05000275/FIN-2016007-03 | 2016Q1 | H.14 | Failure to Ensure Safety-Related Alternating Current and Direct Current Equipment Functionality at Maximum Allowable Voltages |
05000275/FIN-2016007-04 | 2016Q1 | H.6 | Failure to Evaluate the Extent of Condition for a Degraded Condition on a Nonsafety-Related 4160 Vac Breaker |
05000275/FIN-2016007-05 | 2016Q1 | H.6 | Failure to Evaluate the Voltage Effects of Limiting Design Basis Events on the 230 kV Offsite Power Circuit |
05000275/FIN-2016007-06 | 2016Q1 | H.6 | Failure to Translate Appropriate Load Tap Changer Timing Acceptance Criteria into Periodic Tests |
05000275/FIN-2016007-02 | 2016Q1 | P.2 | Failure to Promptly Correct the Lack of Design Verification of 460 Vac Motors at Maximum Allowable Frequency |
05000275/FIN-2016007-01 | 2016Q1 | | Failure to Evaluate 480 Vac Motor Starters with Circuit Breaker Trip Settings Higher than Manufacturers Specifications |
05000275/FIN-2016001-01 | 2016Q1 | | Failure to Verify Adequate Design Airflow for 480 volt AC Switchgear and 125 volt DC Inverter Rooms |
05000275/FIN-2016301-01 | 2016Q2 | H.1 | Insufficient Procedural Direction Contained Within Procedure EOP E-2, Faulted Steam Generator Isolation |
05000323/FIN-2016002-01 | 2016Q2 | H.12 | Misplaced Spent Fuel Assembly in the Spent Fuel Pool |
05000323/FIN-2016010-01 | 2016Q3 | | Failure to Establish Adequate Work Instructions for Installation of Namco Snap Lock Limit Switches |
05000275/FIN-2016403-01 | 2016Q4 | H.7 | Security |
05000323/FIN-2016004-01 | 2016Q4 | H.7 | Failure to Follow Maintenance Procedure Resulted in Improper Configuration of Safety Related Equipment |