05000440/FIN-2009005-04
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Excess Dose Incurred for the Alternate Decay Heat Removal Project |
Description | The inspectors identified a finding of very low safety significance for inadequate job planning and ineffective work controls which adversely impacted the licensees ability to minimize dose for the alternate decay heat removal (ADHR) project during Refuel Outage 12. Specifically, controls were not effectively implemented to reduce ambient radiation levels, and minimize in-field work hours for craft personnel. The issue resulted in an actual dose outcome that was not consistent with the planned, intended dose for work associated with modifications to the ADHR. Corrective actions were implemented to address the organization and programmatic deficiencies in managing the installation of major plant modifications. The finding was more than minor because it impacted the Occupational Radiation Safety Cornerstone objective for ensuring adequate protection of worker health and safety from exposure to radiation in the attribute of program and process for ALARA planning, in that, ineffective ALARA planning and work control deficiencies contributed to an actual increase in worker doses in excess of five person-rem and exceeded the licensees initial intended dose estimates by more than 50 percent. The finding did not involve: (1) an overexposure; (2) a substantial potential for an overexposure; or (3) an impaired ability to assess dose. While the finding involved ALARA planning and controls, the3-year rolling average dose for the Perry Plant was less than the SDP threshold of240-person-rem for boiling water reactors at the time the performance deficiency occurred. Consequently, the inspectors concluded through the SDP assessment that this is a finding of very low safety-significance. The finding was determined to be associated with a cross-cutting aspect in the area of human performance in work controls, per IMC 0305 H.3.a., in that, the licensee did not appropriately plan work activities by incorporating radiological safety. |
Site: | Perry |
---|---|
Report | IR 05000440/2009005 Section 4OA5 |
Date counted | Dec 31, 2009 (2009Q4) |
Type: | Finding: Green |
cornerstone | Or Safety |
Identified by: | NRC identified |
Inspection Procedure: | |
Inspectors (proximate) | A Wilson J Tapp R Russell E Coffman R Leidy J Cameron P Voss T Hartman P Smagacz E Denison M Marshfield D Szwarc W Slawinski C Moore M Phalen M Bielby |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |