed by Hartford Steam Boiler Inspection and Insurance Company of Hartford, Connecticut have inspected the items described in this Owner's Activity Report, during the period 4/11/03 to 4/01/05 , and state that to the best of my knowledge and belief, the Owner has performed all of the activities represented by this report in accordance with the requirements of Section XI.

By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations, tests, repairs, replacements, evaluations and corrective measures descnbed in this report. Furthermore, neither the inspector nor his employer shall be liable In any mamner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.

p& a r Commissions NC-1433, AINBC rInspector's Signature National Board, State, Province and Endorsements Date__ __ _ __ _

This form (EO01 27) may be obtained for the Order Dept., ASME, 22 Law Drive, Box 2300, Fairfield, NJ 07007-2300 I OENP-16 I Rev. 43 @

ATTACHMENT 2 Page 2 of 2 '

Code Case N-532 Tables 1, 2, and 3 Note: This Owner's Activity Report is only applicable to the Containment Inspection Program (Subsection IWE & IWL) and does not address Class 1, 2, and 3 components.

TABLE 1 ABSTRACT OF EXAMINATIONS AND TESTS Total Total Total Total Examinations Examinations Examinations Examinations Credited ('%) To Examination Required For Credited For Credited (s) Date For Category The Interval This Period For This Period The Interval Remarks E-A See Notes See Notes 100% 66% All components within this category were examined except those components which were insulated or submerged.

E-B N/A N/A N/A NA This Category is not being implemented as allowed by 10 CFR 50.55a(b)(2)(ix)(C).

E-C See Notes See Notes 100% 66% All components within this category were examined E-D See Notes See Notes 100% 66% All components within this category were examined E-F N/A N/A N/A WA This Category is not being implemented as allowed by 10 CFR 50.55a(b)(2)(ix)(C).

E-G See Notes See Notes 100% 66% All components within this category were examined.

E-P N/A N/A N/A N/A L-A NIA 18 100% N/A L-B N/A N/A N/A N/A The Unit 2 containment does not have a post-I_ _tensioning system.

TABLE 2 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRE EVALUATION FOR CONTINUED SERVICE TABLE 3 ABSTRACT OF REPAIRS, REPLACEMENTS, OR CORRECTIVE MEASURES REQUIRED FOR CONTINUED SERVICE

- Flaw or Relevant Condition Found Repair, During Scheduled Replacement, Section Xl Repair/

Code or Corrective Examination or Date Replacement Class Measure Item Description Description of Work Test (Yes or No) Completed Plan Number E-A 2-X-2 General Corrosion on Restored design wall thickness Yes 3/25/05 584530-01 Penetration Sleeve Exterior by welding on Interior surface.

Surfaces In accordance with 10CFR50.55a (b)(2)(ix)(A), the inaccessible areas of the containment liner which displayed evidence of degradation are addressed below.

(1) Blistering and bulging was identified during general visual examinations in 1-X-2. As a consequence of this, engineering directed inspections were conducted on the Unit 2 Personnel Airlock Penetration Sleeve 2-X-2.

Contingency Work Order 584530 was developed prior to the outage to support inspection and repair of the liner, additionally, the Specification for Containment Structures Steel Liners, Spec. 015-001 was revised to provide a minimum design wall thickness for the life of the plant. Ultrasonic measurements were taken to assess liner thickness in areas identified as bulged. The ultrasonic measurements indicated that the liner thickness in the area of the bulging was below the expected wall thickness for the liner when compared with the design drawings. Based on the inspection results from Unit 1, wastage on the exterior surface of the Drywell Personnel Airlock penetration was attributed to surface corrosion as a result of a material defect occurring during construction.

(2) Areas of the liner which were below the minimum design wall thickness were restored to the design wall thickness specified in Spec. 015-001. W/O 584530 provided instructions for this repair.

I OENP-16 I Rev. 43 I

A I I v ATTACHMENT 2 Page 2 of 2 Code Case N-532 Tables 1, 2, and 3 (3) The repair to this area is complete. Relief Request CIP-05, "Successive Examinations Following a Repair" provides for relief from conducting augmented examinations of this component.

I OENP-1 6 Rev. 43 I I lI .EP Rev 43