3F0418-03, ISFSI Only Emergency Plan Implementing Procedures

From kanterella
(Redirected from 3F0418-03)
Jump to navigation Jump to search
ISFSI Only Emergency Plan Implementing Procedures
ML18110A189
Person / Time
Site: Crystal River  Duke Energy icon.png
Issue date: 04/17/2018
From: Dixon P
Duke Energy Florida
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
3F0418-03
Download: ML18110A189 (2)


Text

SECURITY - RELATED INFORMATION -WITHHOLD UNDER 10 CFR 2.390(d)

U.S. Nuclear Regulatory Commission Page 2 of 2 3F0418-03 If you have any questions regarding this submittal, please contact Mr. Phil Rose, Licensing Lead, Nuclear Regulatory Affairs, at (352) 501-4883.

Sincerely,

~~

Phyllis A. Dixon Manager - SAFSTOR Technical Support Crystal River Nuclear Plant PAD/par

Enclosures:

1. List of Revision to the ISFSI Only Emergency Plan Implementing Procedure
2. 10 CFR 50.54(q)(5) Analysis Summary
3. Copy of Revised ISFSI Only Emergency Plan Implementing Procedures SECURITY- RELATED INFORMATION xc: NMSS Project Manager Regional Administrator, Region I SECURITY - RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390(d)

WHEN SEPARATED FROM ENCLOSURE 3 THIS LETTER IS DECONTROLLED

SECURITY - RELATED INFORMATION -WITHHOLD UNDER 10 CFR 2.390(d)

Crystal River Nuclear Plant

(~DUKE 15760 W. Power Line Street

~ ENERGY Crystal River, FL 34428 Docket 50-302 Docket 72-1035 Operating License No. DPR-72 10 CFR 50.4(b )(5)(iii) 10 CFR 50.54(q)(5) 10 CFR 50, Appendix E April 17, 2018 3F0418-03 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-001

Subject:

Crystal River Unit 3 - ISFSI Only Emergency Plan Implementing Procedures

Dear Sir:

In accordance with 10 CFR 50.4(b)(5)(iii), 10 CFR 50.54(q)(5), and 10 CFR 50, Appendix E, Section V, Duke Energy Florida, LLC (DEF), hereby submits a revision to existing emergency plan implementing procedures for the recently approved and implemented Crystal River Unit 3 (CR-3) Independent Spent Fuel Storage Installation (ISFSI) Only Emergency Plan (IOEP). One of these implementing procedures has been determined to contain Security Related Information (SRI).

Implementing procedures specifically address elements of the IOEP that directly aid in the mitigation of, or lessen the impact of, an emergency. Implementing procedures provide direction and information used during an actual emergency in areas such as: assessing the significance of an emergency condition, staff augmentation, responsibilities and actions of emergency and non-emergency personnel, emergency notifications, and assessment of radiological releases.

CR-3 has revised multiple IOEP implemepting procedures due to the recently approved Amendment No. 253 for the IOEP. The revised procedures are: Al 4000, Al 4001, EM 205, EM 502, EM 504, HPP 334, ISFS 190, TPP 219, and EM-911 D. EM911 D does contain Security Related Information; as such, it must be withheld from the pu~lic in accordance with 10 CFR 2.390(d).

Enclosure 1 lists the revised implementing procedures. Enclosure 2 provides the 10 CFR 50.54(q)(5) analysis summary for the revised implementing procedures. Enclosure 3 provides a copy of the revised implementing procedures.

There are no new regulatory commitments contained within this letter.

SECURITY - RELATED INFORMATION-WITHHOLD UNDER 10 CFR 2.390(d)

WHEN SEPARATED FROM ENCLOSURE 3 THIS LETTER IS DECONTROLLED