| Q | CCA | Title |
---|
05000397/FIN-2009002-01 | 2009Q1 | H.5 | Failure to Perform Engineering Evaluation to Determine Seismic Qualification of Safety related Equipment |
05000397/FIN-2009002-02 | 2009Q1 | H.14 | Failure to Perform an Adequate Site Acceptance Test |
05000397/FIN-2009003-02 | 2009Q2 | H.5 | Reactor Scram Due to Seal Oil Leak for Main Generator |
05000397/FIN-2009003-01 | 2009Q2 | P.5 | Failure to Barricade and Conspicuously Post a High Radiation Area |
05000397/FIN-2009009-01 | 2009Q3 | H.1 H.2(d) | Failure to Provide Adequate Respiratory Protection Equipment for Emergency Response |
05000397/FIN-2009008-01 | 2009Q3 | H.2(a) H.6 | Failure to Promptly Replace Keep Fill Pumps |
05000397/FIN-2009008-03 | 2009Q3 | P.1 P.1(a) | Failure to Follow Housekeeping Program Requirements |
05000397/FIN-2009008-02 | 2009Q3 | | Failure to Ensure Suitability of Class 1E Electrical Components |
05000397/FIN-2009202-01 | 2009Q3 | | Security |
05000397/FIN-2009004-01 | 2009Q3 | P.3 | Failure to Adequately Implement the Requirements of Procedure SOP-ENTRY-DW |
05000397/FIN-2009004-02 | 2009Q3 | H.4 H.5 | Failure to Perform Back-up Monitoring |
05000397/FIN-2009005-03 | 2009Q4 | H.4 H.5 | Failure to Notify Radiological Planning Personnel of a Work Plan Deviation |
05000397/FIN-2009403-01 | 2009Q4 | H.10 | Security |
05000397/FIN-2009005-01 | 2009Q4 | H.13 | Failure to Classify a Notification of Unusual Event During a Toxic Gas Event |
05000397/FIN-2009005-04 | 2009Q4 | H.7 | Failure To Submit An Outage Job To The Senior Site ALARA Committee For Review |
05000397/FIN-2009005-02 | 2009Q4 | H.11 H.12 | Failure to Follow Radiation Protection Requirements |
05000397/FIN-2009005-05 | 2009Q4 | H.7 | Digital Electro-Hydraulic Leak Results in Reactor Scram |