Letter Sequence Request |
|---|
|
Results
Other: L-PI-03-016, Response to Opportunity for Comment on Task Interface Agreement (TIA) 2001-10, Design Basis Assumptions for Ability of Prairie Island, Unit 2, Emergency Diesel Generators to Meet Single-Failure Criteria for External Events, ML013480323, ML020020074, ML020020108, ML020030002, ML020410002, ML020570514, ML021060641, ML021070317, ML021140405, ML021140426, ML021610096, ML021990405, ML022140006, ML022600292, ML023290377, ML023640310, ML031010026, ML032040412, ML050900176, ML051030051
|
MONTHYEARML0134803232002-01-0404 January 2002 Task Interface Agreement 2000-18, Design-Basis Assumptions for Non-Seismic Piping Failures at the Perry Plant Project stage: Other ML0200201082002-01-16016 January 2002 Opportunity for Comment on TIA 2001-04, Design-Basis Reliance on Non-Seismic and Non-Safety Related Equipment Project stage: Other ML0200300022002-01-16016 January 2002 Opportunity for Comment on TIA 2001-10, Design Basis Assumptions for Ability of Prairie Island, Units 2, Emergency Diesel Generators to Meet Single Failure Criteria for External Events Project stage: Other ML0200200742002-01-18018 January 2002 Opportunity for Comment on TIA 2001-02, Design Basis Assumptions for Non-Seismic Piping Failure Project stage: Other ML0204100022002-02-11011 February 2002 Report on the Status of Open TIAs Assigned to NRR Project stage: Other ML0208702382002-03-13013 March 2002 Response to Request for Additional Information (RAI) Regarding Technical Specification (TS) Change 01-10, One-Time Frequency Extension for Type a Test (Containment Integrated Leak Rate Test (Cilrt)) Project stage: Response to RAI ML0208003112002-03-18018 March 2002 Day Response to Order for Interim Safeguards Security Compensatory Measures Project stage: Request ML0210100662002-04-0909 April 2002 TSC 01-10 - TVA Response to RAI Project stage: Request ML0211404052002-04-11011 April 2002 Additional Information for Technical Specification (TS) Change 01-10, One-Time Frequency Extension for Type a Test (Containment Integrated Leak Rate Test (Cilrt)) Project stage: Other ML0210703172002-04-17017 April 2002 Memo to Raghavan from Manoly, Response to Task Interface Agreement (TIA 2001-15) for D. C. Cook, Units 1 and 2 Project stage: Other ML0210606412002-05-0101 May 2002 Task Interface Agreement (TIA) 2001-07 from Region III Regarding Quad Cities Maintenance Rule (MR) Issues Project stage: Other ML0205705142002-05-0606 May 2002 Response to Task Interface Agreement - TIA 2001-12, Licensing Bases for the Standby Liquid Control System Project stage: Other ML0212904652002-05-10010 May 2002 Meeting with Nuclear Management Company, LLC to Discuss the Aspects of Security Orders Project stage: Request ML0215504192002-05-10010 May 2002 Response to Draft NRR Position on TIA 2001-04, Design Basis Reliance on Non-Seismic and Non-Safety Related Equipment Project stage: Draft Other ML0215504132002-05-10010 May 2002 Response to Draft NRR Position on TIA 2001-02, Design Basis Assumptions for Non-Seismic Piping Failure Project stage: Draft Other ML0211404262002-05-24024 May 2002 Memo Re Response to Task Interface Agreement 2001-009 Regarding Potential Unisolable Reactor Coolant Leak Outside Containment Project stage: Other ML0509001762002-05-28028 May 2002 Fire Hazard Analysis for Fire Zone 98-J, Emergency Diesel Generator Corridor and Fire Zone 99-M, North Electrical Switchgear Room, Arkansas Nuclear One, Unit 1 Project stage: Other ML0214800332002-05-31031 May 2002 DC Cook, Units 1 & 2 - Request for Additional Information Regarding Containment Structure Conformance to Design-Basis Requirements Project stage: RAI ML0216100962002-06-11011 June 2002 Information Sent & Received by Electronic Mail Concerning Heavy Loads Request for Additional Infomration Project stage: Other 05000237/LER-2002-003, Manual Valve Failures Prevent the Cooling Water Flow to Control Room Refrigeration Condensing Unit2002-07-0808 July 2002 Manual Valve Failures Prevent the Cooling Water Flow to Control Room Refrigeration Condensing Unit Project stage: Request ML0220301902002-07-16016 July 2002 Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements Project stage: Response to RAI ML0220303702002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Verification Manual, Pages A30.1 - A56.4 Project stage: Response to RAI ML0220304002002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Verification Manual, Pages A57.1 - A80.10 Project stage: Response to RAI ML0220304152002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Engineering Report SE 99-5, Attachment 6 to AEP:NRC:2520, Pages 1 - B29.6 Project stage: Response to RAI ML0220304172002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Verification Manual, Pages A81.1 - 1.2 Project stage: Response to RAI ML0220304462002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Verification Manual, Pages B30.1 - B67.6 Project stage: Response to RAI ML0220304482002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Verification Manual, Attachment 6, Pages B68.1 - Attachment 7 Project stage: Response to RAI ML0220303342002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Attachment 5, Solvia Engineering Report SE 99-4 Project stage: Response to RAI ML0219904052002-07-18018 July 2002 Supplemental Fire Modeling for Fire Zone 98-J, Emergency Diesel Generator Corridor & Fire Zone 99-M, North Electrical Switchgear Room, Arkansas Nuclear One, Unit 1 Project stage: Other ML0224100432002-08-23023 August 2002 Supplement to Nuclear Regulatory Commission Request for Additional Information Regarding Containment Structure Conformance to Design Basis Requirements Project stage: Supplement ML0223805242002-08-23023 August 2002 License Amendment Request for One-Time Extension of Essential Service Water System Allowed Outage Time-Additional Information Project stage: Request ML0221400062002-08-29029 August 2002 Response to Task Interface Agreement (TIA 2001-02) &Tia 2001-04 Evaluation of Service Water System Design Basis Requirements Project stage: Other ML0224201372002-09-11011 September 2002 Cover Letter - Draft Response to Task Interface Agreement 2001-13 Concerning the Reactor Building Crane and Heavy Loads Project stage: Draft Other ML0226002922002-09-17017 September 2002 Memorandum Regarding Report on the Status of Open TIAs Assigned to NRR Project stage: Other ML0231000392002-11-11011 November 2002 Examples of Risk-Informed Licensing Actions for Acrs/Acnw Project stage: Request ML0236403102002-12-30030 December 2002 Opportunity for Comment on Task Interface Agreement (TIA) 2001-10, Design-Basis Assumptions for Ability of Prairie Island, Unit 2, Emergency Diesel Generators to Meet Single-Failure Criteria for External Events Project stage: Other ML0510300512003-01-13013 January 2003 Response to Task Interface Agreement (TIA 2001 -15) Regarding Evaluation of Containment Structure Conformance to Design-basis Requirements Project stage: Other ML0232903772003-01-13013 January 2003 Task Interface Agreement (TIA 2001-15) Evaluation of Containment Structure Conformance to Design-Basis Requirement Project stage: Other ML0224200972003-02-21021 February 2003 Draft - NRR Response to TIA 2001-13, Backfitting Requirements for Dresden Units 2 & 3 Reactor Building Crane Project stage: Draft Other ML0310100262003-02-21021 February 2003 NRC Response to TIA 2001-13, Backfitting Requirements for Dresden Units 2 & 3 Reactor Building Crane Project stage: Other L-PI-03-016, Response to Opportunity for Comment on Task Interface Agreement (TIA) 2001-10, Design Basis Assumptions for Ability of Prairie Island, Unit 2, Emergency Diesel Generators to Meet Single-Failure Criteria for External Events2003-04-21021 April 2003 Response to Opportunity for Comment on Task Interface Agreement (TIA) 2001-10, Design Basis Assumptions for Ability of Prairie Island, Unit 2, Emergency Diesel Generators to Meet Single-Failure Criteria for External Events Project stage: Other ML0320404122003-09-0404 September 2003 Response to TIA 2001-10, Design Basis Assumptions for Ability of Emergency Diesel Generators to Meet Single Failure Criteria for External Events Project stage: Other ML0411204872004-04-13013 April 2004 License Amendment Request to Use Yield Strength Determined from Measured Material Properties for Reinforcing Bar in Structural Calculations for Control Rod Drive Missile Shields Project stage: Request 2002-05-28
[Table View] |
LER-2002-003, Manual Valve Failures Prevent the Cooling Water Flow to Control Room Refrigeration Condensing Unit |
| Event date: |
|
|---|
| Report date: |
|
|---|
| Reporting criterion: |
10 CFR 50.73(a)(2)(v), Loss of Safety Function |
|---|
| 2372002003R00 - NRC Website |
|
text
Exelo n.
Exelon Generation www.exeloncorp.com Nuclear Dresden Generating Station 6500 North Dresden Road Morris, IL 60450-9765 Tel 815-942-2920 10 CFR 50.73 July 8, 2002 RHLTR: #02-0049 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Dresden Nuclear Power Station, Unit 2 Facility Operating License No. DPR-1 9 NRC Docket No. 50-237
Subject:
Licensee Event Report 2002-003-00, "Manual Valve Failures Prevent the Cooling Water Flow to Control Room Refrigeration Condensing Unit" Enclosed is Licensee Event Report 2002-003-00, "Manual Valve Failures Prevent the Cooling Water Flow to Control Room Refrigeration Condensing Unit," for the Dresden Nuclear Power Station (DNPS). This event is being reported in accordance with 10 CFR 50.73(a)(2)(v)(D),
"Any event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to mitigate the consequences of an accident."
Corrective Actions include:
A temporary modification was implemented to remove the internals of the two valves, restoring flow to the heat exchangers.
The valves, 2/3-3999-332 and 2/3-3999-334 will be replaced with stainless steel valves.
Valves that are susceptible to conditions identified in the root cause in both the Diesel Generator Cooling Water and Control Room Train 'B' Heating Ventilation and Air Conditioning systems will be inspected to determine if similar conditions exist. The conditions observed during the inspection of these valves will be evaluated to verify that the appropriate corrective measures are in place to prevent recurrence.
July 8, 2002 U.S. Nuclear Regulatory Commission Page 2 If you have any questions, please contact Bob Rybak, Regulatory Assurance Manager at (815) 416-2800.
Respectfully, I#1 R. J. Hovey Site Vice President Dresden Nuclear Power Station Enclosure cc:
Regional Administrator - NRC Region III NRC Senior Resident Inspector - Dresden Nuclear Power Station
Abstract
On May 9, 2002, while performing the monthly surveillance requirement for the control room heating, ventilation and air conditioning (HVAC) system, the refrigeration condensing unit (RCU) compressor tripped due to high discharge pressure.
A review of the system operating parameters by Operations determined that there was no cooling water flow through the RCU heat exchanger. Troubleshooting of the system determined that the disk from manual valve 2/3-3999-334 (inlet) was separated from the stem and became stuck in the closed position preventing any cooling flow to the Control Room Train B HVAC RCU heat exchanger. Additional investigation determined that manual valve 2/3-3999-332 (outlet) was also found separated from stem but did not block the flowpath. The failed disks of the valves were evaluated and found to be corroded over the entire surfaces. The cause of this event was determined to be a combination of using carbon steel material and frequently exercising the valves in a Service Water environment. Frequent exercising of the valves caused the protective corrosion layer on the ears to be removed, which accelerated the rate of corrosion. The valve internals were removed in accordance with a temporary modification, which allows flow to the heat exchanger. The valves will be replaced with stainless steel valves. The non-safety related Control Room HVAC System "A" Train was available and started during the unavailability of the "B" Train HVAC System RCU. The heat removal capability of the "A" Train System is equivalent to the "B" Train. At no time did this condition compromise the health and safety of the public.
- - U.S. NUCLEAR REGULATORY APPROVED BY OMB NO. 3150-0104 COMMISSION EXPIRES 0713112004 (7-2001)
, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
FACILITY NAME (1)
DOCKET NUMBER (2)
ER NUMBER 6 PAGE (3)
YEAR SEQUENTIAL REVISION Dresden Nuclear Power Station Unit 2 05000237 NUMBER NUMBER 2002 003 00 2 of 3 (If more space is required, use additional copies of NRC Form 366A)(17)
A.
Plant Conditions Prior to Event:
Unit: 02 (03)
Event Date: 05-09-2002 Event Time: 1750 CDT Reactor Mode: 1 (1)
Mode Name: Run (Run)
Power Level: 97 (100) percent Reactor Coolant System Pressure: 1005 (1002) psig B.
Description of Event
This event is being reported in accordance with 10 CFR 50.73 (a)(2)(v)(D), which requires reporting "Any event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to mitigate the consequences of an accident."
On May 9, 2002, while performing the Control Room train "B" HVAC and Air Filtration [VI] Surveillance for normal operability run, the refrigeration condensing unit (RCU) compressor tripped due to high discharge pressure. The "B" train of Control Room HVAC system was secured and the "A" train started in accordance with station procedures. A review of the system operating parameters by Operations determined that there was no cooling water flow through the RCU heat exchanger. Troubleshooting of the system determined that the disk from manual valve 2/3-3999-334 (inlet) was separated from the stem and became stuck in the closed position preventing any cooling flow to the Control Room Train B HVAC RCU heat exchanger. Additional investigation determined that manual valve 2/3-3999-332 (outlet) was also found separated from stem but did not block the flowpath. The failed disks of the manual valves were evaluated and found to be corroded over the entire surfaces. A temporary modification was implemented that removed the valve internals, which restored flow to the RCU.
C.
Cause of Event
The root cause of this event was determined to be the combination of using carbon steel material and frequently exercising the valves in a Service Water [BI] environment. (NRC Cause Code E)
Frequent exercising of the valves caused the protective corrosion layer on the ears to be removed, which accelerated the rate of corrosion. The immediate corrective actions were to remove the valve internals in accordance with a temporary modification, which allowed flow to the heat exchanger. Extent of condition revealed similar valves in the Diesel Generator Cooling Water System and the Control Room Train B HVAC RCU system.
Corrective actions are in place to disassemble and inspect these valves.
D.
SafetV AnalVsis:
The non-safety related Control Room HVAC System "A" train was available and started during the unavailability of the "B" train HVAC system RCU. The "A" train system is the normal supply for the control room. The heat removal capability of the "A" train system is equivalent to the "B" train and the "A" train system can be used if "B" train fails to perform its design function. Station procedures provide instructions to power the "A" Train system via an alternate power source if required, in the event of a loss of offsite power. At no time did this condition compromise the health and safety of the public.U.S. NUCLEAR REGULATORY APPROVED BY OMB NO. 3150-0104 COMMISSION EXPIRES 0713112004 (7-2001)
, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3)
YEAR SEQUENTIAL REVISION Dresden Nuclear Power Station Unit 2 05000237 NUMBER NUMBER 2002 003 00 3 of 3 (If more space is required, use additional copies of NRC Form 366A)(17)
E.
Corrective Actions
A temporary configuration control package was implemented to remove the 2/3-3999-332 and 2/3-3999-334 valve internals, which restored flow to the heat exchangers.
Valves 2/3-3999-332 and 2/3-3999-334 will be replaced with stainless steel valves.
Valves that are susceptible to conditions identified in the root cause in both the Diesel Generator Cooling Water and Control Room Train 'B' Heating Ventilation and Air Conditioning systems will be inspected to determine if similar conditions exist. The conditions observed during the inspection of these valves will be evaluated to verify that the appropriate corrective measures are in place to prevent recurrence.
F.
Previous Occurrences
None G.
Component Failure Data
Manufacturer Nomenclature:
Model Number:
Manufacture Part Number:
Nuclear Valve Div. / Borg-Warner 402HBD4-001 N/A
|
|---|
|
|
| | | Reporting criterion |
|---|
| 05000249/LER-2002-001, HPCI Not in Standby Operation When Required by the Technical Specifications | HPCI Not in Standby Operation When Required by the Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000237/LER-2002-001, Re Unit 2 Isolation Condenser Time Delay Relay Surveillance Failures Due to Setpoint Tolerances Specified with No Margin | Re Unit 2 Isolation Condenser Time Delay Relay Surveillance Failures Due to Setpoint Tolerances Specified with No Margin | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000249/LER-2002-002, Reactor Scram Due to Main Shaft Oil Pump Failure | Reactor Scram Due to Main Shaft Oil Pump Failure | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | | 05000237/LER-2002-002, Smoke Purge Mode Operation Prevents Safety Function of the Control Room Emergency Ventilation System on April 10, 2002 | Smoke Purge Mode Operation Prevents Safety Function of the Control Room Emergency Ventilation System on April 10, 2002 | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000249/LER-2002-003, Reactor Recirculation Loop a Sensing Line Socket Weld Vibration Fatigue Failure | Reactor Recirculation Loop a Sensing Line Socket Weld Vibration Fatigue Failure | 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | | 05000237/LER-2002-003, Manual Valve Failures Prevent the Cooling Water Flow to Control Room Refrigeration Condensing Unit | Manual Valve Failures Prevent the Cooling Water Flow to Control Room Refrigeration Condensing Unit | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000249/LER-2002-004, Regarding Main Steam Safety Valves Failed TS as Found Lift Setpoint | Regarding Main Steam Safety Valves Failed TS as Found Lift Setpoint | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000237/LER-2002-004, Re Control Room Ventilation Ductwork Breached During Replacement of Temperature Transmitter | Re Control Room Ventilation Ductwork Breached During Replacement of Temperature Transmitter | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000249/LER-2002-005, High Pressure Coolant Injection System Inoperable Due to Water Hammer Event | High Pressure Coolant Injection System Inoperable Due to Water Hammer Event | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000237/LER-2002-005, Pressure Switches Found Above Technical Specification Allowable Values | Pressure Switches Found Above Technical Specification Allowable Values | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000249/LER-2002-006, Re Reactor Recirculation Loop a Sensing Line Socket Weld Failure | Re Reactor Recirculation Loop a Sensing Line Socket Weld Failure | 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown |
|