|
---|
Category:Letter
MONTHYEARML23180A1512023-06-29029 June 2023 LLC, Request for Exemption to the Reporting Requirements of 10 CFR 50.46(a)(3) ML21102A3072021-04-15015 April 2021 OEDO-21-00155 - Lessons-Learned from the Design Certification Review of the NuScale Power, LLC, Small Modular Reactor ML21050A4312021-02-19019 February 2021 LLC - Lessons-Learned from the Design Certification Review of the NuScale Power, LLC Small Modular Reactor ML20247J5642020-09-11011 September 2020 Standard Design Approval for the NuScale Power Plant Based on the NuScale 600 Standard Plant Design Certification Application ML20231A8042020-08-28028 August 2020 Final Safety Evaluation Report for the NuScale Standard Plant Design ML20224A4602020-08-25025 August 2020 OEDO-20-00292-Response to the Advisory Committee on Reactor Safeguards Letter on NuScale Power, LLC, Report on the Safety Aspects of the NuScale Small Modular Reactor ML20231A5982020-08-25025 August 2020 OEDO-20-00285_NuScale Area of Focus - Boron Redistribution ML20210M8902020-07-29029 July 2020 Area of Focus - Boron Redistribution ML20195A5872020-07-13013 July 2020 LLC - Submittal of Draft Operator Licensing and Examination Standard for NuScale Small Modular Reactors ML20195C7662020-07-13013 July 2020 LLC Request for Standard Design Approval Based on the NuScale Standard Plant Design Certification Application ML20192A3262020-07-10010 July 2020 LLC, Submittal of Environmental Report: Revision Status ML20198M3932020-07-0202 July 2020 LLC Submittal of Revised Packing Slip for Submittal of the NuScale Standard Plant Design Certification Application, Revision 4.1, Dated June 19, 2020 ML20174A3472020-07-0101 July 2020 OEDO-20-00220 - Area of Focus - Probabilistic Risk Assessment and Emergency Core Cooling System Valve Performance ML20184A2872020-07-0101 July 2020 LLC Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topic - Boron Redistribution and General Design Criterion 33, PM-0720-70785, Revision 0 ML20181A4322020-06-22022 June 2020 Final SER for NuScale TR-0516-49416 NON-Loss-of-Coolant Analysis Model, Rev 3 (Letter) ML20181A2702020-06-22022 June 2020 Final SER for NuScale TR-0516-49422 Loss-of-Coolant Analysis Model, Rev 2 (Letter) ML20198M3922020-06-19019 June 2020 LLC - Submittal of the NuScale Standard Plant Design Certification Application, Revision 4.1 ML20171A7312020-06-19019 June 2020 LLC, Submittal of Riser Flow Hole Methodology and Associated Changes to Final Safety Analysis Report Incorporating Its Use ML20157A2232020-06-0303 June 2020 Letter to NuScale Requesting -A for TR-0716-50350 ML20150C5172020-05-29029 May 2020 LLC Submittal of Presentation Materials Entitled NRC Public Meeting Presentation: Boron Redistribution and Associated Design and DCA Changes, PM-0620-70336, Revision 0 ML20150E1772020-05-29029 May 2020 LLC - Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topic - Extended Dhrs Operation and RCS Boron Redistribution (Closed Session), PM-0620-70243, Revision 0 ML20150C8812020-05-29029 May 2020 LLC Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topic - Boron Redistribution and Associated Design and DCA Changes, PM-0620-70244, Revision 0 ML20149M1192020-05-28028 May 2020 LLC Summary of Impacts to Erai 8930 Response and Discussion on the Exemption from General Design Criterion 33 ML20141L8082020-05-20020 May 2020 LLC Submittal of Containment Response Analysis Methodology Technical Report, TR-0516-49084, Revision 3 ML20141N0122020-05-20020 May 2020 LLC Submittal of Changes to Final Safety Analysis Report, Section 6.2, Containment Systems, Section 6.3, Emergency Core Cooling System, and Technical Report TR-0516-49084, Containment Response Analysis Methodology Technical Report ML20141M7642020-05-20020 May 2020 LLC Submittal of Nuclear Steam Supply System Advanced Sensor Technical Report, TR-0316-22048, Revision 3 ML20141L7872020-05-20020 May 2020 LLC, Submittal of Second Updates to Standard Plant Design Certification Application, Revision 4 ML20141L8162020-05-20020 May 2020 LLC, Submittal of Long-Term Cooling Methodology, TR-0916-51299, Revision 3 ML20141M1142020-05-20020 May 2020 LLC Submittal of NuScale Instrument Setpoint Methodology Technical Report, TR-0616-49121, Revision 3 ML20141L8042020-05-20020 May 2020 LLC Submittal of Technical Specifications Regulatory Conformance and Development, TR-1116-52011, Revision 4 ML20128J3162020-05-18018 May 2020 OEDO-20-00167 - Response to the ACRS Letter on Combustible Gas Monitoring ML20133K0882020-05-12012 May 2020 LLC, Submittal of Presentation Materials Entitled Public Meeting Presentation: Topic - Emergency Core Cooling System (ECCS) Boron Distribution (Closed Session), PM-0420-69512, Revision 0 ML20133J9142020-05-11011 May 2020 LLC Submittal of Presentation Materials Entitled Public Meeting Presentation: Topic - Emergency Core Cooling System (ECCS) Boron Distribution, PM-0420-69511, Revision 0 ML20112F4552020-05-0101 May 2020 LLC, Design Certification Application Phases 5 and 6 Review Status ML20107F8492020-05-0101 May 2020 OEDO-2000140 - NuScale Area of Focus - Helical Tube Steam Generator Design ML20104A0792020-04-27027 April 2020 OEDO-20-00115 - Safety Evaluation Report for Topical Report TR-0516-49416, Revision 2, Non-Loss-of-Coolant Accident Analysis Methodology ML20099H0802020-04-0808 April 2020 LLC - Submittal of Presentation Materials Entitled NRC Public Meeting: Revisions to Nuscale'S EPZ Sizing Methodology Topical Report, PM-0420-69598, Revision 0 ML20098G2372020-04-0707 April 2020 Nuscale Power, LLC Submittal of Remaining Closure Items for the Emergency Core Cooling System Valve Failure Mode Effects Analysis Audit Items ML20097F1922020-04-0606 April 2020 Nuscale Power, LLC Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: Nuscale Topic - Hydrogen/Oxygen Monitoring, PM-0420-69518, Revision 0 ML20094H6742020-04-0303 April 2020 LLC Submittal of Presentation Materials Entitled ACRS Full Committee Presentation NuScale Topic-Probabilistic Risk Assessment with a Focus on Emergency Core Cooling System Analysis PM-0420-69559, Revision 0 ML20092L8992020-04-0101 April 2020 LLC - Submittal of Updates to Standard Plant Design Certification Application, Revision 4 ML20072M6682020-03-30030 March 2020 Response to NuScale Letter Dated February 24, 2020, on Planned SDA Application Content ML20072H3332020-03-0909 March 2020 LLC - Submittal of Presentation Materials Entitled Public Meeting Presentation: Topic - Emergency Core Cooling System (ECCS) Boron Distribution, PM-0320-69218, Revision 0 ML20057D9002020-03-0606 March 2020 Submittal of Errata to Final SE for NuScale Power, LLC TR-1010-859-NP-A, Quality Assurance Program Description for the NuScale Power Plant ML20062F7262020-03-0505 March 2020 Request for Withholding Information from Public Disclosure for Nuscale Power, LLC Letter Public ML20069A1572020-03-0404 March 2020 LLC - Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topical Report-Rod Ejection Accident Methodology, PM-0320-69146, Revision 0 ML20069A1772020-03-0404 March 2020 LLC - Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topical Report-Non-Loss-of-Coolant Accident, PM-0320-69141, Revision 0 ML20069A9632020-03-0404 March 2020 LLC Submittal of Presentation Materials Entitled ACRS Full Committee Presentation: NuScale Topical Report, Loss-of-Coolant Accident Evaluation Model, PM-0320-69138, Revision 0 ML20066G2802020-03-0303 March 2020 LLC, Submittal of Presentation Materials Entitled ACRS Subcommittee Presentation: NuScale Topic - Hydrogen Monitoring, PM-0220-69071, Revision 0 ML20066G2882020-02-28028 February 2020 LLC Submittal of Presentation Materials Titled ACRS Full Committee Presentation: NuScale - Steam Generator Design (Closed Session), PM-0220-69053, Revision 0 2023-06-29
[Table view] |
Text
August 25, 2020 Matthew W. Sunseri, Chairman Advisory Committee on Reactor Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
RESPONSE TO THE ADVISORY COMMITTEE ON REACTOR SAFEGUARDS LETTER ON THE NUSCALE POWER, LLC, REPORT ON THE SAFETY ASPECTS OF THE NUSCALE SMALL MODULAR REACTOR
Dear Mr. Sunseri:
On behalf of the U.S. Nuclear Regulatory Commission (NRC) staff, I would like to thank you for the letter from the Advisory Committee on Reactor Safeguards (ACRS or the Committee) dated July 29, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20211M386). In that letter, the ACRS reported on the Committees review of the NRC staffs safety evaluation report (SER) with no open items for the NuScale Power, LLC (NuScale), design certification application and standard design approval (SDA) application for its small modular reactor. I appreciate the time and effort the ACRS has devoted to this review, as reflected in meetings held with the ACRS Full Committee on July 21-24, 2020.
The ACRS letter included the following conclusions and recommendations:
- 1. The NuScale small modular reactor is a natural-circulation, pressurized water reactor that incorporates unique design and passive safety features, providing enhanced margins of safety. There is reasonable assurance that it can be constructed and operated without undue risk to the health and safety of the public.
Staff Response: The staff agrees with the ACRS conclusion.
- 2. The NRC staffs final SER for the NuScale design should be issued.
Staff Response: The staff agrees with the ACRS conclusion.
- 3. A design certification and SDA for the NuScale applications should be issued, subject to the staffs proposed exclusions regarding the finality of design requirements: shield wall design, containment leakage from combustible gas monitoring, and steam generator tube structural and leakage integrity.
M. Sunseri Staff Response: The staff agrees with the ACRS conclusion.
For these three concerns, the staffs proposed appendix to Title 10 of the Code of Federal Regulations (10 CFR) Part 52, Licenses, certifications, and approvals for nuclear power plants, that codifies the NuScale design certification will identify that these concerns are not resolved within the meaning of 10 CFR 52.63(a)(5) and will state that a future applicant is responsible for providing the design information to address these concerns before the NRC issues any license. The SDA will also specifically list these items as not being resolved.
- 4. We identify in this letter report several potentially risk-significant items that are not completed at this time. We request the opportunity to review the qualification of emergency core cooling system valve performance, the identification of a successful recovery strategy to prevent potential reactivity insertion accidents associated with boron dilution sequences, and the updated probabilistic risk assessment.
Staff Response: The staff acknowledges the ACRS request.
The staff anticipates additional information will be available on these topics as part of a future license application that will reference the NuScale small modular reactor design. The staff looks forward to working with the Committee on the review of that future application. Additionally, the NRC letter to the ACRS, OEDO-20-00285, dated August 25, 2020, responding to the ACRS letter dated July 29, 2020, on the NuScale boron redistribution area of focus (ADAMS Accession No. ML20210M890), provides additional information on boron dilution and the DCA probabilistic risk assessment.
The NRC staff appreciates the ACRSs review of this application for the NuScale Small Modular Reactor. The Committees novel review approach, which focused more on critical issues, significantly complemented the staffs efforts to ensure that its review was appropriately risk informed, efficient and thorough.
Sincerely, Margaret M. Doane Digitally signed by Margaret M. Doane Date: 2020.08.25 14:45:53 -04'00' Margaret M. Doane Executive Director for Operations Docket No.52-048 cc: Chairman Svinicki Commissioner Baran Commissioner Caputo Commissioner Wright Commissioner Hanson SECY
Pkg: ML20217L596 Ltr: ML20224A460 *via e-mail NRR-106 OFFICE NRR/DNRL/NRLB: PM NRR/DNRL/NRLB: LA QTE NAME GCranston* SGreen* JDougherty*
DATE 08/21/2020 08/17/2020 08/18/2020 OFFICE NRR/DNRL/NRLB: BC NRR/DNRL: D NRR: D NAME MDudek* ABradford* HNieh* RTaylor for*
DATE 08/21/2020 08/19/2020 08/21/2020 OFFICE NRR/EDO NAME MDoane DATE 08/25/2020