MONTHYEARML24038A1742024-02-0707 February 2024 Pre-submittal Meeting Slides ML24019A1512024-01-22022 January 2024 Slides - Modification of Browns Ferry Technical Specifications to Eliminate LCO 3.3.2.1 Actions C.2.1.1 and C.2.1.2 for Rod Worth ML24003A8532024-01-0303 January 2024 January 4, 2024 Presubmittal Meeting Presentation-Risk Informed Process for Evaluations (RIPE) License Amendment Request for Safety Injection Tank (SIT) LCO (EPID: L?2023?LRM-0108) ML23296A0162023-10-20020 October 2023 October 20, 2023 Presubmittal Meeting Presentation - 1R24 Pressurizer Nozzle Repair - RR-70 (EPID: L?2023?LLR-0057) ML23240A3232023-08-31031 August 2023 APS Presentation Slides for Pre-Submittal Meeting on 8/31/23, Alloy-600 Management Program Plan ML23192A0102023-07-11011 July 2023 NRC RIPE 7-11-23 Public Meeting Presentation Slides ML23144A0252023-05-25025 May 2023 APS Presentation Slides for Pre-Submittal Meeting on 5/25/23, Przr Surge Line ML23093A0252023-04-30030 April 2023 April 5, 2023, Presubmittal Meeting Presentation - Containment Temperature and Safety Injection Tank Volume Requirements LAR ML23055B0572023-03-0101 March 2023 March 1, 2023 Presubmittal Meeting Presentation - Request for Use of Mururoa V4F1 and MTH2 Supplied Air Suits (EPID: L?2023?LRM-0012) ML22312A5952022-11-0808 November 2022 Independent Spent Fuel Storage Installation, Submittal of Annual Financial Reports 2021 ML22299A1812022-10-26026 October 2022 Presubmittal Meeting Presentation - License Amendment Request - Adoption of TSTF-107-A Separate Control Rods That Are Untrippable Versus Inoperable and Change to TS 3.1.5 Condition B (EPID: L?2021?LRM-0081) ML22096A0052022-04-0606 April 2022 TSTF-487 LAR Pre-submittal Public Meeting Presentation Slides ML22025A0012022-01-25025 January 2022 1/25/22 Pre-submittal Meeting Presentation Slides for RR-69 to Extend Containment Tendon Inspection by Three Months Beyond 2/8/22 ML21342A0502021-12-0808 December 2021 TSTF-567 LAR Pre-submittal Public Meeting Presentation Slides ML21320A1032021-11-17017 November 2021 RIPE Exemption 11-17-21 Pre-submittal Public Meeting Presentation Slides ML21278B0912021-10-0606 October 2021 Presubmittal Meeting with Arizona Public Service Company Regarding Relief Request No. 68 for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (EPID L-2021-LRM-0104) (Slides) ML21243A5432021-09-0101 September 2021 Request for Partial Exemption from 10 CFR 50.62(c)(1) Risk-Informed Process for Evaluations (RIPE) ML21194A2502021-08-10010 August 2021 RIC 2021 - Ai EPRI-Artificial Intelligence and Development at EPRI ML21165A1832021-06-14014 June 2021 RR-67 6-16-21 Pre-Submittal Public Meeting Presentation Slides ML21131A0132021-05-13013 May 2021 License Transfer from Pnm to SRP, 5-13-21 Pre-submittal Public Meeting Presentation Slides ML21130A6462021-05-13013 May 2021 Pre-Submittal Meeting with NRC on May 13, 2021 Application for Transfer of Minority Interests in Palo Verde Nuclear Generating Station, Units 1 and 2 Subject to Expiring Leases ML21055A8502021-02-24024 February 2021 Public Meeting Summary ML21025A0032021-01-26026 January 2021 Risk-Informed Process for Evaluations (RIPE) - NEI Public Meeting Presentation Slides ML21025A0042021-01-25025 January 2021 Risk-Informed Process for Evaluations (RIPE) - NRC Public Meeting Presentation Slides ML21011A2752021-01-0606 January 2021 License Amendment Request (LAR) to Revise Containment Leakage Rate Testing Program Frequencies - NRC Pre-Submittal Meeting, January 6, 2021 (Presentation Slides) ML20171A2352020-06-24024 June 2020 Inservice Testing - Supplemental Position Indication Relief Request - NRC Pre-Application Meeting - June 24, 2020 ML19060A2982019-03-0101 March 2019 Transmittal of Audit Presentation Slides Regarding License Amendment Request and Exemption Request to Support the Implementation of Framatome CE16HTP Fuel ML17003A0762017-01-10010 January 2017 Regulatory Audit Report for the November 2-3, 2016, Audit at the Westinghouse Facility in Rockville, MD, for the License Amendment and Exemption Requests Associated with Next Generation Fuel (CAC Nos. MF8076-MF8081) ML17003A0352017-01-0404 January 2017 Summary of Pre-Application Meeting with Arizona Public Service to Discuss a Proposed Second Emergency License Amendment Request to Revise Technical Specification 3.8.1, AC (Alternating Current) Sources - Operating, for Palo Verde Nuclear ML17003A0332016-12-29029 December 2016 Enclosure 2 - APS Meeting Slides ML17003A0862016-11-0303 November 2016 Enclosure 2 Slides Regulatory Audit Report for November 2-3, 2016 ML16253A4112016-09-0707 September 2016 Palo Verde Nuclear Generating Station Generic Letter 2004-02 - September 7, 2016 ML16083A4722016-03-24024 March 2016 NRC Subsequent Pre-Submittal Meeting Next Generation Fuel - Palo Verde, Units 1, 2, and 3 ML16014A1102016-01-20020 January 2016 Draft APS Slides for January 20, 2015, Public Meeting with APS Regarding Upcoming Next Generation Fuel License Amendment Request for Palo Verde, Units 1, 2, and 3 ML15348A0542015-12-15015 December 2015 Slides for December 17, 2015 Public Meeting with APS on Resolution of GL 2004-02 ML15244B2632015-08-27027 August 2015 Slides for Public Meeting with Arizona Public Service Company to Discuss License Amendment Request for Palo Verde Regarding Revised Methodology for Spent Fuel Pool Criticality Analysis ML15236A1342015-08-26026 August 2015 Presentation Slides for Public Meeting with Arizona Public Service Generic Letter 2004-02 for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML15159B2972015-06-0909 June 2015 Near-Term Task Force Recommendation 2.1 (R2.1) Seismic Hazard Evaluation - Arizona Public Service, Palo Verde Nuclear Generating Station Public Meeting - June 9, 2015 ML15156B3312015-06-0909 June 2015 Public Meeting Slides on R2.1 Seismic Hazard Re-Evaluation ML15134A3592015-05-11011 May 2015 5/11/2015, Meeting Slide Regarding Pre-Submittal Meeting for Palo Verde Unit 1, 2, and 3 Updated Spent Fuel Pool Criticality Analysis ML15126A2072015-05-11011 May 2015 Presentation Slides for Prelicensing Meeting with Arizon Public Service Company to Discuss License Amendment Request for Palo Verde, Units 1, 2, and 3, ML15103A2882015-04-0909 April 2015 Presentation on Potential Relief Request About Pressure Boundary Leakage on Reactor Coolant Pump 2A Pipe Nozzle ML15070A2522015-02-18018 February 2015 Pre-Submittal Public Meeting Final Slides on Risk-Informed Completion Times. ML15042A4152015-02-11011 February 2015 Pre-Submittal Public Meeting Draft Slides on Risk- Informed Completion Times ML14184B4112014-06-11011 June 2014 Nrc/Nei/Utility MTG 6/11/14 ML14149A5092014-04-23023 April 2014 4/23/14 Meeting Slide for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 Re. Sig Tube Inspection ML14098A1832014-04-0202 April 2014 4/2/2014 Meeting Slide for Bottom-Mounted Instrument (Bmi) Relief Request 52 Pre-Submittal Meeting ML13309A7202013-11-0505 November 2013 Meeting Presentation for November 5, 2013 Public Meeting Regarding Incorporation of NEI 11-04 Into the QA Program at Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML13308B3322013-11-0404 November 2013 Meeting Presentation for November 4, 2013 Public Meeting Regarding Bmi Leakage ML13197A0952013-07-11011 July 2013 7/11/13 Meeting Slides - Implementation of STAR Program and Replacement of the 2/3 Cycle Mtc Measurement 2024-02-07
[Table view] |
Text
License Amendment Request (LAR) to Revise Containment Leakage Rate Testing Program Frequencies NRC Pre-Submittal Meeting Palo Verde Nuclear Generating Station January 6, 2021
=
Background===
- Extends the testing frequencies for Type A integrated leakage rate test (ILRT) from 10 years to 15 years and select Type C local leakage rate tests (LLRTs) from 60 months to 75 months
- Adopts a more conservative allowable test interval extension of nine months, for Type A, Type B and Type C leakage rate tests 2
Background (Continued)
- This LAR also proposes the following administrative change to TS 5.5.16.a:
- Deletes the information regarding the performance of the next PVNGS Type A tests as these dates have already occurred and the associated Type A tests have been performed
- Change includes updates to the following UFSAR sections:
- Section 1.8 (RG 1.163), Performance-Based Containment Leak-Test Program
- Section 6.2.6, Containment Leakage Testing
Proposed Technical Specification Change 4
Proposed Technical Specification Change 5
Risk Insights A plant specific risk assessment was conducted to support this proposed change.
- The total integrated plant risk for population dose meets the criteria defined in NEI 94-01
- Increase in conditional containment failure probability (CCFP) is small The risk assessment concludes that increasing the ILRT test frequency on a permanent basis to a one-in-fifteen-year frequency is considered to represent a small change in the PVNGS risk profile.
6
Risk Insights (Continued)
A review of the Regulatory Guide 1.200 Revision 3 was conducted to determine if there were any impacts on this proposed change.
The PRA model used to assess this proposed change was issued on July 4, 2020 and reflected the following:
- Includes internal events, flooding, fire and seismic PRA models fully compliant with the endorsed ASME/ANS PRA Standard including NRC exceptions/clarifications at Capability Category II and these models have been peer reviewed
- All Other External Hazards listed in Regulatory Guide 1.200 Revision 3 except seismic events were screened out and the screening was peer reviewed
- Addressed all NRC license conditions from the 10 CFR 50.69 and Risk-Informed Completion Time License Amendments
- All Peer Review Facts and Observations Findings were closed by the NRC endorsed Closure Review Process (observed by NRC staff in June 2020)
- No newly developed methods were utilized in the PRA model
- No additional key assumptions or sources of uncertainty are applicable based on the updated guidance in Regulatory Guide 1.200 Revision 3 7
Precedents
- This LAR is similar in nature to the following approved license amendments to extend the Type A Test Frequency to 15 years and the Type C test frequency to 75 months:
- McGuire Nuclear Station, Units 1 and 2, issued January 31, 2018 (ADAMS Accession No. ML18009A842)
- Vogtle Electric Generating Plant, Units 1 and 2, issued October 29, 2018 (ADAMS Accession No. ML18263A039)
- Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, issued September 10, 2020 (ADAMS Accession No. ML20149K698) 8
Submittal Timeline
- Planning to submit the week of January 11, 2021
- Estimating a 1-year NRC review
- Requesting an implementation period of 90 days 9
Questions