LER-1981-027, Forwards LER 81-027/03L-0.Detailed Event Analysis Encl |
| Event date: |
|
|---|
| Report date: |
|
|---|
| 2671981027R00 - NRC Website |
|
text
.
pubuc Service Company
& CcHendo
,)
16805 ROAD 19%
. 'u. _ s PLATTEVILLE, COLOR ADO 80651
\\
May 13, 1981 g
e Fort S t.
Vrain V.gs D
/
F y '\\
Unit No. 1 M
0 '\\
b F
P-81143
! l.y bg\\
f.i
'3
\\y..,
- - l'l.
..w
?,
';T "
Mr. Karl V. Seyf rit, Director C
Nuclear Regulatory Commission Region IV Of fice of Inspection and Enforcement 611 Ryan Plaza Drive Suite 1000 Arlington, Texas 76012 Reference: Facility Operaciag License No. DP R-34 Docket No. 50-267
Dear Mr. Seyf rit:
Enclosed please find,a copy of Reportable Occurrence Report No. 50-267/
81-027, Final,, submitted per the requirements of Technical Specification AC 7.5.2(b)2.
Also, please find enclosed one copy of the Licensee Event Report for Reportable Occurrence Report No. 50-267/81-027.
Very truly yours,
d $s L?s Don Warembourg Manager, Nuclear Production DW/cls Enclosure g
I cc:
Director, MIPC
//
Td106030 W S
REPORT DATE:
May 13, 1981 REPORTABLE OCCURRENCE 81-027 ISSUE O OCCURRENCE DATE:
Aoril 13, 1981 Page 1 of 5 FORT ST. VRAIN NUCLEAR GENERATING STATION PUBLIC SERVICE COMPANY OF COLORADO 16805 WELD COUNTY ROAD 191/2 PLATTEVILLE, Col.0RADO 80651 REPORT NO. 50-267/81-027/03-L-0 Final IDENTIFICATION OF OCCURRENCE:
Between April 12, 1981, and April 25, 1981, the plant was operated in a degraded mode of LCO 4.2.10 on five separate occasions.
These events are reportable per Fort St.
Vrain Technical Specification AC 7.5.2(b)2.
EVENT
DESCRIPTION
Event #1.
See Figure 1.
On April 12, 1981, at 1300 hours0.015 days <br />0.361 hours <br />0.00215 weeks <br />4.9465e-4 months <br />, a plant power increase to approximately 60% power was initiated.
By midnight, the core average outlet temperature was greater than 1200 degrees fahrenheit.
The total primary coolant oxidants, the sum of moisture, carbon monoxide, and carbon dioxide, had exceeded 10 parts per million (ppm). Total oxidants had peaked and started to decrease by noon of April 13. At 1435 hours0.0166 days <br />0.399 hours <br />0.00237 weeks <br />5.460175e-4 months <br />, an electrical problem occurred on reactor plant motor control cabinet #1, which resulted in a reactor scram at 1440 hours0.0167 days <br />0.4 hours <br />0.00238 weeks <br />5.4792e-4 months <br />.
Event #2.
On April 15, 1981, during the plant recovery from the scram of April 13, average core outlet temperature was increased te greater than 1200 degrees fahienheit.
As power increased, the primary coolant oxidants also increased until at 0930 hours0.0108 days <br />0.258 hours <br />0.00154 weeks <br />3.53865e-4 months <br />, the 10 ppm limit was exceeded.
The power level was gradually increased over the next several days to approximately 80%.
During this time, the total primary coolant oxidants cecreased.
On April 19, at 0135 hours0.00156 days <br />0.0375 hours <br />2.232143e-4 weeks <br />5.13675e-5 months <br />, a hot reheat scram occurred.
Events #3 and #4.
On April 22, 1981, at 2200 hours0.0255 days <br />0.611 hours <br />0.00364 weeks <br />8.371e-4 months <br />, and again on April 23, at 1400 hours0.0162 days <br />0.389 hours <br />0.00231 weeks <br />5.327e-4 months <br />, during the plant recovery f*om the scram of April 19, primary coolant total oxidants temporarily exceeded 10 ppm.
Event
- 5.
On April 23, while power was being increased to approximately 30%, the total primary coolant oxidants again exceeded 10 opm.
The oxidants increased until a hot reheat scram occurred at 0143 hours0.00166 days <br />0.0397 hours <br />2.364418e-4 weeks <br />5.44115e-5 months <br /> on April 25.
T.hroughout this ceriod, the helium purificator system was in operation removing contaminants from the helium.
i 1
REPORTABLE OCCURRENCE 81-027 ISSUE 0 Page 2 of 5
CAUSE
DEscRIprION:
Event #1.
The increase in primary coolant oxidants is being attributed to off gassing from the core due to increasing core temperatures during the plant startup.
Event #2.
The increase in prima ry coolant oxidants is being attributed to the moisture ingress, which resulted from the Loop 2 trip and hot reheat scram of April 13.
Events #3, #4, and #5. The increase in primary coolant oxidants is being attributed to the moisture ingress, which resulted from the circulator trip and reactor scram of April 19 and the Loop 2 trip of April 20.
CORRECTIVE A.C. TIOM -
Events #1, #2, and #5 were terminated by reactor scrams and turbine trips.
Events #3 and #4 were individual readings greater than 10 pom and no,
corrective action was taken.
There was no affect on public health or safety.
1
REPORTABZI OCCURRENCE 81-027 ISSUE O A
b H 2 =r.=?.
O Page 3 of 5 4./2-3/
a v f **
- 44*
- 4F-8/
vV4
MW e
1 9
f
.e I
I o e r e
e u
e o
.e 4
4.
s e
1a f 6 4
$ { g e
e e
I g 6
e o $ $e o
J e
6
,, __ _.' 40 og. $t t T $ $ _1 I 1 $ % % $ S ! $ $ # $
P e e b
e g(oo ;
---i
_.._4
- :... r _-_--a
_-- _. ; y
---.s 60
_ _ _. _. 1_
=. - - - - s.:..=:
-- i
= = - *
"-d ss Avr Ooet curttr TGmP e. ne w
Tarns. Fuusy & f.,rsus>>n
--- y e
w- =- x -x
' 3 2.
se So ee' 1980 1
M 10:
a---m----~
n-P F-7 *--
^
a s.
- - pM h, -f.N-"
..a
.S
~
^^Ik- --'
- - t u---P M'_.
%py'"
u A.
s s
._e.,_
w
,-e.
l f.o.
- tZ.
!K
,e N
g 800e pr
,y
-. bh M7
_M-
$4 L >T
- g
$O-
, - (qgg af - /-i 4,
f--.s-- W v-at
.-:: :_ : w.
2
>t.---- J i--x--/-,/_.s=m /
as r - - -s-:-
- -/ -.
L:,: :,: ;-w i 1
~~ r -':
. 1 A
1 --
-/-/~,"
'^!
. 9:-
+-n.: L
- s--
r,n nr k.
'f----
/
4
+
Y f..%,"., $,.,;h,,:1-il,
. ?,, ; l '-
- _; -;,p.s
_.2-t,
su
-, /t
, "-+,
' Q:-'
-- : /' '-" p" ' ' /---/-,
,l/---2-ar 1"
l L" -": ': ': ": ',__;": : : - /---/
- - s
- = - -
- ' -~f--J-1
~
m-
~ *
' t.
x
,D F 7.' T
.-1r:
y W
d QL' W
3 TD h
2,D
.2.
PounORiGliiAl.*
~
REPORTABLE OCCUPJu21CE 81-026
~
g x I '.r::: ':l O*.ll'.':.**
ISSUE O Pcg2 4 cf 5 4.n oi r.wot
.t.w t
+.ns et o-e s
.4e H /
ns+'
i
- s
- : i I:
1 1 : : 1 f j1
- 1 t t i i stss i 1. ::
- s i st es i
- 2. s 15 s : :
f tSoo: s : e W
+ - m ; -- _-- !=.- :: { c-*' r: r ~ =! =._..... _....
r; =rr I
_7.___
._.._ t = : =.= rr
=-
..__.4..a._...
==:: ;. :- 3_. ;.-.=- ~ r.~=*r. :T _. :.: ;-- -...
c--
.=u.
w_.~~,
_.. _. _. = - -
_d
... _. g_~~._ :.j
- {
=gQg g
o-o-o-*._
Ge
- - r = :. :
u
. ju
=
- - m = } = --, =. := g= : =
- Tes Ibesy b df C e aT5 g
n._-_7=,
.3 y ~=
g
_ a a
+-- -. - -.r x x r_-
- - p _.. :-..
g.
4
^~ RD y,7 4
+--
Me e._
-+
__._. ;- r 1 -I~~r+.
g g.
4___
p
- - y :;_.._.
[EE!hU$
k: -- _c5-.-.21 rw=-t.
u
.j_
g l[=
w]
.~~._~ at :
- - _.e
_._-...(--__..__..____._._._..
.-- ;f'It 1
+
ro
~.__;,
.=_.,__ j._
q_
.... _ g=
+
_. _p-_. :
_- _4 r.. - m; -. p.
3 ' = -
4---- ~ i g..
.---J-!
--]
y
"-9""*r s.
, ---i. g, g=.
- f --- +-. y._ -
__g-~ 7 4
- - p,
m __ l 4
gs.
~~~~~
WY 5_? I.
._, jf l
=
{'
g5 d. c.
g._
.l b
h.____
y' w =sj:':
g s.
g i
N
?
Sm47
..it __
__ i A" fg
- 1. -
g t
J!
a:-._ f u.
w E
f-q K rf.-~~f.:"
JC '
?
{V W
._+
,s v =.:_.
\\.
1=/=./-
v.
+.-
- g
--k
- p
---f=7.It-
~
w nf
.2 s
1 __ -4 i
f-_
k Iti
~,, -
E_
=
Y u-ag-,
gs.
g..
i.
2_.
_y__,_3
. }-/.-- __f
.. T _.. -._ y __
I---M[._ g jr.
yg.3..._._._ ::=.- =_._<.....
- = _.
- =
- ._.t=
_4--
y
. -g i. W mg#
a 60
.r-i._._.._w e
= +.. _., V ft_- t, _,-
- - s 7
._r 3
M te.
[%_ :.l
.,"L
- .f 3
- - m.
y.-
.r 1 n -
q
(~
_p, ge
~.
,, ~ ~ S..,
,f '
y,,
'A B
M e-mm-
- - dE'E
^#E-i E 5-EUR 2 g ypp r
P UUN UK li IM L
REPORTABLE OCCURRENCE 81-028 ISSUE O l
Page 5 of 5 Prepared By:
IM Asa T. Keec
. Technical Services Technician i
Reviewed By:
/TechnicalServicesSupervisor
. W. 4anm Reviewed By:
Frank M. Mathie Operations Manager Approved By:
- h Don Warembourg Manager, Nuclear Production 4
,,.7,
|
|---|
|
|
| | | Reporting criterion |
|---|
| 05000267/LER-1981-001, Forwards LER 81-001/03L-0.Includes Narrative Description of Event Re High Outlet Temp in Pcrv Cooling Water Sys | Forwards LER 81-001/03L-0.Includes Narrative Description of Event Re High Outlet Temp in Pcrv Cooling Water Sys | | | 05000267/LER-1981-001-03, /03L-0:on 801230,outlet Temp of Loop 2 Pcrv Cooling Water Sys Exceeded Tech Spec Level.Caused by High Setpoint of Cooling Water Temp Controller Following Calibr. Controller Reset & Operators Will Be Reinstructed on Sys | /03L-0:on 801230,outlet Temp of Loop 2 Pcrv Cooling Water Sys Exceeded Tech Spec Level.Caused by High Setpoint of Cooling Water Temp Controller Following Calibr. Controller Reset & Operators Will Be Reinstructed on Sys | | | 05000267/LER-1981-002-03, /03L-0:on 810107,during Normal Operation,Sampling Requirements of SR NR1.1 Found Not Met for Day shift,801225. Caused by Personnel Error.Sampling Resumed on Next Shift & Personnel Reinstructed Re Importance of Requirements | /03L-0:on 810107,during Normal Operation,Sampling Requirements of SR NR1.1 Found Not Met for Day shift,801225. Caused by Personnel Error.Sampling Resumed on Next Shift & Personnel Reinstructed Re Importance of Requirements | | | 05000267/LER-1981-002, Forwards LER 81-002/03L-0 | Forwards LER 81-002/03L-0 | | | 05000267/LER-1981-003-03, /03L-0:on 810106,during Test,One Channel of 1D Helium Circulator Drain Malfunction Found Inoperable.Caused by Blown Switch Module Fuse.Fuse Replaced & Switch Returned to Svc | /03L-0:on 810106,during Test,One Channel of 1D Helium Circulator Drain Malfunction Found Inoperable.Caused by Blown Switch Module Fuse.Fuse Replaced & Switch Returned to Svc | | | 05000267/LER-1981-003, Forwards LER 81-003/03L-0 | Forwards LER 81-003/03L-0 | | | 05000267/LER-1981-004-03, /03L-0:on 810115,high Residual Chlorine Levels Found in Circulating Water Sys Liquid Effluent Sample.Cause Unknown.Subsequent Samples Normal | /03L-0:on 810115,high Residual Chlorine Levels Found in Circulating Water Sys Liquid Effluent Sample.Cause Unknown.Subsequent Samples Normal | | | 05000267/LER-1981-004, Forwards LER 81-004/03L-0 | Forwards LER 81-004/03L-0 | | | 05000267/LER-1981-005, Forwards LER 81-005/03L-0 | Forwards LER 81-005/03L-0 | | | 05000267/LER-1981-005-03, /03L-0:on 810107,during Surveillance Testing,Trip Setting on PDIS-21177 Bearing Water Differential Pressure Switch Found Below Tech Spec Limit.Caused by Instrument Drift.Switch Adjusted & Returned to Svc | /03L-0:on 810107,during Surveillance Testing,Trip Setting on PDIS-21177 Bearing Water Differential Pressure Switch Found Below Tech Spec Limit.Caused by Instrument Drift.Switch Adjusted & Returned to Svc | | | 05000267/LER-1981-006-03, During Annual Testing & Calibr,Six of 12 Helium Circulator Seal Malfunction Pressure Differential Switch Units Tripped Outside Limits.Caused by Dirt Accumulation in Electrical Switches.Switches Replaced | During Annual Testing & Calibr,Six of 12 Helium Circulator Seal Malfunction Pressure Differential Switch Units Tripped Outside Limits.Caused by Dirt Accumulation in Electrical Switches.Switches Replaced | | | 05000267/LER-1981-006, Forwards LER 81-006/03L-0 | Forwards LER 81-006/03L-0 | | | 05000267/LER-1981-007, Forwards LER 81-007/03T-0 | Forwards LER 81-007/03T-0 | | | 05000267/LER-1981-007-03, /03T-0:on 810108,during Pcrv Cooling Water Sys Data Evaluation,Violation of Limiting Conditions of Operation Found Re Loop 2 Inlet & Outlet Average Temp Below Tech Spec Limit.Caused by Insufficient Heat Input | /03T-0:on 810108,during Pcrv Cooling Water Sys Data Evaluation,Violation of Limiting Conditions of Operation Found Re Loop 2 Inlet & Outlet Average Temp Below Tech Spec Limit.Caused by Insufficient Heat Input | | | 05000267/LER-1981-008, Forwards LER 81-008/03L-0 | Forwards LER 81-008/03L-0 | | | 05000267/LER-1981-008-03, /03X-2:on 810120,during Primary Coolant Pressure Scram,Calibr Found Voltage Outputs of Three Pressure Transmitters High.Caused by Instrument Drift.Pressure Transmitters Calibr | /03X-2:on 810120,during Primary Coolant Pressure Scram,Calibr Found Voltage Outputs of Three Pressure Transmitters High.Caused by Instrument Drift.Pressure Transmitters Calibr | | | 05000267/LER-1981-009, Forwards LER 81-009/03L-0.Detailed Event Analysis Submitted | Forwards LER 81-009/03L-0.Detailed Event Analysis Submitted | | | 05000267/LER-1981-009-03, /03L-0:on 810116-0131,plant Operated in Degraded Mode on Five Occasions.Caused by Moisture Outgassing from Core Graphite Due to Increased Power Level.Average Core Outlet Temp Reduced & Purification Sys Removed | /03L-0:on 810116-0131,plant Operated in Degraded Mode on Five Occasions.Caused by Moisture Outgassing from Core Graphite Due to Increased Power Level.Average Core Outlet Temp Reduced & Purification Sys Removed | | | 05000267/LER-1981-010-03, /03L-0:on 810120,five Sample Flow Circuits Found Out of Calibr.Caused by Change of Instrument Characteristics.Calibr Values Revised & Flow Transmitters Recalibr.Alarm Setpoint Functional Test Values Also Changed | /03L-0:on 810120,five Sample Flow Circuits Found Out of Calibr.Caused by Change of Instrument Characteristics.Calibr Values Revised & Flow Transmitters Recalibr.Alarm Setpoint Functional Test Values Also Changed | | | 05000267/LER-1981-010, Forwards LER 81-010/03L-0 | Forwards LER 81-010/03L-0 | | | 05000267/LER-1981-011, Forwards LER 81-011/03L-0 | Forwards LER 81-011/03L-0 | | | 05000267/LER-1981-011-03, /03L-0:on 810121,liquid Nitrogen Storage Tank Level Noted Below Min Required.Caused by Sys Usage & Late Delivery of Liquid Nitrogen.Delivery Restored Tank Levels to Acceptable Values.Second Load Delivered to Top Off Tank | /03L-0:on 810121,liquid Nitrogen Storage Tank Level Noted Below Min Required.Caused by Sys Usage & Late Delivery of Liquid Nitrogen.Delivery Restored Tank Levels to Acceptable Values.Second Load Delivered to Top Off Tank | | | 05000267/LER-1981-012-03, /03L-0:on 810127,six of Twelve Steam Pipe Rupture (Pipe Cavity)Ultrasonic Noise Channels Had Unacceptably Low Response to Known Noise Source During Test.Caused by Microphone &/Or Transmitter Gain Reduced to Stop Tripping | /03L-0:on 810127,six of Twelve Steam Pipe Rupture (Pipe Cavity)Ultrasonic Noise Channels Had Unacceptably Low Response to Known Noise Source During Test.Caused by Microphone &/Or Transmitter Gain Reduced to Stop Tripping | | | 05000267/LER-1981-012, Forwards LER 81-012/03L-0 | Forwards LER 81-012/03L-0 | | | 05000267/LER-1981-013-01, /01T-0:on 810203,following Liquid Waste Release 429,tritium Concentration Exceeded Tech Spec.Caused by Sys Design Inadequacy W/Oil Separator on Liquid Waste Discharge Line.Bypass Installed Around Oil Separator | /01T-0:on 810203,following Liquid Waste Release 429,tritium Concentration Exceeded Tech Spec.Caused by Sys Design Inadequacy W/Oil Separator on Liquid Waste Discharge Line.Bypass Installed Around Oil Separator | | | 05000267/LER-1981-013, Forwards LER 81-013/01T-0.Detailed Event Analysis Submitted | Forwards LER 81-013/01T-0.Detailed Event Analysis Submitted | | | 05000267/LER-1981-014, Forwards LER 81-014/03L-0.Detailed Summary Also Encl | Forwards LER 81-014/03L-0.Detailed Summary Also Encl | | | 05000267/LER-1981-014-03, /03L-0:on 810104,instrument Air Compressors 1C & 1A Out of Svc,Leaving Only Compressor 1B in Svc.Caused by Compressor 1C Tripping on High Discharge Air Temp & Compressor 1A Being Cleared Out for Insp & Repairs | /03L-0:on 810104,instrument Air Compressors 1C & 1A Out of Svc,Leaving Only Compressor 1B in Svc.Caused by Compressor 1C Tripping on High Discharge Air Temp & Compressor 1A Being Cleared Out for Insp & Repairs | | | 05000267/LER-1981-015, Forwards LER 81-015/03L-0.Detailed Event Analysis Encl | Forwards LER 81-015/03L-0.Detailed Event Analysis Encl | | | 05000267/LER-1981-015-03, /03L-0:on 810204-0220,plant Operated in Degraded Mode on Nine Occasions.Causes Include Increased Oxidant Outgassing After Power Increase & Moisture Introduced Into Primary Coolant as Part of Approved Test | /03L-0:on 810204-0220,plant Operated in Degraded Mode on Nine Occasions.Causes Include Increased Oxidant Outgassing After Power Increase & Moisture Introduced Into Primary Coolant as Part of Approved Test | | | 05000267/LER-1981-016-03, During Testing,Three of 12 Helium Circulator Seal Malfunction Pressure Differential Switch Units Tripped Outside Limits.Caused by Dirt Accumulation in Electrical Switches.Switches Replaced | During Testing,Three of 12 Helium Circulator Seal Malfunction Pressure Differential Switch Units Tripped Outside Limits.Caused by Dirt Accumulation in Electrical Switches.Switches Replaced | | | 05000267/LER-1981-016, Forwards LER 81-016/03L-0 | Forwards LER 81-016/03L-0 | | | 05000267/LER-1981-017-03, /03L-0:on 810217,standby Diesel Engine 1B Tripped on High Cooling Water Temp.Caused by Sticking Temp Control Valve.Valve Disassembled,Cleaned & Returned to Svc | /03L-0:on 810217,standby Diesel Engine 1B Tripped on High Cooling Water Temp.Caused by Sticking Temp Control Valve.Valve Disassembled,Cleaned & Returned to Svc | | | 05000267/LER-1981-017, Forwards LER 81-017/03L-0 | Forwards LER 81-017/03L-0 | | | 05000267/LER-1981-018-03, /03L-0:on 810214,sample Flow Alarm Setpoints of Three Dewpoint Moisture Monitors Found Outside Tech Spec. Probably Caused by Previous Misadjustment.Trip Points Readjusted | /03L-0:on 810214,sample Flow Alarm Setpoints of Three Dewpoint Moisture Monitors Found Outside Tech Spec. Probably Caused by Previous Misadjustment.Trip Points Readjusted | | | 05000267/LER-1981-018, Forwards LER 81-018/03L-0.Detailed Event Analysis Encl | Forwards LER 81-018/03L-0.Detailed Event Analysis Encl | | | 05000267/LER-1981-019, Forwards LER 81-019/03L-0.Detailed Event Analysis Encl | Forwards LER 81-019/03L-0.Detailed Event Analysis Encl | | | 05000267/LER-1981-019-03, /03L-0:on 810220,plant Operated in Degraded Mode to Repair Pressure Control Valve PV-21243-1.Caused by Excessive Leakage Through 1/2-inch Masoneilan Pressure Control Valve.Valve Stroke Lengthened.Seat & Stem Replaced | /03L-0:on 810220,plant Operated in Degraded Mode to Repair Pressure Control Valve PV-21243-1.Caused by Excessive Leakage Through 1/2-inch Masoneilan Pressure Control Valve.Valve Stroke Lengthened.Seat & Stem Replaced | | | 05000267/LER-1981-020, Forwards LER 81-020/03L-0.Detailed Event Analysis Encl | Forwards LER 81-020/03L-0.Detailed Event Analysis Encl | | | 05000267/LER-1981-020-03, /03L-0:on 810226,primary Coolant Moisture & Oxidants Exceeded Limits.Caused by Circulator Buffer Sys Upset & Helium Circulator Trip Due to 810223 Reactor Scram. Reactor Power Reduced Until Moisture Level Decreased | /03L-0:on 810226,primary Coolant Moisture & Oxidants Exceeded Limits.Caused by Circulator Buffer Sys Upset & Helium Circulator Trip Due to 810223 Reactor Scram. Reactor Power Reduced Until Moisture Level Decreased | | | 05000267/LER-1981-021, Forwards LER 81-021/03L-0.Detailed Event Analysis Encl | Forwards LER 81-021/03L-0.Detailed Event Analysis Encl | | | 05000267/LER-1981-021-03, /03L-0:on 810302,liquid Nitrogen Storage Tank Level Lower than Tech Spec Requires.Caused by Sys Usage & Unavailable Recondensers.Level Restored W/Two Loads | /03L-0:on 810302,liquid Nitrogen Storage Tank Level Lower than Tech Spec Requires.Caused by Sys Usage & Unavailable Recondensers.Level Restored W/Two Loads | | | 05000267/LER-1981-022, Forwards LER 81-022/03L-0.Detailed Event Analysis Encl | Forwards LER 81-022/03L-0.Detailed Event Analysis Encl | | | 05000267/LER-1981-022-03, /03L-0:on 810310,found That Total Dissolved Solids in Plant Nonradioactive Liquid Waste Effluent Exceeded Tech Specs on 810224.Caused by Restoration of Water Sys Blowdown at High Rate.Blowdown Reduced | /03L-0:on 810310,found That Total Dissolved Solids in Plant Nonradioactive Liquid Waste Effluent Exceeded Tech Specs on 810224.Caused by Restoration of Water Sys Blowdown at High Rate.Blowdown Reduced | | | 05000267/LER-1981-023, Forwards LER 81-023/03L-0.Detailed Event Analysis Encl | Forwards LER 81-023/03L-0.Detailed Event Analysis Encl | | | 05000267/LER-1981-023-03, /03L-0:on 810310,during Release of Reactor Bldg Sump,Sump Pump Effluent Discharge Proportional Sampler Found Inoperable.Caused by Error in Instructions.New Instructions Issued to Assure Sampler Operability | /03L-0:on 810310,during Release of Reactor Bldg Sump,Sump Pump Effluent Discharge Proportional Sampler Found Inoperable.Caused by Error in Instructions.New Instructions Issued to Assure Sampler Operability | | | 05000267/LER-1981-024-03, During Testing,Five of 12 Helium Circulator Seal Malfunction Pressure Differential Switch Units Tripped Outside Limits.Caused by Accumulation of Dirt on Switches.Switches Replaced | During Testing,Five of 12 Helium Circulator Seal Malfunction Pressure Differential Switch Units Tripped Outside Limits.Caused by Accumulation of Dirt on Switches.Switches Replaced | | | 05000267/LER-1981-024, Forwards LER 81-024/03L-0.Detailed Event Analysis Encl | Forwards LER 81-024/03L-0.Detailed Event Analysis Encl | | | 05000267/LER-1981-025, Forwards LER 81-025/03L-0.Detailed Event Analysis Encl | Forwards LER 81-025/03L-0.Detailed Event Analysis Encl | | | 05000267/LER-1981-025-03, /03X-1:on 810317,liquid Nitrogen Storage Tank Level Decreased to Below 650 Gallons.Caused by Loss of Power to Fill Line Isolation Valve.Circuit Breaker Reclosed.Level Reestablished.Bypass Valve Installed Around Converter | /03X-1:on 810317,liquid Nitrogen Storage Tank Level Decreased to Below 650 Gallons.Caused by Loss of Power to Fill Line Isolation Valve.Circuit Breaker Reclosed.Level Reestablished.Bypass Valve Installed Around Converter | |
|