Finding | |
---|---|
Title | Failure to provide adequate decommissioning funding assurance from Dec. 31, 2008 through the present (10 CFR 50.75(b)) |
Description | First, 10 CFR 50.75(b) requires, in part, that each holder of a power reactor operating license submit a decommissioning report that contains a certification that financial assurance for decommissioning has been provided in an amount which may be more, but not less, than the amount stated in the table in 10 CFR 50.75(c)(1). Contrary to the above, from December 31, 2008, to the present time, Entergy failed to provide sufficient financial assurance certification for River Bend Station. Specifically, Entergy failed to provide financial assurance for decommissioning in an amount which was more than the amount stated in 10 CFR 50.75(c)(1) by having a shortfall of $164 million |
Site: | River Bend |
---|---|
Report | IR 05000458/2010004 Section 4OA5 |
Date counted | Sep 30, 2010 (2010Q3) |
Type: | AV: |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | |
Inspectors (proximate) | P Elkmann C Osterholtz R Hagar G Larkin V Gaddy C Norton D Strickland R Kumana C Stancil G Guerra |
INPO aspect | |
' | |