Finding | |
|---|---|
| Title | Failure to Perform Engineering Evaluation to Determine Seismic Qualification of Safety related Equipment |
| Description | The inspectors identified a noncited violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, for Energy Northwests failure to follow procedure PPM 10.2.53, Seismic Requirements for Scaffolding, Ladders, Man-Lifts, Tool Gang Boxes, Hoists, Metal Storage Cabinets, and Temporary Shielding Racks, Revision 26. Specifically, the position of equipment is required to meet specific criteria to prevent damage to safety-related equipment during a seismic event. Contrary to this procedure, the inspectors identified that equipment was routinely positioned next to safety-related equipment without a supporting engineering evaluation. This finding is greater than minor because it was a human performance error which affected the mitigating systems cornerstone objective to ensure the availability and reliability of systems that respond to initiating events to prevent undesirable consequences. This was determined to be consistent with NRC Manual Chapter 0612, Power Reactor Inspection Reports, Appendix E, Example 4.a. for being more than minor risk significance because Energy Northwest had routinely failed to perform the requisite engineering evaluation. The finding was determined to be of very low risk significance (Green) because no actual loss of safety function occurred and the finding did not screen as potentially risk significant due to external events. Specifically, the as-found position of the equipment was determined to not adversely affect seismic qualification of the affected safety-related components. A crosscutting aspect in human performance with a work control component was identified in that Energy Northwest failed to appropriately plan work on multiple occasions, resulting in job site conditions which may have impacted plant components H.3.a] |
| Site: | Columbia |
|---|---|
| Report | IR 05000397/2009002 Section 1R04 |
| Date counted | Mar 31, 2009 (2009Q1) |
| Type: | NCV: Green |
| cornerstone | Mitigating Systems |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71111.04 |
| Inspectors (proximate) | C Graves R Cohen W Walker N Hernandez |
| CCA | H.5, Work Management |
| INPO aspect | WP.1 |
| ' | |