Letter Sequence Acceptance Review | |
---|---|
CAC:L-2017-LLA-0101, (Approved, Closed) | |
Initiation Administration Questions
| |
MONTHYEARML18030A7342018-01-30030 January 2018
[Table View]COL Docs - VOG-RAI-Letter for LAR 17-033.docx Project stage: Acceptance Review ML18038B1152018-02-13013 February 2018 LAR-17-033 Audit Plan Project stage: Request ND-18-0111, Supplement to Request for License Amendment Regarding: Passive Residual Heat Removal Heat Transfer and In-containment Refueling Water Storage Tank Heat Up Test Acceptance Criteria Change (LAR-17-033S1)2018-02-28028 February 2018 Supplement to Request for License Amendment Regarding: Passive Residual Heat Removal Heat Transfer and In-containment Refueling Water Storage Tank Heat Up Test Acceptance Criteria Change (LAR-17-033S1) Project stage: Supplement ML18059A7552018-03-12012 March 2018 Audit Report for Vogtle Electric Generating Plant, Units 3 and 4, Request for License Amendment and Exemption: Prhr Heat Transfer and IRWST Heat Up Test Acceptance Criteria Change (LAR 17-033) Project stage: Other ML18085A0512018-04-11011 April 2018 Safety Evaluation Report - Vogtle Electric Generating Plant Units 3 and 4 - LAR 17-033 Project stage: Approval ML18085A0452018-04-11011 April 2018 Issuance of Amendments No. 120 and 119 Passive Residual Heat Removal Heat Transfer and In-Containment Refueling Water Storage Tank Heat Up Test Acceptance Criteria (LAR 17-033) Project stage: Request ML18085A0502018-04-11011 April 2018 Attachment - Vogtle Electric Generating Plant Unit 4 LAR 17-033 Project stage: Acceptance Review ML18085A0492018-04-11011 April 2018 Amendment - Vogtle Electric Generating Plant Unit 4 LAR 17-033 Project stage: Other ML18085A0482018-04-11011 April 2018 Attachment - Vogtle Electric Generating Plant Unit 3 LAR 17-033 Project stage: Acceptance Review ML18085A0472018-04-11011 April 2018 Amendment - Vogtle Electric Generating Plant Unit 3 LAR 17-033 Project stage: Other ML18085A0462018-04-11011 April 2018 Cover Letter for Vogtle Electric Generating Plant Units 3 and 4 -LAR-17-033 Project stage: Other 2018-02-28 |
ML18085A050 | |
Person / Time | |
---|---|
Site: | Vogtle |
Issue date: | 04/11/2018 |
From: | Kallan P B NRC/NRO/DNRL/LB4 |
To: | Whitley B H Southern Nuclear Operating Co |
kallan p/415-2809 | |
Shared Package | |
ML18085A045 | List: |
References | |
CAC L-2017-LLA-0101, LAR 17-033 | |
Download: ML18085A050 (3) | |
Similar Documents at Vogtle | |
---|---|
Category:License-Combined License (COL) (New/Renewal/Amendments) DKT 52
MONTHYEARML23243B0542023-12-19019 December 2023
[Table view]VEGP Unit 4 Amendment No. 193 - Enclosure 2 ML23243A9682023-12-19019 December 2023 VEGP Unit 3 Amendment No. 197 - Enclosure 1 ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action ML23159A0972023-07-31031 July 2023 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 23-001) ML23072A2722023-05-0101 May 2023 Enclosure 1 - LAR 22-005 Amendment No. 191 Vogtle Unit 3 ML23072A2732023-05-0101 May 2023 Enclosure 2 - LAR 22-005 Amendment No. 188 Vogtle, Unit 4 ML23072A2762023-05-0101 May 2023 Attachment to Enclosure 2 - VEGP U4 Amendment 188 LAR-22-005 ML23037A0892023-02-0808 February 2023 Amendment - Vogtle Unit 3 Amendment No. 190, Tech Spec Exceptions for In-Containment Refueling Water Storage Tank Operability Prior to Initial Criticality (Exigent Circumstances) ML20290A2822022-08-0303 August 2022 Finding That Acceptance Criteria in the Combined License Are Met (10 CFR 103g - Finding) ML21237A2342021-10-15015 October 2021 Amendment Unit 3 - Vogtle Electric Generating Plant LAR 21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2352021-10-15015 October 2021 Attachment Unit 3 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2372021-10-15015 October 2021 Attachment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2362021-10-15015 October 2021 Amendment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21217A0242021-09-17017 September 2021 Amendment No. 187 - Vogtle Electric Generating Plant Unit 3 ML21217A0252021-09-17017 September 2021 Amendment No. 185 - Vogtle Electric Generating Plant Unit 4 ML21217A0272021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment No. 185 ML21217A0262021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment No. 187 ML20314A0132020-12-0707 December 2020 License Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 20-005) ML20314A0142020-12-0707 December 2020 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment 184 (LAR-20-005) ML20314A0112020-12-0707 December 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 186 (LAR-20-005) ML20314A0102020-12-0707 December 2020 License Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-005) ML20247J4612020-10-14014 October 2020 Amendment 183 - Vogtle Electric Generating Plant Unit 4 (LAR 20-004) ML20247J4592020-10-14014 October 2020 Amendment 185 - Vogtle Electric Generating Plant Unit 3 (LAR 20-004) ML20237F4922020-09-24024 September 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 184 (LAR-20-003) ML20237F4942020-09-24024 September 2020 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment 182 (LAR-20-003) ML20237F4932020-09-24024 September 2020 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 20-003) ML20237F4912020-09-24024 September 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-003) ML20196L6772020-08-11011 August 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 183 for LAR-20-002 ML20196L6782020-08-11011 August 2020 Amendment 181 - Vogtle Electric Generating Plant Unit 4 for LAR 20-002 ML20196L6792020-08-11011 August 2020 Attachment - Vogtle Electric Generating Plant Unit 4 for Amendment 181 for LAR-20-002 ML20132A0762020-08-0404 August 2020 Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 20-001) ML20059N7792020-05-12012 May 2020 Amendment 181 - LAR-19-010: Auxiliary Building Room Heatup ML20059N7822020-05-12012 May 2020 Amendment 180 - LAR-19-010: Auxiliary Building Room Heatup ML20106F1632020-05-12012 May 2020 Attachment to Amendment 180 - LAR-19-010: Auxiliary Building Room Heatup ML20106F1622020-05-12012 May 2020 Attachment to Amendment 181 - LAR-19-010: Auxiliary Building Room Heatup ML20120A0072020-04-30030 April 2020 Attachment for Amendment 178 Cyber Security Plan Changes (LAR-19-020) ML20106F1592020-04-30030 April 2020 Attachment for Amendment 179 Cyber Security Plan Changes (LAR-19-020) ML20057E1172020-04-30030 April 2020 Amendment 178 - Issuance of Amendments for Cyber Security Plan Changes (LAR-19-020) ML20057E1062020-04-30030 April 2020 Amendment 179 - Issuance of Amendments for Cyber Security Plan Changes (LAR-19-020) ML20064E6682020-03-23023 March 2020 Enclosure 4: Supplemental Attachment to License Amendment No. 148 for COL No. NPF-91 ML20064E6802020-03-23023 March 2020 Enclosure 5: Supplemental Attachment to License Amendment No. 147 for COL No. NPF-92 ML20064E5722020-03-23023 March 2020 Supplemental Attachment to License Amendment No. 36 for COL No. NPF-92 ML20064E6122020-03-23023 March 2020 Enclosure 2: Supplemental Attachment to License Amendment No. 125 for COL No. NPF-91 ML20064E6282020-03-23023 March 2020 Enclosure 3: Supplemental Attachment to License Amendment No. 124 for COL No. NPF-92 ML20013G6882020-02-0303 February 2020 Amendment - Vogtle Electric Generating Plant Unit 4 ML19350C7142020-01-28028 January 2020 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 19-015) ML19350C6862020-01-28028 January 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 19-015) ML19350C7002020-01-28028 January 2020 Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 19-015).d 2023-07-31 |