Thank You Letter Regarding Response to Notice of Violation and NRC Inspection Report 05000298/2011002
ML111600340
Person / Time
Site: Cooper Entergy icon.png
Issue date: 06/08/2011
From: Vincent Gaddy
NRC/RGN-IV/DRP/RPB-C
To: O'Grady B J
Nebraska Public Power District (NPPD)
References
EA-2011-090, IR-11-002
Download: ML111600340 (2)


See also: IR 05000298/2011002

Text

June 8, 2011 EA-2011-090 Mr. Brian J. O'Grady, Vice President-Nuclear and Chief Nuclear Officer Nebraska Public Power District 72676 648A Avenue Brownville, NE 68321 SUBJECT: RESPONSE TO NOTICE OF VIOLATION AND NRC INSPECTION REPORT 05000298/201102 Dear Mr. O'Grady: Thank you for your letter date June 2, 2011, in response to our May 3, 2011, letter and Notice of Violation regarding the failure to appropriately assess and manage the risk associated with planned maintenance activities, per 10 CFR 50.65(a)(4), and to restore compliance within a

reasonable time after noncited violations were identified in previous inspection reports. We have reviewed your reply and find it responsive to the concerns raised in our Notice of Violation. We will review the implementation of your corrective actions during a future inspection to

determine that full compliance has been achieved and will be maintained.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response, if you choose to provide one for cases where a response is not

required, will be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy or proprietary, information so that it can be made available to the Public without redaction. Sincerely, /RA/ Vince Gaddy, Chief Project Branch C Division of Reactor Projects Docket: 50-298 License: DPR-46

Distribution via ListServ UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 EAST LAMAR BLVD, SUITE 400ARLINGTON, TEXAS 76011-4125

Nebraska Public Power District - 2 - Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov) Deputy Regional Administrator (Art.Howell@nrc.gov) DRP Director (Kriss.Kennedy@nrc.gov) DRP Deputy Director (Troy.Pruett@nrc.gov) DRS Director (Anton.Vegel@nrc.gov) Senior Resident Inspector (Jeffrey.Josey@nrc.gov) Resident Inspector (Michael.Chambers@nrc.gov) Branch Chief, DRP/C (Vincent.Gaddy@nrc.gov) Senior Project Engineer, DRP/C (Bob.Hagar@nrc.gov) Project Engineer, DRP/C (Rayomand.Kumana@nrc.gov) CNS Administrative Assistant (Amy.Elam@nrc.gov) Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov) Project Manager (Lynnea.Wilkins@nrc.gov) Branch Chief, DRS/TSB (Dale.Powers@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov) Congressional Affairs Officer (Jenny.Weil@nrc.gov) ACES Branch Chief (Nick.Taylor@nrc.gov) RIV/ETA:OEDO (Stephanie.Bush-Goddard@nrc.gov) OEMail Resource ROP Reports

R:\_Reactors\2011\_CNS\CNS NOV IR 05000298 2011002.docx ADAMS: No Yes SUNSI Review Complete Reviewer Initials: Publicly Available Non-Sensitive Non-publicly Available Sensitive C:DRP/C VGaddy /RA/ 6/8/2011 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax