Finding | |
---|---|
Title | Inadequate Compensatory Measures for Inoperable Hose Stations |
Description | The inspectors identified a non-cited violation of Technical Specification 5.4.1.d for the failure of the licensee to place signs at inoperable fire hose stations and at the compensatory fire hoses identifying the purpose and location of the compensatory measures. The inspectors determined that the licensees compensatory actions were complex, undocumented, and not communicated to the fire brigade leader. As a result, the compensatory actions for inoperable hose stations were inadequate. The licensee entered the finding into the corrective action program as Condition Report CR-2012-006524. The licensees failure to place signs at the inoperable fire hose stations and at the compensatory fire hoses identifying the purpose and location of the compensatory measures was a performance deficiency. The finding was more than minor because it was associated with the protection against external factors attribute of the mitigating systems cornerstone and adversely affected the cornerstone objective to ensure the availability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the fire protection compensatory actions for inoperable hose stations were inadequate. Using NRC Inspection Manual Chapter 0609, Significance Determination Process, Attachment 4, Appendix A, Exhibit 2, d.3.c, the finding was referred to NRC Inspection Manual Chapter 0609, Appendix M, Significance Determination Process Using Qualitative Criteria. A senior reactor analyst evaluated the finding and determined qualitatively that the resultant increase in risk would be of very low safety significance. The finding has a human performance cross-cutting aspect associated with decision-making because the licensee failed to communicate decisions to personnel who have a need to know the information in order to perform work safely. |
Site: | Comanche Peak |
---|---|
Report | IR 05000445/2012004 Section 1R05 |
Date counted | Sep 30, 2012 (2012Q3) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.05 |
Inspectors (proximate) | G Guerra W Walker B Tindell D Proulx J Kramer K Wood |
CCA | H.10, Bases for Decisions |
INPO aspect | CO.2 |
' | |