Status of the NRC Review of the Gle Compliance Plan
ML22308A045
Person / Time
Site: 07007033
Issue date: 11/04/2022
From: Matt Bartlett
NRC/NMSS/DFM/FFLB
To: Jenny P
Global Laser Enrichment
References
Download: ML22308A045 (1)


Text

From: Matt Bartlett To: Jenny, Pat

Subject:

AWARENESS: Status of the NRC Review of the GLE Compliance Plan Date: Friday, November 4, 2022 8:12:00 AM

Pat, The Compliance Plan decision letter has been updated to include an extension of the 32 CFR 117 enforcement discretion by 60 days (e.g., January 29, 2022). The cover letter and security evaluation report package is in formal concurrence, which I hope to have completed by November 11, 2022. You should see it the following week.

This email will be docketed in public ADAMS.

Thanks.

Sincerely, Matt Bartlett Sr. Project Manager NMSS/DFM/FFLB 301-415-7154