St. Lucie, Units 1 & 2, Turkey Point, Units 3 & 4, Seabrook, Duane Arnold and Point Beach, Units 1 & 2, 60-Day Response to NRC 10 CFR 50.54(f) Request for Information Regarding Near-Term Task Force Recommendation 2.1, FloodingML13028A473 |
Person / Time |
---|
Site: |
Saint Lucie, Point Beach, Seabrook, Turkey Point, Duane Arnold |
---|
Issue date: |
01/24/2013 |
---|
From: |
Bhatnagar A Nextera Energy |
---|
To: |
Document Control Desk, Office of Nuclear Reactor Regulation |
---|
References |
---|
L-2013-017 |
Download: ML13028A473 (2) |
|
|
---|
Category:Letter
MONTHYEARL-2024-184, Radiological Emergency Plan Revision 772024-11-0505 November 2024 Radiological Emergency Plan Revision 77 IR 05000266/20240032024-11-0505 November 2024 Integrated Inspection Report 05000266/2024003 and 05000301/2024003 ML24295A1142024-10-31031 October 2024 Suppl Env Audit Summary Letter W/Enclosure 1 L-2024-173, Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-31031 October 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles IR 05000443/20240032024-10-30030 October 2024 Integrated Inspection Report 05000443/2024003 L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums ML24303A0352024-10-29029 October 2024 Operator Licensing Examination Approval IR 05000331/20240022024-10-25025 October 2024 NRC Inspection Report No. 07200032/2024001 and 05000331/2024002 L-2024-175, Cycle 34 Core Operating Report2024-10-24024 October 2024 Cycle 34 Core Operating Report ML24291A2882024-10-24024 October 2024 Westinghouse Topical Report - Request for Withholding Information from Public Disclosure L-2024-177, Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis2024-10-22022 October 2024 Revised Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis L-2024-160, Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41)2024-10-21021 October 2024 Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41) IR 05000335/20250102024-10-21021 October 2024 Notification of St. Lucie Plant Units 1 & 2 Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000335/2025010 and 05000389/2025010 ML24295A0862024-10-21021 October 2024 Notification of NRC Baseline Inspection and Request for Information Inspection Report 0500026/2025002 ML24227A9702024-10-18018 October 2024 Letter to Kenneth Mack Dir, License and Reg Compliance, NextEra Energy, Inc Response to Request Re Engagement Re Sub License Renewal Environmental Review - St Lucie Nuclear Plant 1 and 2 IR 05000443/20244022024-10-17017 October 2024 Material Control and Accounting Program Inspection Report 05000443/2024402 (Cover Letter Only) ML24276A2302024-10-16016 October 2024 Westinghouse Topical Report – Request for Withholding Information from Public Disclosure ML24289A2372024-10-15015 October 2024 Transmittal of Revision 1 Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles L-2024-159, Core Operating Limits Report for Reload Cycle 242024-10-15015 October 2024 Core Operating Limits Report for Reload Cycle 24 L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-085, Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results2024-10-15015 October 2024 Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results L-2024-165, Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made2024-10-14014 October 2024 Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-120, LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization2024-10-0808 October 2024 LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization L-2024-157, Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-0303 October 2024 Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles IR 05000250/20243012024-10-0303 October 2024 NRC Operator License Examination Report 05000250/2024301 and 05000251/2024301 L-2024-147, Submission of Periodic Reports2024-10-0101 October 2024 Submission of Periodic Reports ML24255A3092024-09-30030 September 2024 SLRA - Revised SE Letter L-2024-155, Subsequent License Renewal Application, Third Annual Update2024-09-27027 September 2024 Subsequent License Renewal Application, Third Annual Update 05000335/LER-2024-001, Unplanned Reactor Scram2024-09-25025 September 2024 Unplanned Reactor Scram L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24254A2552024-09-25025 September 2024 Alternative Request No. 4A-01 for the Fourth 10-Year Inservice Inspection Interval ML24269A1292024-09-24024 September 2024 Response to Requests for Additional Information Regarding Turkey Point License Amendment Request 277, Updated Spent Fuel Pool Criticality Analysis ML24239A5382024-09-20020 September 2024 Issuance of Amendment No. 175 One-Time Allowable Outage Time Extension to the Technical Specification 3.8.1.1, A.C. Sources – Operating, Limiting Condition for Operation ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A2262024-09-18018 September 2024 NRC Examination Results Summary - Examination Reports: 05000250/2024301 and 05000251/2024301 ML24262A2272024-09-18018 September 2024 Transmittal of Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles IR 05000335/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000335/2024011 and 05000389/2024011 IR 05000266/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000266/2024011 and 05000301/2024011 ML24158A0052024-09-17017 September 2024 Completion of Subsequent License Renewal Site Specific Environmental Review and Modification to Subsequent Renewed Facility Operating Licenses L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24207A0342024-09-13013 September 2024 – Exemption from Certain Requirements of 10 CFR 50.46 for Use of Axiom Fuel Rod Cladding – Letter ML24256A1132024-09-13013 September 2024 Regulatory Audit Summary Related to the Review of Regarding the Updated Spent Fuel Pool Criticality Safety Analysis License Amendment Request L-2024-138, License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles2024-09-11011 September 2024 License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles L-2024-148, Submittal of Offsite Dose Calculation Manual (Odcm), Revision 552024-09-0909 September 2024 Submittal of Offsite Dose Calculation Manual (Odcm), Revision 55 L-2024-145, Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency2024-09-0909 September 2024 Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000443/20240052024-08-29029 August 2024 Updated Inspection Plan for Seabrook Station (Report 05000443/2024005) ML24207A0202024-08-28028 August 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Point Beach Nuclear Plant, Units 1 and 2 (Docket Numbers: 50-0266 and 50-0301) IR 05000250/20240052024-08-23023 August 2024 Updated Inspection Plan for Turkey Point Units 3 & 4 - Report 05000250/2024005 and 05000251/2024005 2024-09-09
[Table view] |
Text
NExTera T M ENERGY L-2013-017 JAN 2 4 2013 10 CFR 50.54(f)ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-001 RE: Florida Power & Light Company St. Lucie Units 1 & 2 Docket Nos. 50-335 and 50-389 Turkey Point Units 3 & 4 Docket Nos. 50-250 and 50-251 NextEra Energy Seabrook, LLC Seabrook Station Docket No. 50-443 NextEra Energy Duane Arnold, LLC Duane Arnold Energy Center Docket No. 50-331 NextEra Energy Point Beach, LLC Point Beach Units 1 & 2 Docket Nos. 50-266 and 50-301 60-Day Response to NRC 10 CFR 50.54(f) Request for Information Regarding Near-Term Task Force Recommendation 2.1, Flooding
References:
(1) NRC Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident; dated March 12, 2012, Accession No. ML12073A348.
(2) U.S. NRC Japan Lessons-Learned Project Directorate, JLD-ISG-2012-05, Guidance for Performing the Integrated Assessment for External Flooding, Interim Staff Guidance, Revision 0, dated November 30, 2012, Accession No. ML12311A214.
(3) NRC Letter, David L. Skeen (NRC) to Joseph E. Pollock (NEI), Trigger Conditions for Performing and Integrated Assessment and Due Date for Response, dated December 3, 2012, Accession No. ML12326A912.
On March 12, 2012, the NRC staff issued Reference 1 requesting information pursuant to Title 10 of the Code of Federal Regulations 50.54(f).
Enclosure 2 of the Reference 1 request identifies the Requested Information associated with Near-Term Task Force (NTTF)Recommendation 2.1 for Flooding.
Item 1 of the Requested Information is for a Hazard NextEra Energy, Inc.700 Universe Boulevard, Juno Beach, FL 33408 L-2013-017 Page 2 Reevaluation Report, which is to be provided for each plant site. Item 2 of the Requested Information is for an Integrated Assessment Report, which is to be provided for those plant sites where the reevaluated flooding hazard is not bounded by the current design basis. Further, Required Response 1 of Reference 1 Enclosure 2 directs that: 'Within 60 days of the date of the NRC's issuance of guidance on implementation details of the Integrated Assessment Report, including criteria for identifying vulnerabilities, submit an approach for developing an Integrated Assessment Report including criteria for identifying vulnerabilities." Florida Power & Light Company, the licensee for the St. Lucie Nuclear Plant, Units 1 and 2, and the Turkey Point Nuclear Plant, Units 3 and 4, and its affiliates, NextEra Energy Seabrook, LLC, the licensee for the Seabrook Station, NextEra Energy Duane Arnold, LLC, the licensee for the Duane Arnold Energy Center, and NextEra Energy Point Beach, LLC, the licensee for the Point Beach Nuclear Plant, Units 1 and 2 (hereafter referred to collectively as "NextEra"), submits the following 60-Day response to Required Response 1.On November 30, 2012, the NRC issued the Reference 2 Interim Staff Guidance.
NextEra adopts the Reference 2 guidance as our approach for developing the NTTF 2.1 flooding Integrated Assessment Report for those plant sites in our nuclear generating fleet where the reevaluated flooding hazard is not bounded by the current design basis flood.NextEra also adopts the guidance provided by Reference 3 regarding the trigger conditions and scope of any required Integrated Assessment.
This letter contains no new Regulatory Commitments and no revision to existing Regulatory Commitments.
Should you have any questions regarding this submittal, please contact Christopher Wasik, NextEra Nuclear Licensing Project Manager, at 561-691-7419.