NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information LAR-16-01490 NFPA-805 Program Revisions
ML19072A144
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 03/13/2019
From: Shawn Williams
Plant Licensing Branch II
To: Maria Moore
South Carolina Electric & Gas Co
References
L-2018-LLA-0233
Download: ML19072A144 (3)


Text

NRR-DMPSPEm Resource From: Williams, Shawn Sent: Wednesday, March 13, 2019 10:51 AM To: MOORE, MICHAEL S Cc: DALICK, SARA BETH ; JUSTIN.BOUKNIGHT@scana.com

Subject:

Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information RE:

LAR-16-01490 NFPA-805 Program Revisions (EPID No. L-2018-LLA-0233)

Attachments: Summer Post NFPA 805 RAIs.docx

Dear Mr. Moore,

By letter dated August 29, 2018 (Agencywide Documents Access and Management System Accession No. ML18242A658)

South Carolina Electric & Gas Company (SCE&G) requested changes to the Operating License for the Virgil C. Summer Nuclear Plant, Unit 1.

The proposed amendment would revise license conditions and approve the following:

  • Changes to plant modifications evaluated using fire probabilistic risk assessment methods and approaches that have been previously accepted in Amendment No. 199 or that have been accepted for another nuclear power plant station .

o NFPA 805 Section 3.3.4, Insulation Materials o NFPA 805 Section 3.3.5.1, Wiring above Suspended Ceilings The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the submittal and determined that additional information is needed to complete its review as discussed in the attachment. During a clarification call on March 13, 2019, Mr. Bouknight, of your staff agreed that SCE&G would respond within 45 days of the date of this e-mail. Please note that the NRC staff's review is continuing and further requests for information may be developed.

If you have any questions, please contact me at 301-415-1009 or Shawn.Williams@nrc.gov.

Sincerely, Shawn A. Williams, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 50-395

Enclosure:

Request for Additional Information 1

Hearing Identifier: NRR_DMPS Email Number: 858 Mail Envelope Properties (BL0PR0901MB3154E37CD0C9B78CE54B4E0D904A0)

Subject:

Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information RE: LAR-16-01490 NFPA-805 Program Revisions (EPID No. L-2018-LLA-0233)

Sent Date: 3/13/2019 10:51:03 AM Received Date: 3/13/2019 10:51:05 AM From: Williams, Shawn Created By: Shawn.Williams@nrc.gov Recipients:

"DALICK, SARA BETH " <SARA.DALICK@scana.com>

Tracking Status: None "JUSTIN.BOUKNIGHT@scana.com" <JUSTIN.BOUKNIGHT@scana.com>

Tracking Status: None "MOORE, MICHAEL S" <MICHAEL.S.MOORE@scana.com>

Tracking Status: None Post Office: BL0PR0901MB3154.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 1675 3/13/2019 10:51:05 AM Summer Post NFPA 805 RAIs.docx 29733 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received:

REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST TO REVISE NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 FIRE PROTECTION PROGRAM VIRGIL C. SUMMER NUCLEAR STATION, UNIT NO. 1 DOCKET NO. 50-395 By letter dated August 29, 2018 (Agencywide Document Access and Management System (ADAMS)

Package Accession No. ML18242A657), South Carolina Electric and Gas (SCE&G), submitted a license amendment request (LAR) for the Virgil C. Summer Nuclear Station, Unit 1 (VCSNS), to make changes to its approved fire protection program (FPP) under 10 CFR 50.48(c). In its LAR, the licensee proposed to make several changes to its FPP including changes to plant modifications, use of performance-based alternatives to the requirements of NFPA 805, Chapter 3, and several clarifications and editorial corrections. Based on the information provided by the licensee, the NRC staff requests that the licensee provide the information below.

Probabilistic Risk Assessment (PRA), Request for Additional Information (RAI) 01 In Enclosure 1, Attachment 1, to the licensees letter dated August 29, 2018, the licensee stated that refinements were made in the main control room abandonment (MCR) model, to make the model symptom-based. The LAR is not clear on whether these refinements go beyond those described in the NFPA 805 LAR (ADAMS Package Accession No. ML113320227). Describe the refinements to the MCR abandonment model and identify the human reliability analysis (HRA) approach used to modify the model, and discuss whether it was used previously to support the NFPA 805 LAR or in another plant LAR and subsequent amendment. In addition, provide clarification regarding whether this refinement to the PRA model is consistent with plant procedures for MCR abandonment.

PRA RAI 02 In Enclosure 1, Attachment 1, to the licensees letter dated August 29, 2018, the licensee stated that heat release rates (HRRs) were increased to account for secondary combustibles of insulation and high density polyethylene (HDPE) piping. The LAR is not clear on the approach used and its basis. Provide a summary of the approach used for increasing the HRRs and discuss whether it was used previously to support the NFPA 805 LAR or in another plant LAR and subsequent amendment.

PRA RAI 03 In Enclosure 1, Attachment 1, to the licensees letter dated August 29, 2018, the licensee stated that refinements were made to the reactor coolant pump (RCP) seal loss of coolant accident (LOCA) model based on the RCP seal upgrades. The LAR is not clear on whether these refinements go beyond those described in the NFPA 805 LAR. Describe the refinements to the RCP seal LOCA model and discuss whether the approach was used previously to support the NFPA 805 LAR or in another plant LAR and subsequent amendment and if these changes constitute a PRA upgrade. Provide the basis for the conclusion regarding whether the refinements are considered a PRA upgrade. Please indicate whether you have taken credit for abeyance seals in your PRA model.