05000461/FIN-2010002-03
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Interconnecting Floor Drains Between the Residual Heat Removal A Pump Room and Radwaste Pipe Tunnel |
Description | The inspectors identified a finding of very low safety significance with an associated Non-Cited Violation of 10 CFR 50, Appendix B, Criteria III, Design Control, regarding the licensees failure to correctly translate the design basis into the design of the Auxiliary Building floor drain system with appropriate margin. The inspectors identified that floor drains in the Residual Heat Removal (RHR) A Pump Room and the Radwaste Pipe Tunnel were interconnected, which resulted in the plant being in an unanalyzed condition that degraded plant safety and could have prevented fulfillment of the safety function of the containment suppression pool. To address the immediate operability concern, the licensee plugged the two floor drains in the Radwaste Pipe Tunnel line to prevent communication with the floor drain system in the RHR A Pump Room. An exposed vertical section of the drain line was then cut and a solid steel plate welded into the pipe per an engineering design change to permanently isolate the floor drains between the two rooms. The finding was of more than minor significance because it was associated with the Design Control attribute of the Mitigating Systems Cornerstone and affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Specifically, the as-found configuration of the interconnecting floor drains resulted in the plant being in an unanalyzed condition that could have prevented fulfillment of the safety function of the containment suppression pool. Although the finding would represent a loss of safety function in the event of a postulated accident, it was determined to be of very low safety significance during a Phase 3 Significance Determination Process review because the delta core damage frequency was determined to be negligible since the initiating event frequency for flooding due to an RHR pump suction pipe failure was sufficiently low. Because this condition had existed since initial plant construction, the performance issue did not necessarily reflect current licensee performance and no cross-cutting aspect was identified |
Site: | Clinton |
---|---|
Report | IR 05000461/2010002 Section 1R06 |
Date counted | Mar 31, 2010 (2010Q1) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.06 |
Inspectors (proximate) | M Holmberg R Jickling R Langstaff J Cassidy B Metrow B Kemker M Ring S Mischke D Lords E Coffman J Draper A Scarbeary D Sand |
INPO aspect | |
' | |
Finding - Clinton - IR 05000461/2010002 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Clinton) @ 2010Q1
Self-Identified List (Clinton)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||