Finding | |
---|---|
Title | Inadequate Procedure for Reactivity Manipulations |
Description | The inspectors identified a non-cited violation of Technical Specification 5.5.1.1 for the failure of operations personnel to follow procedures for performing reactivity manipulations. Specifically, a procedure modification performed to Procedure SO23-3-2.19.2, Control Element Assembly Exercise and Troubleshooting, was inaccurate and incomplete to appropriately control reactivity manipulations, and thus, an adequate procedure was not in hand as required by Procedure SO123-O-A1, Conduct of Operations, to appropriately control the control element assembly manipulations by a licensed operator. This finding was entered into the licensees corrective action program as Nuclear Notification 200339686. The finding is greater than minor because it is associated with procedure quality attribute of the Initiating Events Cornerstone and affects the cornerstone objective of limiting the likelihood of those events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Using Manual Chapter 0609, Significance Determination Process, Appendix G, Shutdown Operations Significance Determination Process, Checklist 4, the finding is determined to have very low safety significance because the finding did not increase the likelihood of a loss of reactor coolant system inventory, degrade the ability to terminate a leak path, or degrade the ability to recover decay heat removal. This finding has crosscutting aspect in the area human performance associated with work control because the licensee did not appropriately plan a work activity [H.3.(a)] |
Site: | San Onofre |
---|---|
Report | IR 05000361/2009002 Section 1R19 |
Date counted | Mar 31, 2009 (2009Q1) |
Type: | NCV: Green |
cornerstone | Initiating Events |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.19 |
Inspectors (proximate) | P Elkman T Steadham J Reynoso G Warnick C Osterholtz M Hay |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |