Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Sept 1986
ML20213D825
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 10/31/1986
From: Joann Ireland
LOS ALAMOS NATIONAL LABORATORY
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
CON-FIN-A-7552 Q-DO-TR-86-149, NUDOCS 8611120250
Download: ML20213D825 (4)


Text

_ - _ _ _ _ - - _

i'

',oj y AsA;amos LOs Alamos NationalLaboratory Los Alamos NewMexico87545 October 31, 1986 Q-DO/TR-86-149 Energy Division .

TM@MOWM T NOV - 4 E l

Mr. E. H. Johnson ,

Reactor Project Branch 1 US Nuclear Regulatory Commission Region IV _

611 Ryan Plaza Drive, Suite 1000 Arlington, TX .76011

Dear Mr. Johnson:

SUBJECT:

MONTHLY BUSINESS LETTER REPORT FOR REGION IV--FIN A7552 (TECHNICAL ASSISTANCE TO REGION IV--PORT ST. VRAIN)

Enclosed is the monthly progress report for September 1986. The purpose of this report is to apprise you of any problems, delays, or scheduling constraints that we currently have or anticipate, in addition to keeping you informed about the progress and costs.

Please do not hesitate to call if you have any questions or requests regarding thec. reports.

Sincerely yours, t

John R. Ireland Project Manager for Reactor Safety Programs JRI:ke Enc. Letter Report cy: R. E. Ireland, Region IV D. M. Meyer, Region IV W. H. Poster, Region IV C. A. Anderson, Q-13, MS J576 S. W. Moore, Q-13, MS J576 CRM-4, MS A150 (2)

~

B611120250 861031 PDR  ! I I ADOCK 05000267 P pop ,

An Equal Opportunity Employer / operated by University of Cahfornia m___=_.____ _ __ _ . _ _

Lb:,

3..

LOS ALAMOS NATIONAL LABORATORY MONTHLY REPORT Project

Title:

Technical Assistance to Region IV (Fort St. Vrain)

FIN NO.: A-7552 NRC 189 Proposal Date: January 11, 1985 Revision No.: _

NRC Project Manager E. H. Johnson, [

Reactor Project Branch 1 -

NRC Technical Monitors: R. E. Ireland, Special Projects and Engineering Section Los Alamos Principal Investigator S. W. Moore (FTS 843-2228)

Period of Performance: October 1, 1985 to =

September 30, 1986 _

Reporting Period: September, 1986 A. PROJECT STATUS SECTION

1. Summary of Effort and Progress Proiect 1: Review and Assessment of CRDM Refurbishment Placed on hold until more information and data are received.

Project 2: Technical Sunnort of Lona-Term Issues Placed on hold.

2. Problems and Delays Project 1: Review and Assessment of CRDM Refurbishment Placed on hold until more information and data are received.

Proiect 2: Technical Suonort of Lona-Term Issues Placed on hold.

r

(. .'.

3. Summary of Progress to-Date

.Proiect Percentaae of Comoletion 1 30 2 0

4. Plans for Next Reporting Period Project 1:

Meet or coordinate with NRC/PSC to establish information channel.

i Proiect 2:

Initiate subcontract and coordination when appropriate.

B. FINANCIAL STATUS SECTION

. 1. The total cost (value) of the FSV project as reflected in the proposal (NRC Form 189), the total amount of funds obligated to date, and the balance of funds required to complete the work by end of FY 86 are as follows:

Total Funds Balance of Funds

Projected Obligated Required to Complete Tasks l Proiect Cott To Date By End of FY 836

$ 65.0 K $ 65.0 K $ 0.0 K

2. The total direct staff use and amount of funds expended (costed) during the period and the total cumulative to date in the.following categories are:

Seotember 1986 Cumulative

a. Direct Staff Effort 0.0 0.2
b. Funds-($000) Seotember 1986 FY 86 Direct Salaries 0.0 K 11.6 K Material and Services (excluding ADP) 0.0 1.8 ADP Support 0.0 0.8 Subcontracts 0.0 0.0 Travel Expenses 0.0 0.0 Indirect Labor Costs 0.0 9.2 Other (specify) General Administrative TOTAL 0.0 K 23.4 K l

{

l

g. .

{..L- 3.

Total amount of funds expended during the period and cumulative to date for the FSV project is as follows-

_ Proiect September 1986 Cumulative Fort St. Vrain 0.0 K 23.4 K

4. Expenditure Summary Seotember 1986 Cumulative Proiect 1: Review and Assessment CRDM Refurbishment 0.0 23.4 P_toject 2: Technical Support on Long Term Issues 0.0 0.0 k