MONTHYEARML0214800332002-05-31031 May 2002 DC Cook, Units 1 & 2 - Request for Additional Information Regarding Containment Structure Conformance to Design-Basis Requirements Project stage: RAI ML0220304482002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Verification Manual, Attachment 6, Pages B68.1 - Attachment 7 Project stage: Response to RAI ML0220304462002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Verification Manual, Pages B30.1 - B67.6 Project stage: Response to RAI ML0220304172002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Verification Manual, Pages A81.1 - 1.2 Project stage: Response to RAI ML0220304152002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Engineering Report SE 99-5, Attachment 6 to AEP:NRC:2520, Pages 1 - B29.6 Project stage: Response to RAI ML0220304002002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Verification Manual, Pages A57.1 - A80.10 Project stage: Response to RAI ML0220303702002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Solvia Verification Manual, Pages A30.1 - A56.4 Project stage: Response to RAI ML0220303342002-07-16016 July 2002 Attachment to Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements. Attachment 5, Solvia Engineering Report SE 99-4 Project stage: Response to RAI ML0220301902002-07-16016 July 2002 Response to NRC Request for Additional Information Re Containment Structure Conformance to Design Basis Requirements Project stage: Response to RAI ML0224100432002-08-23023 August 2002 Supplement to Nuclear Regulatory Commission Request for Additional Information Regarding Containment Structure Conformance to Design Basis Requirements Project stage: Supplement ML0226002922002-09-17017 September 2002 Memorandum Regarding Report on the Status of Open TIAs Assigned to NRR Project stage: Other ML0232903772003-01-13013 January 2003 Task Interface Agreement (TIA 2001-15) Evaluation of Containment Structure Conformance to Design-Basis Requirement Project stage: Other ML0510300512003-01-13013 January 2003 Response to Task Interface Agreement (TIA 2001 -15) Regarding Evaluation of Containment Structure Conformance to Design-basis Requirements Project stage: Other ML0411204872004-04-13013 April 2004 License Amendment Request to Use Yield Strength Determined from Measured Material Properties for Reinforcing Bar in Structural Calculations for Control Rod Drive Missile Shields Project stage: Request 2002-08-23
[Table View] |
Similar Documents at Cook |
---|
Category:Letter
MONTHYEARIR 05000315/20230042024-01-31031 January 2024 Integrated Inspection Report 05000315/2023004 and 05000316/2023004 ML24004A1582024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0039 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) AEP-NRC-2024-01, Emergency Plan Revision 482024-01-0808 January 2024 Emergency Plan Revision 48 AEP-NRC-2023-56, Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor2023-12-20020 December 2023 Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor ML23352A3502023-12-19019 December 2023 Dc. Cook Nuclear Power Plant, Units 1 Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23338A2642023-12-0505 December 2023 Confirmation of Initial License Examination AEP-NRC-2023-45, Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation IR 05000315/20234042023-11-0606 November 2023 Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 IR 05000315/20234032023-09-19019 September 2023 Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 IR 05000315/20230112023-08-31031 August 2023 Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 ML23242A1832023-08-30030 August 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report05000315/2023004 AEP-NRC-2023-40, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2023-08-29029 August 2023 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes IR 05000315/20234022023-08-11011 August 2023 Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 AEP-NRC-2023-34, Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation2023-08-0202 August 2023 Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation IR 05000315/20230022023-07-24024 July 2023 Integrated Inspection Report 05000315/2023002 and 05000316/2023002 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000315/20230122023-06-22022 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 IR 05000315/20235012023-06-21021 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 AEP-NRC-2023-29, Core Operating Limits Report2023-06-19019 June 2023 Core Operating Limits Report ML23159A0192023-06-13013 June 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 AEP-NRC-2023-32, Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations2023-06-0606 June 2023 Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2023-33, Renewable Operating Permit2023-06-0505 June 2023 Renewable Operating Permit AEP-NRC-2023-30, Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump2023-06-0101 June 2023 Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-27, Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Annual Radiological Environmental Operating Report ML23131A3282023-05-11011 May 2023 D.C. Cook Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000315/2023404 and 05000316/2023404 IR 05000315/20230012023-05-0303 May 2023 Integrated Inspection Report 05000315/2023001 and 05000316/2023001 AEP-NRC-2023-19, Annual Radioactive Effluent Release Report2023-04-30030 April 2023 Annual Radioactive Effluent Release Report ML23117A0062023-04-27027 April 2023 Review of the Spring 2022 Steam Generator Tube Inspections Report ML23114A1142023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection AEP-NRC-2023-23, Annual Report of Individual Monitoring for 20222023-04-24024 April 2023 Annual Report of Individual Monitoring for 2022 AEP-NRC-2023-24, Notification of Ph Non-Compliance for Turbine Room Sump2023-04-12012 April 2023 Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-20, Annual Report of Property Insurance2023-04-0303 April 2023 Annual Report of Property Insurance AEP-NRC-2023-15, Decommissioning Funding Status Report2023-03-28028 March 2023 Decommissioning Funding Status Report ML23076A0212023-03-20020 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection; Inspection Report 05000315/2023011; 05000316/2023011 IR 05000315/20234012023-03-16016 March 2023 Security Baseline Inspection Report 05000315/2023401 and 05000316/2023401 ML23066A1882023-03-0707 March 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Donald C. Cook Nuclear Plant IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220042023-02-0101 February 2023 Integrated Inspection Report 05000315/2022004 and 05000316/2022004 and Exercise of Enforcement Discretion AEP-NRC-2023-11, Form OAR-1, Owner'S Activity Report2023-01-31031 January 2023 Form OAR-1, Owner'S Activity Report IR 05000315/20230102023-01-31031 January 2023 Phase 4 Post-Approval License Renewal Inspection Report 05000315/2023010 and 05000316/2023010 AEP-NRC-2023-02, Request for Approval of Change Regarding Neutron Flux Instrumentation2023-01-26026 January 2023 Request for Approval of Change Regarding Neutron Flux Instrumentation ML22363A5622023-01-0404 January 2023 Relief Request ISIR-5-06 Related to ASME Code Case N-729-6 Supplemental Examination Requirements of Reactor Vessel Closure Head Penetration Nozzles AEP-NRC-2022-66, Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring2022-12-15015 December 2022 Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2022-46, Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in2022-12-12012 December 2022 Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in ML22340A1392022-11-30030 November 2022 Submittal of Revision 31 to Updated Final Safety Analysis Report and 10CFR50.71(e) Updated and Related Site Change Reports IR 05000315/20220112022-11-0404 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000315/2022011 and 05000316/2022011 IR 05000315/20220032022-10-28028 October 2022 Integrated Inspection Report 05000315/2022003 and 05000316/2022003 AEP-NRC-2022-58, U1C31 Steam Generator Tube Inspection Report2022-10-24024 October 2022 U1C31 Steam Generator Tube Inspection Report AEP-NRC-2022-61, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-062022-10-24024 October 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-06 2024-01-08
[Table view] |
Text
Indiana Michigan Power Company 500 Circle Drive Buchanan, MI 49107 1373 INDIANA MICHIGAN POWER July 16, 2002 AEP:NRC:2520 10 CFR 50.90 Docket No.: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-PI-17 Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 RESPONSE TO NUCLEAR REGULATORY COMMISSION REQUEST FOR ADDITIONAL INFORMATION REGARDING CONTAINMENT STRUCTURE CONFORMANCE TO DESIGN BASIS REQUIREMENTS (TAC NOS. MB3603 AND MB33604)
Reference:
Letter from J. F. Stang (NRC) to A. C. Bakken (I&M),
"Donald C. Cook Nuclear Plant, Units 1 and 2 - Request for Additional Information, Regarding Containment Structure Conformance to Design Basis Requirements (TAC Nos. MB3603 and MB3604)," dated May 31, 2002 This letter provides Indiana Michigan Power Company's (I&M) response to a Nuclear Regulatory Commission request for additional information (RAI) regarding conformance of the containment structures at Donald C. Cook Nuclear Plant to design basis requirements. The RAI was transmitted by the referenced letter. The referenced letter documented I&M's agreement to provide its response to the RAI by July 2, 2002. In subsequent telephone discussions, I&M informed J. F. Stang, NRC, that the response would be submitted by July 16, 2002. to this letter provides the requested information. Attachments 2 through 6 provide additional documentation supporting the information provided in Attachment 1. Attachment 7 documents a new commitment contained in this letter.
A0`1
U. S. Nuclear Regulatory Commission AEP:NRC:2520 Page 2 Should you have any questions, please contact Mr. Gordon P. Arent, Manager of Regulatory Affairs, at (616) 697-5553.
Sincerely, StA. Greenlee Director of Nuclear Technical Services JRW/jen Attachments:
- 1. Response to Nuclear Regulatory Commission Request for Additional Information Regarding Containment Structure Conformance to Design Basis Requirements
- 2. AEP Report No. NED-2001-010-REP, "Test Report for Reactor Reflective Insulation Crushing Experiments," dated May 2001
- 3. AEP Report No. NED-2001-011-REP, "The response of Reflective Insulation and HVAC Ducting to Design Basis Events," dated May 2001
- 4. Comparison of Selected Verification Problems - ADINA versus SOLVIA
- 5. Solvia Engineering Report SE 99-4, "SOLVIA Verification Manual Linear Examples"
- 6. Solvia Engineering Report SE 99-5, "SOLVIA Verification Manual Non-Linear Examples"
- 7. Comittments c: K. D. Curry, w/o attachments J. E. Dyer MDEQ - DW & RPD, w/o attachments NRC Resident Inspector R. Whale, w/o attachments