NRR E-mail Capture - Acceptance Review for Summer to Defer Weld Examinations (L-2022-LLR-0052)
ML22173A029
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 06/17/2022
From: Ed Miller
Plant Licensing Branch II
To: Erica Combs
South Carolina Electric & Gas Co
References
L-2022-LLR-0052
Download: ML22173A029 (2)


Text

From: Miller, Ed Sent: Friday, June 17, 2022 2:51 PM To: Erica.N.Combs@dominionenergy.com

Subject:

Acceptance Review for Summer to Defer Weld Examinations (L-2022-LLR-0052)

Erica, By letter dated June 9, 2022 (Agencywide Documents Access and Management System Package Accession No. ML22160A477), Dominion Energy, submitted a relief request for VC Summer Unit 1. The request would allow deferral of ASME Code Section XI ISI examinations for specified Pressurizer and Steam Generator pressure-retaining welds and full penetration welded nozzles. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to begin its detailed technical review. The acceptance review is also intended to identify whether the request has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your request and concluded that it does provide technical information in sufficient detail to enable the NRC staff to begin its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment.

Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified in requests for additional information despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> to complete. The NRC staff expects to complete this review by April 1, 2023. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they can change due to several factors including requests for additional information, unanticipated addition of scope to the review, review by NRC advisory committees, or hearing-related activities.

If you have any questions, please contact me at (301) 415-2481 or ed.miller@nrc.gov.

Ed Miller (301) 415-2481

Hearing Identifier: NRR_DRMA Email Number: 1681 Mail Envelope Properties (SA1PR09MB7487B2641B168C9E4BB62AE2E9AF9)

Subject:

Acceptance Review for Summer to Defer Weld Examinations (L-2022-LLR-0052)

Sent Date: 6/17/2022 2:51:18 PM Received Date: 6/17/2022 2:51:00 PM From: Miller, Ed Created By: Ed.Miller@nrc.gov Recipients:

"Erica.N.Combs@dominionenergy.com" <Erica.N.Combs@dominionenergy.com>