Finding | |
---|---|
Title | |
Description | A NRC-identified NCV of 10 CFR 50.55a, Codes and Standards, was identified for the failure to adequately perform a Boiler and Pressure Vessel Code (BPVC) class 1 and 2 replacement activity in accordance with the Turkey Point Plant American Society of Mechanical Engineers (ASME)Section XI Repair/Replacement Program. Specifically, the licensee did not ensure a system leakage test conducted on October 19, 2017, was appropriately evaluated to meet the requirements of ASME Section XI for pre-service leakage testing of a Unit 4 high head safety injection (HHSI) cold leg injection check valve that was replaced on October 15, 2017. This issue was entered into the licensees Corrective Action Program (CAP) as ARs 2235484 and 2239149. Corrective actions included documenting a formal bases for current operability via a prompt operability determination and updating work order (WO) documentation to fully comply with ASME BPVC Section XI requirements. This performance deficiency was determined to be more than minor because an inadequate inservice inspection repair/replacement plan adversely affected the Reactor Coolant System (RCS) Equipment and Barrier Performance attribute of the Barrier Integrity Cornerstone objective to provide reasonable assurance that physical design barriers (fuel cladding, reactor coolant system, and containment) protect the public from radionuclide releases caused by accidents or events. In accordance with IMC 0609, Appendix A, The Significance Determination Process for Findings At-Power, the inspectors determined that the issue had very low safety significance because there was no actual degradation of the RCS boundary. This finding was assigned a cross-cutting aspect in the Procedure Adherence component of the Human Performance cross-cutting area, in that the licensee did not effectively evaluate and appropriately implement the ASME BPVC requirements in the 4-873A Repair/Replacement Plan which were reiterated in licensee administrative procedure 0-ADM-532, ASME Section XI Repair/Replacement Program [H.8]. |
Site: | Turkey Point |
---|---|
Report | IR 05000251/2017004 Section 1R19 |
Date counted | Dec 31, 2017 (2017Q4) |
Type: | NCV: Green |
cornerstone | Barrier Integrity |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.19 |
Inspectors (proximate) | J Orr J Reyes A Butcavage P Capehart M Donithan W Loo J Panfel J Rivera T Stephen L Suggs |
Violation of: | 10 CFR 50.55a |
CCA | H.8, Procedure Adherence |
INPO aspect | WP.4 |
' | |