Application for Amends to Licenses DPR-58 & DPR-14, Consisting of TS Revising Visual Insp Surveillance Requirements & Acceptance Criteria Associated W/Tss 3/4.7.8 & 3/4.7.7
ML17329A484
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 05/01/1992
From: FITZPATRICK E
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To: MURLEY T E
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML17329A485 List:
References
AEP:NRC:1143, NUDOCS 9205050144
Download: ML17329A484 (5)


Text

.ACCELERATED DI+GBUTION DEMONSTJ/TION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)ACCESSION NBR:9205050144 DOC.DATE: 92/05/01 NOTARIZED:

NO DOCKET FACIL:50-315 Donald C.Cook Nuclear Power Plant, Unit.1, Indiana M 05000315 50-316 Donald C.Cook Nuclear Power Plant, Unit 2, Indiana M 05000316 AUTH.NAME AUTHOR AFFILIATION FITZPATRICK,E.

Indiana Michigan Power Co.(formerly Indiana&Michigan Ele RECIP.NAME RECIPIENT AFFILIATION R MURLEY,T.E.

RECIPIENT ID CODE/NAME PD3-1 PD

SUBJECT:

Application for amends to licenses DPR-58 6 DPR-14, consisting of TS revising visual insp surveillance requirements 6 acceptance criteria associated w/T/Ss 3/4.7,8 3/4.7.7.lt>j DISTRIBUTION CODE: AOOID COPIES RECEIVED:LTR I ENCL/SIZE:,~&i/+~

TITLE: OR Submittal:

General Distribution NOTES:~,~7M RECIPIENT COPIES COPIES ID CODE/NAME LTTR ENCL LTTR ENCL PD3-1 LA 1 1 1 1 STANG,J 2 2 D D D INTERNAL: NRR/DET/ECMB 7D NRR/DOEA/OTSB11 NRR/DST/SELB 7E NRR/DST/SRXB 8E OC FMB G'FI 01 EXTERNAL: NRC PDR 1 1 1 1 1 1 1 1 1 0 1 1 1 1 NRR/DET/ESGB NRR/DST 8E2 NRR/DST/SICB8H7 NUDOCS-ABSTRACT OGC/HDS2 RES/DSIR/EIB NSIC 1 1 1 1 1 1 1 1 1 0 1 1 R D NOTE TO ALL"RIDS" RECIPIENTS:

D D PLEASE HELP US TO REDUCE WASTE!CONTACT THE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT.20079)TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR'8 ENCL 16

'8~0 Indiana Michigan Power Company P.O.Box 16631 Cofumbus, OH 43216 AEP:NRC:1143 Donald C.Cook Nuclear Plant Units 1 and 2 License Nos.50-315 and 50-316 Docket Nos.DPR-58 and DPR-74 SNUBBER TECHNICAL SPECIFICATION CHANGES U.S.Nuclear Regulatory Commission Document Control Desk Washington, D.C.20555 Attn: T.E, Murley May 1, 1992

Dear Dr.Murley:

This letter and its attachments constitute an application for amendment of the license conditions and Technical Specifications (T/Ss)for the Donald C.Cook Nuclear Plant Units 1 and 2.Specifically, the changes proposed in this letter revise the visual inspection surveillance requirements and the acceptance criteria associated with T/Ss 3/4.7.8 and 3/4.7.7,"Snubbers," Units 1 and 2 respectively, in accordance with the guidance provided in Generic Letter 90-09,"Alternative Requirements for Snubber Visual Inspection Intervals and Corrective Actions," dated December 11, 1990.An alternate schedule for visual inspections has been developed by the NRC that maintains the same confidence level as the existing schedule and.will generally allow visual inspections and corrective actions to be performed during plant outages.In addition, we are proposing to remove the snubber component lists in Tables 3.7.4 and 3.7.9 of T/Ss 3/4.7.8 and 3/4.7.7 for Units 1 and 2 respectively, in accordance with the guidance provided in Generic Letter 84-13,"Technical Specification for Snubbers," dated May 3, 1984.Attachment 1 provides a detailed description of the proposed changes, the justification for the changes, and our proposed determination of no significant hazards consideration performed pursuant to 10 CFR 50.92.Attachment 2 contains the existing T/S pages marked to reflect the proposed changes.Attachment 3 contains the proposed T/S pages.We believe that the proposed changes will not result in (1)a significant change in the types of any effluent that may be released offsite, or (2)a significant increase in individual or cumulative occupational radiation exposure.9205050144 920501 PDR~ADOCK 05000315 ,P"'DR fg a~~-A it Dr.T.E.Murley-2-AEP:NRC:1143 These proposed changes have been reviewed by the.Plant Nuclear Safety Review Committee and the Nuclear Safety and Design Review Committee.

In compliance with the requirements of 10 CFR 50.91 (b)(1), copies of this letter and its attachments have been transmitted to the Michigan Public Service Commission and the Michigan Department of Public Health.This document has been prepared following Corporate procedures which incorporate a reasonable set of controls to ensure its accuracy and completeness prior to signature by the undersigned.

Sincerely, E.E.Fitzpatrick Vice President tow Attachments CC;D.H.Williams, Jr.A.A.Blind-Bridgman J.R.Padgett G.Charnoff NFEM Section Chief A.B.Davis-Region III NRC Resident Inspector-Bridgman