| | Q | CCA | Title |
|---|
| 05000397/FIN-2008005-01 | 2008Q4 | P.2 | Failure to follow procedures during an overhaul of emergency diesel engine 1A1 |
| 05000397/FIN-2008005-02 | 2008Q4 | | Failure to translate design basis into procedures for residual heat removal operating modes |
| 05000397/FIN-2009002-02 | 2009Q1 | H.14 | Failure to Perform an Adequate Site Acceptance Test |
| 05000397/FIN-2009002-01 | 2009Q1 | H.5 | Failure to Perform Engineering Evaluation to Determine Seismic Qualification of Safety related Equipment |
| 05000397/FIN-2009003-02 | 2009Q2 | H.5 | Reactor Scram Due to Seal Oil Leak for Main Generator |
| 05000397/FIN-2009003-01 | 2009Q2 | P.5 | Failure to Barricade and Conspicuously Post a High Radiation Area |
| 05000397/FIN-2009004-01 | 2009Q3 | P.3 | Failure to Adequately Implement the Requirements of Procedure SOP-ENTRY-DW |
| 05000397/FIN-2009009-01 | 2009Q3 | H.1 H.2(d) | Failure to Provide Adequate Respiratory Protection Equipment for Emergency Response |
| 05000397/FIN-2009008-01 | 2009Q3 | H.2(a) H.6 | Failure to Promptly Replace Keep Fill Pumps |
| 05000397/FIN-2009008-03 | 2009Q3 | P.1 P.1(a) | Failure to Follow Housekeeping Program Requirements |
| 05000397/FIN-2009008-02 | 2009Q3 | | Failure to Ensure Suitability of Class 1E Electrical Components |
| 05000397/FIN-2009004-02 | 2009Q3 | H.4 H.5 | Failure to Perform Back-up Monitoring |
| 05000397/FIN-2009202-01 | 2009Q3 | | Security |