05000254/LER-2017-001, Regarding Secondary Containment Interlock Doors Opened Simultaneously
| ML17081A289 | |
| Person / Time | |
|---|---|
| Site: | Quad Cities |
| Issue date: | 03/22/2017 |
| From: | Darin S Exelon Generation Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| SVP-17-019 LER 17-001-00 | |
| Download: ML17081A289 (6) | |
| Event date: | |
|---|---|
| Report date: | |
| Reporting criterion: | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(ix)(A) 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i) |
| 2542017001R00 - NRC Website | |
text
Lon G n ration SVP-17-019 March 22, 2017 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265 10 CFR 50.73
Subject:
Licensee Event Report 254/2017-001-00, "Secondary Containment Interlock Doors Opened Simultaneously" Enclosed is Licensee Event Report (LER) 254/2017-001-00, "Secondary Containment Interlock Doors Opened Simultaneously," for Quad Cities Nuclear Power Station, Unit 1.
This report is submitted in accordance with 1 O CFR 50.73 (a)(2)(v)(C) which requires the reporting of any event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to control the release of radioactive material.
There are no regulatory commitments contained in this letter.
Should you have any questions concerning this report, please contact Mr. W. J. Beck at (309) 227-2800.
R#~
Scott Darin Site Vice President Quad Cities Nuclear Power Station cc:
Regional Administrator - NRC Region Ill NRC Senior Resident Inspector - Quad Cities Nuclear Power Station
NRC FORM 366 (06-2016)
NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION (06-2016)
LICENSEE EVENT REPORT (LER)
APPROVED BY OMB: NO. 3150-0104 EXPIRES: 10/31/2018 Estimated burden per response to comply with this mandatory collection request: 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br />.
Reported lessons learned are incorporated into the licensing process and fed back to industry.
Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
- 1. FACILITY NAME Quad Cities Nuclear Power Station Unit 1
- 2. DOCKET NUMBER 05000254
- 3. PAGE 1 OF 5
- 4. TITLE Secondary Containment Interlock Doors Opened Simultaneously
- 5. EVENT DATE
- 6. LER NUMBER
- 7. REPORT DATE
- 8. OTHER FACILITIES INVOLVED MONTH DAY YEAR YEAR SEQUENTIAL NUMBER REV NO.
MONTH DAY YEAR FACILITY NAME Quad Cities Nuclear Power Station Unit 2 DOCKET NUMBER 05000265 01 24 2017 2017 - 001
- - 00 03 22 2017 FACILITY NAME N/A DOCKET NUMBER N/A
- 9. OPERATING MODE
- 11. THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR §: (Check all that apply) 1 20.2201(b) 20.2203(a)(3)(i) 50.73(a)(2)(ii)(A) 50.73(a)(2)(viii)(A) 20.2201(d) 20.2203(a)(3)(ii) 50.73(a)(2)(ii)(B) 50.73(a)(2)(viii)(B) 20.2203(a)(1) 20.2203(a)(4) 50.73(a)(2)(iii) 50.73(a)(2)(ix)(A) 20.2203(a)(2)(i) 50.36(c)(1)(i)(A) 50.73(a)(2)(iv)(A) 50.73(a)(2)(x)
- 10. POWER LEVEL 20.2203(a)(2)(ii) 50.36(c)(1)(ii)(A) 50.73(a)(2)(v)(A) 73.71(a)(4) 098 20.2203(a)(2)(iii) 50.36(c)(2) 50.73(a)(2)(v)(B) 73.71(a)(5) 20.2203(a)(2)(iv) 50.46(a)(3)(ii) 50.73(a)(2)(v)(C) 73.77(a)(1) 20.2203(a)(2)(v) 50.73(a)(2)(i)(A) 50.73(a)(2)(v)(D) 73.77(a)(2)(i) 20.2203(a)(2)(vi) 50.73(a)(2)(i)(B) 50.73(a)(2)(vii) 73.77(a)(2)(ii) 50.73(a)(2)(i)(C)
OTHER Specify in Abstract below or in Page 5 of 5 LER 254/2014-002-00, 06/02/14, Reactor Building Interlock Doors Opened Simultaneously Cause Loss of Secondary Containment (04/1/14) - Both doors in the secondary containment interlock on the 595 foot elevation from the Unit 2 Reactor Feed Pump room to the Reactor Building were opened simultaneously. The cause of the interlock failure was due to a malfunctioning interlock door hydraulic actuator and time delay relays had allowed the second door to open before the first door was secured. Corrective actions included replacing the failed actuator, adjusting the limit switch, and a set point change to resolve relay time delay issues. Since this event cause is different from the current event cause (sticking relay), the previous interlock failure event is not directly applicable to the event of this current LER.
LER 254/2015-006-00, 6/24/15, Interlock Doors Opened Simultaneously Cause Loss of Secondary Containment (04/28/15) - the control room was notified that the Unit 1/2 emergency diesel generator (EDG) room manual side door and the Unit 1 reactor building (RB) side door, as a part of the personnel interlock to the 1/2 EDG room, were opened simultaneously. The failure of this interlock caused a temporary loss of secondary containment (inoperable) per Technical Specification (TS) 3.6.4.1, Condition A. The 1/2 EDG manual interlock door was closed immediately, and the secondary containment boundary was immediately reestablished. Operators verified the RB (secondary containment) differential pressure remained negative during this event. It was determined that the latch did not engage into the strike plate, hence this failure mechanism is not directly applicable to the event of this current LER.
G.
COMPONENT FAILURE DATA
Failed Equipment: Relay Component Manufacturer: General Electric Component Model Number: CR122 Component Part Number: N/A This event has been reported to ICES as Report No. 326170