( ., DUKE Brunswick Nuclear Plant P.O. Box 10429 ENERGY Southport, NC 28461 November 2, 2017 Serial: BSEP 17-0100 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Subject:

Brunswick Steam Electric Plant, Unit Nos. 1 and 2 Renewed Facility Operating License Nos. DPR-71 and DPR-62 Docket Nos. 50-325 and 50-324 Fifth 10-Year lnservice Testing Interval

Reference:

1. Letter from Annette H. Pope (Duke Energy) to the U.S. Nuclear Regulatory Commission Document Control Desk, Fifth 10-Year lnservice Testing {/ST)

Program, dated October 27, 2016, ADAMS Accession Number ML16320A005 Ladies and Gentlemen:

The purpose of this letter is to notify the NRC that Duke Energy Progress, LLC (Duke Energy),

is delaying the planned start date for the next lnservice Testing (IST) Program interval for the Brunswick Steam Electric Plant (BSEP), Unit Nos. 1 and 2. By Reference 1, Duke Energy informed the NRC that the fifth 10-year IST interval start date was being adjusted from the previously scheduled start date (i.e., May 11, 2018) to November 1, 2017. Due to delays encountered during the update process, Duke Energy is delaying the fifth 10-year IST interval start date to December 22, 2017.

Please refer any questions regarding this submittal to Mr. Lee Grzeck, Manager - Regulatory Affairs, at (910) 832-2487.

Sincerely,

~-

Bryan B. Wooten

& f/)~

Director - Organizational Effectiveness Brunswick Steam Electric Plant

U.S. Nuclear Regulatory Commission Page 2 of 2 cc: U.S. Nuclear Regulatory Commission, Region II ATTN: Ms. Catherine Haney, Regional Administrator 245 Peachtree Center Ave, NE, Suite 1200 Atlanta, GA 30303-1257 U.S. Nuclear Regulatory Commission ATTN: Mr. Gale Smith, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 U.S. Nuclear Regulatory Commission ATTN: Mr. Andrew Hon (Mail Stop OWFN 8G9A) (Electronic Copy Only) 11555 Rockville Pike Rockville, MD 20852-2738 Andrew.Hon@nrc.gov Chair - North Carolina Utilities Commission (Electronic Copy Only) 4325 Mail Service Center Raleigh, NC 27699-4300 swatson@ncuc.net Mr. Cliff Dautrich, Bureau Chief North Carolina Department of Labor Boiler Safety Bureau 1101 Mail Service Center Raleigh, NC 27699-1101