ML15176B137

From kanterella
Revision as of 02:12, 9 July 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
FPL Letter to Atomic Safety and Licensing Board
ML15176B137
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 06/25/2015
From: Hamrick S C
Florida Power & Light Co
To: Gibson M M, Kennedy M F, Sager W W
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-250-LA, 50-251-LA, ASLBP 15-935-02-LA-BD01, RAS 27976
Download: ML15176B137 (3)


Text

June 25, 2015 Michael M. Gibson, Esq. Dr. Michael F. Kennedy Chair Administrative Judge Atomic Safety and Licensing Board Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Washington, D.C. 20555-0001 Dr. William W. Sager Administrative Judge Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 In the Matter of Florida Power & Light Company (Turkey Point Units 3 and 4)

Docket Nos. 50-250-LA and 50-251-LA

Dear Administrative Judges:

On May 5, 2015, FPL provided a letter with its u nderstanding of the schedul es for certain related state administrative proceedings and best estimates of the timeframe fo r expected decisions. Since that time, a number of developments have occurred that may be of interest to the Board. First, the South Florida Water Management District issued an Emergency Order on May 19, 2015, which allows the withdrawal of water fr om the L-31 E canal during the pendency of the administrative challenge to the consumptive use permit, subject to certain conditions. Subsequently, the U.S. Army Corps of Engineers and Miami-Dade County issued wetland permits necessary to install pipe for the L-31 E w ithdrawals on May 22 and June 1, respectively.

The L-31 E authorization only allows withdrawals if a certain level of water is available in the canal. To date, no water has been withdrawn from the L-31 E canal due to insufficient rainfall. Second, a joint motion for continuance of the scheduled hearing was filed yesterday by the parties in each of two relevant administrative hearings. These include the challenge to the modification of the Conditions of Certification for Turkey Point Units 3-5 to allow Upper Floridan Aquifer wells and the challenge to the Administrative Order that would require FPL to submit a Salinity Management Plan. In both cases, all parties agreed to a 12-week continuance AdministrativeJudgesGibson,KennedyandSagerJune25,2015Page2of2to allow time and opportunity to at tempt to resolve the issues in dispute. The Administrative Judge today granted the continuances in both cases. FPL will continue to inform the Board of significant developments in these cases.

Respectfully submitted, Signed (electronically) by Steven Hamrick _________________________

Steven C. Hamrick Florida Power & Light Company 801 Pennsylvania Ave. NW, Suite 220 Washington, D.C. 20004 Office: 202-349-3496 Email: Steven.Hamrick@fpl.com cc: Service List UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of )

)

Florida Power & Light Company ) Docket No. 50-250-LA

) 50-251-LA (Turkey Point Units 3 and 4) )

) ASLBP No. 15-935-02-LA-BD01 CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Letter to the Atomic Safety and Licensing Board dated June 25, 2015 was provided to the Electronic Information Exchange for service and via e-mail to CASE.

Signed (electronically) by Steven Hamrick ________________________________ Steven C. Hamrick Florida Power & Light Company 801 Pennsylvania Avenue, N.W. Suite 220