Title | Inadequate Verification of Electrical Protective Device Selective Coordination |
Description | The NRC identified a non-cited violation of Title 10 Code of Federal Regulations Part 50, Appendix B, Criterion III, Design Control, for failure to verify that coordination exists between the protective devices on safety related switchgear in order to minimize the probability of losing a safety related power bus. For immediate corrective actions, the licensee entered this issue into their corrective action program as Action Request (AR) 2220956 and performed an operability determination, which determined the system was operable, and was performing a reevaluation of the calculation to determine adequate coordination. The performance deficiency was determined to be more than minor because it was associated with the Design Control attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, failing to verify short circuits in non-safety related SSCs downstream of the safety related switchgear would not cause a lockout of the safety related bus affected its availability and reliability. The team determined the finding to be of very low safety significance because the finding was a deficiency affecting the design of a mitigating structure, system, or component (SSC), and the SSC maintained their operability or functionality. This finding was not assigned a cross-cutting aspect because the issue did not reflect current licensee performance. |
Site: | Turkey Point ![]() |
---|---|
Report | IR 05000250/2017007 Section 1R21 |
Date counted | Sep 30, 2017 (2017Q3) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.21M |
Inspectors (proximate) | T Fanelli S Bussey M Riley N Morgan M Jones H Leake R Bywater J Bartley |
Violation of: | 10 CFR 50 Appendix B 10 CFR 50 Appendix B Criterion III, Design Control |