05000416/FIN-2014004-02
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | |
Description | The inspectors reviewed a self-revealing finding for the licensee's failure to follow procedure EN-LI-102, "Corrective Action Process, Revision 12, which requires the licensee to appropriately complete assigned corrective actions within the prescribed time frame. On March 29, 2014, with Grand Gulf Nuclear Station operating at 87 percent power, a capacitor in a multiplier module of the main turbine overspeed protection circuit failed, causing the load reject relay to actuate. The main turbine control valves closed and an automatic actuation of the reactor protection system occurred, resulting in a plant scram. The root cause analysis noted that a corrective action initially assigned in 2007 in association with a single point vulnerability review was not completed in the prescribed time frame. The corrective action required that the module in question, which contained a single point vulnerability, either be rebuilt so as to reduce the probability that an age-related failure capable of triggering the vulnerability would occur, or replaced with a new design that eliminated the vulnerability altogether. The licensee entered this issue into the corrective action program under Condition Report CR-GGN-2014-03131. Immediate corrective actions following the scram included replacing the failed module with a spare module that had been visually inspected and functionally checked. Long term corrective actions include replacing the module with a component that does not exhibit single point vulnerability. The licensee's failure to follow procedure by failing to appropriately complete assigned corrective actions was a performance deficiency. The performance deficiency was more than minor, and therefore a finding, because it was associated with the equipment performance attribute of the Initiating Events Cornerstone and adversely affected the cornerstone objective, in that it increased the likelihood of those events that upset plant stability and challenge critical safety functions during power operations. Using NRC Inspection Manual Chapter 0609, Attachment 4, "Initial Characterization of Findings," dated June 19, 2012, the inspectors determined that the issue affected the Initiating Events Cornerstone. Using Inspection Manual Chapter 0609, Appendix A, "The Significance Determination Process for Findings At-Power," dated June 19th, 2012, the finding was determined to be of very low safety significance (Green) because the finding did not contribute to both the likelihood of a reactor trip and the likelihood that mitigating equipment would not be available. The finding was a latent issue and is not reflective of present licensee performance; therefore, no cross-cutting aspect was assigned. |
Site: | Grand Gulf ![]() |
---|---|
Report | IR 05000416/2014004 Section 4OA3 |
Date counted | Sep 30, 2014 (2014Q3) |
Type: | Finding: Green |
cornerstone | Initiating Events |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71153 |
Inspectors (proximate) | B Baca B Parks B Rice G George M Williams P Nizov |
INPO aspect | |
' | |
Finding - Grand Gulf - IR 05000416/2014004 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Grand Gulf) @ 2014Q3
Self-Identified List (Grand Gulf)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||