ML20210A385
ML20210A385 | |
Person / Time | |
---|---|
Site: | Fort Saint Vrain ![]() |
Issue date: | 04/13/1987 |
From: | Bohl R LOS ALAMOS NATIONAL LABORATORY |
To: | Johnson E NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
References | |
CON-FIN-A-7552 N-DO-NRC-87-2N, NUDOCS 8705050077 | |
Download: ML20210A385 (4) | |
Similar Documents at Fort Saint Vrain | |
---|---|
Category:CONTRACTED REPORT - RTA
MONTHYEARML20148D6041997-03-31031 March 1997
[Table view]Confirmatory Survey for Fsv Nuclear Station,Psc, Platteville,Co,Final Rept ML20148D5861997-03-26026 March 1997 Confirmatory Survey Plan for Group E Effluent Discharge Pathway Areas at Fsv Nuclear Station ML20134C8721997-01-29029 January 1997 Draft Confirmatory Survey for Fsv Nuclear Station Public Svc Co of Co,Platteville,Co ML20092G3681995-06-19019 June 1995 Confirmatory Survey for Repower Area Fsv Platteville,Co, Final Rept ML20084F3931995-05-16016 May 1995 Draft Rept, Confirmatory Survey for Repower Area Fsv Platteville,Co ML20245E6601989-01-0606 January 1989 Independent Review of Fire Protection Program Plan,Public Svc Co of Co,Fort St Vrain Nuclear Generating Station ML20245D1951988-10-31031 October 1988 Integrated Technical Evaluation Rept for Review of Fort St Vrain Tech Spec Upgrade Program ML20151B0031988-03-31031 March 1988 Technical Evaluation Rept for Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Informal Rept ML20151S6061988-02-29029 February 1988 Rev 1 to Technical Evaluation Rept for Conformance to NRR Generic Ltrs 83-36 & 83-37 by Fort St Vrain Nuclear Generating Station, Informal Rept ML20195G9611987-12-14014 December 1987 Technical Evaluation of Proposed Redundancy Requirements for Helium Circulation Tech Specs to Accommodate Rapid Depressurization Accident, Technical Evaluation Rept ML20234D6291987-12-14014 December 1987 Technical Assistance to Region IV (Fort St.Vrain), Monthly Business Ltr Rept for Oct 1987 ML20236V3191987-10-31031 October 1987 Draft Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept ML20235R4161987-10-31031 October 1987 Draft Eg&G Technical Evaluation Rept for Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station ML20235V8871987-10-31031 October 1987 Draft Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept ML20236C2611987-09-28028 September 1987 Fort St Vrain Safe Shutdown Using Condensate Sys ML20236U7221987-08-0606 August 1987 Addendum to Review of Proposed Tech Spec Change:Core Inlet Valves/Min Helium Flow & Max Core Region Temp Rise, Limiting Conditon for Operation 4.1.9, Technical Evaluation Rept ML20246J3191987-07-31031 July 1987 Evaluation of Operator Roles in Mitigating High Energy Line Break at Fort St Vrain Nuclear Generating Station ML20235R6121987-07-0101 July 1987 Investigating Causes & Consequences of Cracked Graphite Fuel Elements ML20235M8321987-06-30030 June 1987 Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components:Fort St Vrain, Final Informal Rept ML20215A9031987-06-0505 June 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Apr 1987 ML20235G1141987-06-0404 June 1987 Draft Fort St Vrain Safe Shutdown from 82% Power, Technical Evaluation Rept ML20234C6091987-06-0404 June 1987 Fort St Vrain Safe Shutdown from 82% Power, Technical Evaluation Rept ML20215L9331987-05-31031 May 1987 Evaluation of Integrated Sys Study of CRD Mechanism Rod Position Indication Instrumentation for Fort St Vrain Nuclear Generating Station, Informal Technical Evaluation Rept ML20214H2061987-05-15015 May 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Mar 1987 ML20215M3901987-04-30030 April 1987 Final Conformance to Generic Ltr 83-28,Item 2.2.2 - Vendor Interface Programs for All Other Safety-Related Components: Fort St Vrain, Informal Rept ML20210A3851987-04-13013 April 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Feb 1987 ML20214R8711987-03-31031 March 1987 Technical Evaluation Rept Evaluation of Bldg 10 Electrical Mods Fort St Vrain Nuclear Generating Station, Informal Rept ML20214Q5411987-03-31031 March 1987 Evaluation of Confinement Environ Temp Following High Energy Line Breaks Proposed for Fort St Vrain Environ Qualification Program, Informal Technical Evaluation Rept ML20207T3721987-03-10010 March 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Jan 1987 ML20207R9471987-03-0606 March 1987 Rev 1 to Review of Fort St Vrain Onsite AC `Standby' Power Sys Re Compliance to Single Failure Criterion & Ser ML20212F6771987-02-13013 February 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Dec 1986 ML20216J1991987-02-0404 February 1987 Evaluation of Long-Term Effects of Moisture Ingress in Fort St Vrain Nuclear Reactor ML20210P6451987-01-31031 January 1987 Draft Evaluation of Confinement Environ Temps Following High Energy Line Breaks Proposed for Fort St Vrain Environ Qualification Program, Technical Evaluation Rept ML20245B3401986-12-31031 December 1986 Technical Assistance for Fort St Vrain Task Ii:Pcrv & Pcrv Tendon Evaluation, Final Technical Evaluation Rept ML20207K4701986-12-31031 December 1986 Final Review of Convection Heat Transfer Coefficients Utilized in Fort St Vrain Main Steam Line Break Analysis, Technical Evaluation Rept ML20212B7321986-11-30030 November 1986 Evaluation of Proposed CRD & Orifice Assembly 300 F Temp Limits,Fort St Vrain Nuclear Generating Station ML20197C5981986-10-31031 October 1986 Review of Convection Heat Transfer Coefficients Utilized in Fort St Vrain Main Steam Line Break Analyses, Technical Evaluation Rept ML20213D8251986-10-31031 October 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Sept 1986 ML20214W4521986-10-16016 October 1986 Review of Proposed Tech Spec Change:Core Inlet Orifice Valves/Min Helium Flow & Max Core Region Temp Rise, Technical Evaluation Rept ML20214P4681986-09-30030 September 1986 Conformance to NRR Generic Ltrs 83-36 & 83-37 by Fort St Vrain Nuclear Generating Station, Informal Rept ML20211A6091986-09-26026 September 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Aug 1986 ML20236D3811986-09-24024 September 1986 Technical Evaluation of Dcrdr Info Supplementing Summary Rept for Fort St Vrain Nuclear Generating Station ML20209F1021986-09-0505 September 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr for Jul 1986 ML20212Q1011986-08-31031 August 1986 Conformance to Reg Guide 1.97,Fort St Vrain Nuclear Generating Station, Informal Rept ML20213G5811986-08-0707 August 1986 Draft Review of Fort St Vrain Onsite AC 'Standby' Power Sys W/Regards to Compliance to Single Failure Criterion & Ser ML20205E3711986-07-31031 July 1986 Conformance to Generic Ltr 83-28,Item 2.1 (Part 1), Equipment Classification (Reactor Trip Sys Components) Fort Calhoun,Millstone Unit 2,Nine Mile Point 2 & Fort St Vrain, Technical Evaluation Rept ML20244E1901986-07-31031 July 1986 Conformance to Generic Ltr 83-28,Item 2.1 (Part 1) Equipment Classification (Reactor Trip Sys Components), Fort Calhoun,Millstone Unit 2,Nine Mile Point Unit 2 & Fort St Vrain ML20204E6811986-07-24024 July 1986 Technical Assistance to Region IV - Fort St Vrain, Monthly Business Ltr Repts for May & June 1986 ML20207J7931986-07-0909 July 1986 Fort St Vrain Fuel Element Dynamic Response ML20236D3741986-06-20020 June 1986 Technical Evaluation of Dcrdr Info Supplementing Summary Rept for Fort St Vrain Nuclear Generating Station 1997-03-31 Category:QUICK LOOK MONTHYEARML20148D6041997-03-31031 March 1997
[Table view]Confirmatory Survey for Fsv Nuclear Station,Psc, Platteville,Co,Final Rept ML20148D5861997-03-26026 March 1997 Confirmatory Survey Plan for Group E Effluent Discharge Pathway Areas at Fsv Nuclear Station ML20134C8721997-01-29029 January 1997 Draft Confirmatory Survey for Fsv Nuclear Station Public Svc Co of Co,Platteville,Co ML20092G3681995-06-19019 June 1995 Confirmatory Survey for Repower Area Fsv Platteville,Co, Final Rept ML20084F3931995-05-16016 May 1995 Draft Rept, Confirmatory Survey for Repower Area Fsv Platteville,Co ML20245E6601989-01-0606 January 1989 Independent Review of Fire Protection Program Plan,Public Svc Co of Co,Fort St Vrain Nuclear Generating Station ML20245D1951988-10-31031 October 1988 Integrated Technical Evaluation Rept for Review of Fort St Vrain Tech Spec Upgrade Program ML20151B0031988-03-31031 March 1988 Technical Evaluation Rept for Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Informal Rept ML20151S6061988-02-29029 February 1988 Rev 1 to Technical Evaluation Rept for Conformance to NRR Generic Ltrs 83-36 & 83-37 by Fort St Vrain Nuclear Generating Station, Informal Rept ML20195G9611987-12-14014 December 1987 Technical Evaluation of Proposed Redundancy Requirements for Helium Circulation Tech Specs to Accommodate Rapid Depressurization Accident, Technical Evaluation Rept ML20234D6291987-12-14014 December 1987 Technical Assistance to Region IV (Fort St.Vrain), Monthly Business Ltr Rept for Oct 1987 ML20236V3191987-10-31031 October 1987 Draft Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept ML20235R4161987-10-31031 October 1987 Draft Eg&G Technical Evaluation Rept for Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station ML20235V8871987-10-31031 October 1987 Draft Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept ML20236C2611987-09-28028 September 1987 Fort St Vrain Safe Shutdown Using Condensate Sys ML20236U7221987-08-0606 August 1987 Addendum to Review of Proposed Tech Spec Change:Core Inlet Valves/Min Helium Flow & Max Core Region Temp Rise, Limiting Conditon for Operation 4.1.9, Technical Evaluation Rept ML20246J3191987-07-31031 July 1987 Evaluation of Operator Roles in Mitigating High Energy Line Break at Fort St Vrain Nuclear Generating Station ML20235R6121987-07-0101 July 1987 Investigating Causes & Consequences of Cracked Graphite Fuel Elements ML20235M8321987-06-30030 June 1987 Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components:Fort St Vrain, Final Informal Rept ML20215A9031987-06-0505 June 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Apr 1987 ML20235G1141987-06-0404 June 1987 Draft Fort St Vrain Safe Shutdown from 82% Power, Technical Evaluation Rept ML20234C6091987-06-0404 June 1987 Fort St Vrain Safe Shutdown from 82% Power, Technical Evaluation Rept ML20215L9331987-05-31031 May 1987 Evaluation of Integrated Sys Study of CRD Mechanism Rod Position Indication Instrumentation for Fort St Vrain Nuclear Generating Station, Informal Technical Evaluation Rept ML20214H2061987-05-15015 May 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Mar 1987 ML20215M3901987-04-30030 April 1987 Final Conformance to Generic Ltr 83-28,Item 2.2.2 - Vendor Interface Programs for All Other Safety-Related Components: Fort St Vrain, Informal Rept ML20210A3851987-04-13013 April 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Feb 1987 ML20214R8711987-03-31031 March 1987 Technical Evaluation Rept Evaluation of Bldg 10 Electrical Mods Fort St Vrain Nuclear Generating Station, Informal Rept ML20214Q5411987-03-31031 March 1987 Evaluation of Confinement Environ Temp Following High Energy Line Breaks Proposed for Fort St Vrain Environ Qualification Program, Informal Technical Evaluation Rept ML20207T3721987-03-10010 March 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Jan 1987 ML20207R9471987-03-0606 March 1987 Rev 1 to Review of Fort St Vrain Onsite AC `Standby' Power Sys Re Compliance to Single Failure Criterion & Ser ML20212F6771987-02-13013 February 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Dec 1986 ML20216J1991987-02-0404 February 1987 Evaluation of Long-Term Effects of Moisture Ingress in Fort St Vrain Nuclear Reactor ML20210P6451987-01-31031 January 1987 Draft Evaluation of Confinement Environ Temps Following High Energy Line Breaks Proposed for Fort St Vrain Environ Qualification Program, Technical Evaluation Rept ML20245B3401986-12-31031 December 1986 Technical Assistance for Fort St Vrain Task Ii:Pcrv & Pcrv Tendon Evaluation, Final Technical Evaluation Rept ML20207K4701986-12-31031 December 1986 Final Review of Convection Heat Transfer Coefficients Utilized in Fort St Vrain Main Steam Line Break Analysis, Technical Evaluation Rept ML20212B7321986-11-30030 November 1986 Evaluation of Proposed CRD & Orifice Assembly 300 F Temp Limits,Fort St Vrain Nuclear Generating Station ML20197C5981986-10-31031 October 1986 Review of Convection Heat Transfer Coefficients Utilized in Fort St Vrain Main Steam Line Break Analyses, Technical Evaluation Rept ML20213D8251986-10-31031 October 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Sept 1986 ML20214W4521986-10-16016 October 1986 Review of Proposed Tech Spec Change:Core Inlet Orifice Valves/Min Helium Flow & Max Core Region Temp Rise, Technical Evaluation Rept ML20214P4681986-09-30030 September 1986 Conformance to NRR Generic Ltrs 83-36 & 83-37 by Fort St Vrain Nuclear Generating Station, Informal Rept ML20211A6091986-09-26026 September 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Aug 1986 ML20236D3811986-09-24024 September 1986 Technical Evaluation of Dcrdr Info Supplementing Summary Rept for Fort St Vrain Nuclear Generating Station ML20209F1021986-09-0505 September 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr for Jul 1986 ML20212Q1011986-08-31031 August 1986 Conformance to Reg Guide 1.97,Fort St Vrain Nuclear Generating Station, Informal Rept ML20213G5811986-08-0707 August 1986 Draft Review of Fort St Vrain Onsite AC 'Standby' Power Sys W/Regards to Compliance to Single Failure Criterion & Ser ML20205E3711986-07-31031 July 1986 Conformance to Generic Ltr 83-28,Item 2.1 (Part 1), Equipment Classification (Reactor Trip Sys Components) Fort Calhoun,Millstone Unit 2,Nine Mile Point 2 & Fort St Vrain, Technical Evaluation Rept ML20244E1901986-07-31031 July 1986 Conformance to Generic Ltr 83-28,Item 2.1 (Part 1) Equipment Classification (Reactor Trip Sys Components), Fort Calhoun,Millstone Unit 2,Nine Mile Point Unit 2 & Fort St Vrain ML20204E6811986-07-24024 July 1986 Technical Assistance to Region IV - Fort St Vrain, Monthly Business Ltr Repts for May & June 1986 ML20207J7931986-07-0909 July 1986 Fort St Vrain Fuel Element Dynamic Response ML20236D3741986-06-20020 June 1986 Technical Evaluation of Dcrdr Info Supplementing Summary Rept for Fort St Vrain Nuclear Generating Station 1997-03-31 Category:ETC. (PERIODIC MONTHYEARML20148D6041997-03-31031 March 1997
[Table view]Confirmatory Survey for Fsv Nuclear Station,Psc, Platteville,Co,Final Rept ML20148D5861997-03-26026 March 1997 Confirmatory Survey Plan for Group E Effluent Discharge Pathway Areas at Fsv Nuclear Station ML20134C8721997-01-29029 January 1997 Draft Confirmatory Survey for Fsv Nuclear Station Public Svc Co of Co,Platteville,Co ML20092G3681995-06-19019 June 1995 Confirmatory Survey for Repower Area Fsv Platteville,Co, Final Rept ML20084F3931995-05-16016 May 1995 Draft Rept, Confirmatory Survey for Repower Area Fsv Platteville,Co ML20245E6601989-01-0606 January 1989 Independent Review of Fire Protection Program Plan,Public Svc Co of Co,Fort St Vrain Nuclear Generating Station ML20245D1951988-10-31031 October 1988 Integrated Technical Evaluation Rept for Review of Fort St Vrain Tech Spec Upgrade Program ML20151B0031988-03-31031 March 1988 Technical Evaluation Rept for Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Informal Rept ML20151S6061988-02-29029 February 1988 Rev 1 to Technical Evaluation Rept for Conformance to NRR Generic Ltrs 83-36 & 83-37 by Fort St Vrain Nuclear Generating Station, Informal Rept ML20195G9611987-12-14014 December 1987 Technical Evaluation of Proposed Redundancy Requirements for Helium Circulation Tech Specs to Accommodate Rapid Depressurization Accident, Technical Evaluation Rept ML20234D6291987-12-14014 December 1987 Technical Assistance to Region IV (Fort St.Vrain), Monthly Business Ltr Rept for Oct 1987 ML20236V3191987-10-31031 October 1987 Draft Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept ML20235R4161987-10-31031 October 1987 Draft Eg&G Technical Evaluation Rept for Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station ML20235V8871987-10-31031 October 1987 Draft Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept ML20236C2611987-09-28028 September 1987 Fort St Vrain Safe Shutdown Using Condensate Sys ML20236U7221987-08-0606 August 1987 Addendum to Review of Proposed Tech Spec Change:Core Inlet Valves/Min Helium Flow & Max Core Region Temp Rise, Limiting Conditon for Operation 4.1.9, Technical Evaluation Rept ML20246J3191987-07-31031 July 1987 Evaluation of Operator Roles in Mitigating High Energy Line Break at Fort St Vrain Nuclear Generating Station ML20235R6121987-07-0101 July 1987 Investigating Causes & Consequences of Cracked Graphite Fuel Elements ML20235M8321987-06-30030 June 1987 Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components:Fort St Vrain, Final Informal Rept ML20215A9031987-06-0505 June 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Apr 1987 ML20235G1141987-06-0404 June 1987 Draft Fort St Vrain Safe Shutdown from 82% Power, Technical Evaluation Rept ML20234C6091987-06-0404 June 1987 Fort St Vrain Safe Shutdown from 82% Power, Technical Evaluation Rept ML20215L9331987-05-31031 May 1987 Evaluation of Integrated Sys Study of CRD Mechanism Rod Position Indication Instrumentation for Fort St Vrain Nuclear Generating Station, Informal Technical Evaluation Rept ML20214H2061987-05-15015 May 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Mar 1987 ML20215M3901987-04-30030 April 1987 Final Conformance to Generic Ltr 83-28,Item 2.2.2 - Vendor Interface Programs for All Other Safety-Related Components: Fort St Vrain, Informal Rept ML20210A3851987-04-13013 April 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Feb 1987 ML20214R8711987-03-31031 March 1987 Technical Evaluation Rept Evaluation of Bldg 10 Electrical Mods Fort St Vrain Nuclear Generating Station, Informal Rept ML20214Q5411987-03-31031 March 1987 Evaluation of Confinement Environ Temp Following High Energy Line Breaks Proposed for Fort St Vrain Environ Qualification Program, Informal Technical Evaluation Rept ML20207T3721987-03-10010 March 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Jan 1987 ML20207R9471987-03-0606 March 1987 Rev 1 to Review of Fort St Vrain Onsite AC `Standby' Power Sys Re Compliance to Single Failure Criterion & Ser ML20212F6771987-02-13013 February 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Dec 1986 ML20216J1991987-02-0404 February 1987 Evaluation of Long-Term Effects of Moisture Ingress in Fort St Vrain Nuclear Reactor ML20210P6451987-01-31031 January 1987 Draft Evaluation of Confinement Environ Temps Following High Energy Line Breaks Proposed for Fort St Vrain Environ Qualification Program, Technical Evaluation Rept ML20245B3401986-12-31031 December 1986 Technical Assistance for Fort St Vrain Task Ii:Pcrv & Pcrv Tendon Evaluation, Final Technical Evaluation Rept ML20207K4701986-12-31031 December 1986 Final Review of Convection Heat Transfer Coefficients Utilized in Fort St Vrain Main Steam Line Break Analysis, Technical Evaluation Rept ML20212B7321986-11-30030 November 1986 Evaluation of Proposed CRD & Orifice Assembly 300 F Temp Limits,Fort St Vrain Nuclear Generating Station ML20197C5981986-10-31031 October 1986 Review of Convection Heat Transfer Coefficients Utilized in Fort St Vrain Main Steam Line Break Analyses, Technical Evaluation Rept ML20213D8251986-10-31031 October 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Sept 1986 ML20214W4521986-10-16016 October 1986 Review of Proposed Tech Spec Change:Core Inlet Orifice Valves/Min Helium Flow & Max Core Region Temp Rise, Technical Evaluation Rept ML20214P4681986-09-30030 September 1986 Conformance to NRR Generic Ltrs 83-36 & 83-37 by Fort St Vrain Nuclear Generating Station, Informal Rept ML20211A6091986-09-26026 September 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Aug 1986 ML20236D3811986-09-24024 September 1986 Technical Evaluation of Dcrdr Info Supplementing Summary Rept for Fort St Vrain Nuclear Generating Station ML20209F1021986-09-0505 September 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr for Jul 1986 ML20212Q1011986-08-31031 August 1986 Conformance to Reg Guide 1.97,Fort St Vrain Nuclear Generating Station, Informal Rept ML20213G5811986-08-0707 August 1986 Draft Review of Fort St Vrain Onsite AC 'Standby' Power Sys W/Regards to Compliance to Single Failure Criterion & Ser ML20205E3711986-07-31031 July 1986 Conformance to Generic Ltr 83-28,Item 2.1 (Part 1), Equipment Classification (Reactor Trip Sys Components) Fort Calhoun,Millstone Unit 2,Nine Mile Point 2 & Fort St Vrain, Technical Evaluation Rept ML20244E1901986-07-31031 July 1986 Conformance to Generic Ltr 83-28,Item 2.1 (Part 1) Equipment Classification (Reactor Trip Sys Components), Fort Calhoun,Millstone Unit 2,Nine Mile Point Unit 2 & Fort St Vrain ML20204E6811986-07-24024 July 1986 Technical Assistance to Region IV - Fort St Vrain, Monthly Business Ltr Repts for May & June 1986 ML20207J7931986-07-0909 July 1986 Fort St Vrain Fuel Element Dynamic Response ML20236D3741986-06-20020 June 1986 Technical Evaluation of Dcrdr Info Supplementing Summary Rept for Fort St Vrain Nuclear Generating Station 1997-03-31 Category:INCOMING CORRESPONDENCE MONTHYEARML20205G8771999-03-26026 March 1999
[Table view]Forwards Copy of Cover Page from Fort St-Vrain Welding Manual,Which Had Been Listed as Encl on Page 4 of 990325 Reply to EA 98-081.Cover Page Had Been Inadvertently Left Out with Original Reply ML20197H8811998-12-0101 December 1998 Forwards Proposed Change to Fsv ISFSI Physical Protection Plan in Which Commitment Is Made to Provide Feature to Security Posture for Facility ML20198K1931997-10-10010 October 1997 Provides Supplemental Info in Support of Util Proposed Rev to Physical Security Plan for Plant Plant Isfsi.Plan Withheld,Per 10CFR2.790(d) & 10CFR73.21 ML20141F3521997-05-14014 May 1997 Forwards Proposed Issue 4 of Physical Security Plan for Fort St Vrain ISFSI for Review & Approval.Encl Withheld,Per 10CFR2.790(d) ML20138G2701997-04-28028 April 1997 Provides Response to NRC Comments Re Proposed Sampling & Survey Plan for Fsv Effluent Pathway.Response Documents Fsv Liquid Effluent Discharge Pathway Areas Are Acceptable for Release for Unrestricted Use IAW Draft NUREG/CR-5849 ML20148D4651997-04-24024 April 1997 Forwards Revised Interim Ltr Rept Which Describes Procedures & Results of Confirmatory Survey of Group E Effluent Discharge Pathway Areas at Fsv Station ML20138B0511997-04-22022 April 1997 Forwards Copy of Proposed Amend to Fsv NPDES Permit, Wastewater Discharge Permit CO-0001121 Requested to Support Repowering Activities,Iaw Section 3.2.d of Fsv Non-Radiological Ts,App B to License DPR-34 ML20140E1061997-04-10010 April 1997 Forwards Confirmatory Survey of Group Effluent Discharge Pathway Areas for Fsv Nuclear Station,Platteville,Co ML20137S4481997-04-0808 April 1997 Informs That Decommissioning Activities at Fsv Are Complete & NRC Issued Exemption from Requirements of 10CFR50.54(w) in .Property Damage Insurance Policy Is Maintaned to Protect Fsv balance-of-plant Assets ML20137S5421997-04-0707 April 1997 Forwards Final Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments Affecting Decommissioning of Fort St Vrain Nuclear Station ML20148D5951997-04-0404 April 1997 Forwards Confirmatory Survey for Fsv Nuclear Station, Psc,Platteville,Co, Final Rept ML20148D5811997-03-26026 March 1997 Forwards Confirmatory Survey Plan for Group E Effluent Discharge Pathway Areas at Fsv Nuclear Station, Covered in Final Survey Rept,Vol 6 ML20137G7361997-03-25025 March 1997 Requests Addl Time for Util to Respond to NRC Comments in Re Financial Assurance Mechanism for Fort St Vrain Decommissioning Costs ML20137G9521997-03-24024 March 1997 Forwards Quarterly 10CFR50.59 Rept for Period 961201-970228 Re Changes,Tests & Experiments for Fort St Vrain Decommissioning ML20137C0061997-03-18018 March 1997 Documents That There Have Been No Activities Involving Release of Radioactive Matls from Fsv Nuclear Station That Potentially Could Have Affected Environ,Subsequent to Previous Radiological Envion Operating Rept ML20137C0181997-03-18018 March 1997 Documents That No Personnel Has Received Radiation Exposure at Fsv in 1997 or at Any Time Subsequent to ML20136G1201997-03-11011 March 1997 Forwards Annual Radioactive Effluent Release Rept for Jan- Dec 1996 & Jan-Mar 1997. All Effluent Releases Completed as of 960703.Repts on Activities After 960703 Reflect Disposal of Solid Waste ML20135D7891997-02-27027 February 1997 Forwards Responses to Comments Re Fort St Vrain Final Survey Rept ML20135D9531997-02-27027 February 1997 Forwards Copy of Amend to Util Npdes,Wastewater Discharge Permit CO-0001121,which Clarifies That Monitoring of Farm Pond Outlet Required When Industrial Wastewater Being Discharged Through Upstream Goosequill Ditch ML20134D1551997-01-31031 January 1997 Forwards Util Responses to NRC Comments Provided in NRC Ltr Re Sampling & Survey Plan Used for Final Radiological Survey of Liquid Effluent Pathway at Ft St Vrain ML20134C8481997-01-30030 January 1997 Forwards Draft Confirmatory Survey Rept for Fsv Nuclear Station,Psc,Platteville,Co Providing Info on Essap Activities on 960930-1003 ML20133E0481997-01-0202 January 1997 Forwards Comments to Fsv Nuclear Station, Decommissioning Project Final Survey Rept (Volumes 4-11), for Consideration ML20132F2841996-12-19019 December 1996 Forwards Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments Affecting Decommissioning of Plant,Covering Period of 960901-1130 ML20133A8591996-12-16016 December 1996 Forwards Original & Copy Transcripts of Public Hearing,Held on 961203 in Platteville,Co Re Decommissioning & License Termination of Util Ft Saint Vrain Nuclear Generating Station ML20133N0011996-12-0404 December 1996 Recommends That NRC Require License to Modify Submission of Unexecuted Draft Trust Agreement Remaining Decommissioning Costs for Ft St Vrain Nuclear Generating Station in Listed Ways ML20135A5861996-11-25025 November 1996 Submits Suppl Info Re Annual Environ Rept for 1995 Operation of Fsv ISFSI ML20135A6361996-11-20020 November 1996 Submits Copy of Describing Discharge Practices for Groundwater Seeping Into Fsv'S Reactor Building Sump ML20134L4721996-11-14014 November 1996 Notifies NRC That Util Adopted Fsv ISFSI Emergency Response Plan to Direct Emergency Response for Radiological Accidents Occuring at Site,Until 10CFR50 License Is Terminated ML20134F4351996-10-30030 October 1996 Forwards Sections 1,2,6 & 8 from Survey Packages F0015, F0039 & F0126 & Sections 1,2 & 6 from Survey Package F0115 to Support on-site NRC Insp ML20134G5991996-10-30030 October 1996 Forwards Volumes 1-12 to Final Survey Rept for Groups A,B,C Rev 1,D Rev 1,E,F Rev 1 & G-J for NRC Approval in Support of Forthcoming Request for Termination of Fsv 10CFR50 License ML20133D7691996-10-22022 October 1996 Forwards Preliminary Rept Re Orise Support of NRC License Insp at Fsv on 960930-1003 ML20136B1411996-10-15015 October 1996 FOIA Request for Documents Re NOV Addressed to Scientific Ecology Group Re NRC Insp Rept 50-267/94-03 & OI Investigation Repts 4-94-010 & 4-95-015 ML20128M6181996-10-0404 October 1996 Forwards Ltr from PSC to Co Dept of Public Health & Environ Describing Monitoring Practices at Plant ML20128G8041996-10-0101 October 1996 Forwards Fsv Decommissioning Fire Protection Plan Update ML20128G0481996-09-30030 September 1996 Submits Rev to Psco Definitions of Contents of Documentation Packages Re Fsv Final Survey Project ML20129C0421996-09-20020 September 1996 Forwards Quarterly Submittal of 10CFR50.59 Rept of Changes, Tests & Experiments for Facility Decommissioning,Covering Period of 960601-0831 ML20133D7601996-09-16016 September 1996 Forwards Confirmatory Survey Plan for Fsv Nuclear Station Decommissioning Project,First Final Survey Rept Submittal- Vols 1-5.NRC Comments Incorporated.Spending Plan Attached ML20117P0711996-09-13013 September 1996 Describes Util Plans to Remove Bldg 28 from Plant Facility ML20129A4431996-09-11011 September 1996 Describes Util Plans for Demonstrating That Liquid Effluent Pathway & Surrounding Open Land Areas Satisfy 10 Mrem/Yr Criteria Provided in Plant Final Survey Plan ML20117K5291996-09-0404 September 1996 Provides Notification That Util Will Be Revising Financial Assurance Mechanism That Will Be Used to Cover Remaining Costs of Decommissioning Plant ML20117C7281996-08-22022 August 1996 Discusses Impact of Final Decommissioning Rule & Requests NRC Concurrence That Requirements to Submit & Obtain Approval of License Termination Plan Have Been Satisfied ML20116P3431996-08-16016 August 1996 Describes Actions to Remove Structures & Equipment Items from Fort St Vrain Facility for NRC Info.Requests That NRC Advise Util of Wishes to Perform Confirmatory Survey of Any Parts of New Fuel Storage Building Before 960903 ML20133D7551996-08-14014 August 1996 Provides Environ Survey & Site Assessment Program'S (Essap) Comments Re Review of Fsv Nuclear Station Decommissioning Project Final Survey Rept ML20116M0771996-08-14014 August 1996 Provides Suppl Response to Re Insp Rept 50-267/96-01 in Jan 1996 Re NRC Concerns About Fsv Final Survey Program.Specifically,Bias in Instrumentation Response Overestimating Amount of Contamination Present ML20116M1841996-08-13013 August 1996 Forwards Util Responses to NRC Comments in Re Use of in-situ Gamma Spectroscopy to Measure Exposure Rates During Plant Final Survey.Approval to Use in-situ Gamma Spectroscopic instrument,Microspec-2,requested ML20116K0061996-08-0909 August 1996 Submits Fort St Vrain Nuclear Station Decommissioning Project Final Survey Rept ML20116M1241996-08-0808 August 1996 Responds to NRC Bulletin 96-004, Chemical,Galvanic,Or Other Reactions in Spent Fuel Storage & Transportation. Informs That Modular Vault Dry Storage Sys Is Not Susceptible to Problems Addressed in Bulletin ML20116F3611996-08-0202 August 1996 Submits Revised Documentation for Fort St Vrain Final Survey Program ML20116F8141996-08-0202 August 1996 Informs of Util Intent to Modify Fort St Vrain Control Room,Which Will Make Certain Final Survey Locations Unavailable for Further Review.Final Survey Efforts Are Complete ML20116A4511996-07-19019 July 1996 Requests NRC Approval of Proposed Method to Fsv Final Survey Plan to Determine Exposure Rates in Prestressed Concrete Reactor Vessel 1999-03-26 Category:TEXT-PROCUREMENT & CONTRACTS MONTHYEARML20148D6041997-03-31031 March 1997
[Table view]Confirmatory Survey for Fsv Nuclear Station,Psc, Platteville,Co,Final Rept ML20148D5861997-03-26026 March 1997 Confirmatory Survey Plan for Group E Effluent Discharge Pathway Areas at Fsv Nuclear Station ML20134C8721997-01-29029 January 1997 Draft Confirmatory Survey for Fsv Nuclear Station Public Svc Co of Co,Platteville,Co ML20092G3681995-06-19019 June 1995 Confirmatory Survey for Repower Area Fsv Platteville,Co, Final Rept ML20084F3931995-05-16016 May 1995 Draft Rept, Confirmatory Survey for Repower Area Fsv Platteville,Co ML20245E6601989-01-0606 January 1989 Independent Review of Fire Protection Program Plan,Public Svc Co of Co,Fort St Vrain Nuclear Generating Station ML20245D1951988-10-31031 October 1988 Integrated Technical Evaluation Rept for Review of Fort St Vrain Tech Spec Upgrade Program ML20154S3461988-08-31031 August 1988 Notification of Contract Execution,Mod 3,to HTGR (Fort St Vrain) Training Course. Contractor:Ga Co ML20154S3511988-08-31031 August 1988 Mod 3,incorporating Change of Name Agreement from Ga Technologies to General Atomics,To HTGR (Fort St Vrain) Training Course ML20151B0031988-03-31031 March 1988 Technical Evaluation Rept for Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Informal Rept ML20151S6061988-02-29029 February 1988 Rev 1 to Technical Evaluation Rept for Conformance to NRR Generic Ltrs 83-36 & 83-37 by Fort St Vrain Nuclear Generating Station, Informal Rept ML20195G9611987-12-14014 December 1987 Technical Evaluation of Proposed Redundancy Requirements for Helium Circulation Tech Specs to Accommodate Rapid Depressurization Accident, Technical Evaluation Rept ML20234D6291987-12-14014 December 1987 Technical Assistance to Region IV (Fort St.Vrain), Monthly Business Ltr Rept for Oct 1987 ML20235R4161987-10-31031 October 1987 Draft Eg&G Technical Evaluation Rept for Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station ML20235V8871987-10-31031 October 1987 Draft Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept ML20236V3191987-10-31031 October 1987 Draft Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept ML20236C2611987-09-28028 September 1987 Fort St Vrain Safe Shutdown Using Condensate Sys ML20236U7221987-08-0606 August 1987 Addendum to Review of Proposed Tech Spec Change:Core Inlet Valves/Min Helium Flow & Max Core Region Temp Rise, Limiting Conditon for Operation 4.1.9, Technical Evaluation Rept ML20246J3191987-07-31031 July 1987 Evaluation of Operator Roles in Mitigating High Energy Line Break at Fort St Vrain Nuclear Generating Station ML20235R6121987-07-0101 July 1987 Investigating Causes & Consequences of Cracked Graphite Fuel Elements ML20235M8321987-06-30030 June 1987 Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components:Fort St Vrain, Final Informal Rept ML20215A9031987-06-0505 June 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Apr 1987 ML20235G1141987-06-0404 June 1987 Draft Fort St Vrain Safe Shutdown from 82% Power, Technical Evaluation Rept ML20234C6091987-06-0404 June 1987 Fort St Vrain Safe Shutdown from 82% Power, Technical Evaluation Rept ML20215L9331987-05-31031 May 1987 Evaluation of Integrated Sys Study of CRD Mechanism Rod Position Indication Instrumentation for Fort St Vrain Nuclear Generating Station, Informal Technical Evaluation Rept ML20214H2061987-05-15015 May 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Mar 1987 ML20215M3901987-04-30030 April 1987 Final Conformance to Generic Ltr 83-28,Item 2.2.2 - Vendor Interface Programs for All Other Safety-Related Components: Fort St Vrain, Informal Rept ML20210A3851987-04-13013 April 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Feb 1987 ML20206H7461987-04-0808 April 1987 Notification of Contract Execution,Mod 1,to HTGR (Fort St Vrain) Training Course. Contractor:Ga Technologies ML20206H7621987-04-0808 April 1987 Mod 1,reflecting Administrative Changes Due to NRC Reorganization,To HTGR (Fort St Vrain) Training Course ML20214R8711987-03-31031 March 1987 Technical Evaluation Rept Evaluation of Bldg 10 Electrical Mods Fort St Vrain Nuclear Generating Station, Informal Rept ML20214Q5411987-03-31031 March 1987 Evaluation of Confinement Environ Temp Following High Energy Line Breaks Proposed for Fort St Vrain Environ Qualification Program, Informal Technical Evaluation Rept ML20207T3721987-03-10010 March 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Jan 1987 ML20207R9471987-03-0606 March 1987 Rev 1 to Review of Fort St Vrain Onsite AC `Standby' Power Sys Re Compliance to Single Failure Criterion & Ser ML20212F6771987-02-13013 February 1987 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Dec 1986 ML20216J1991987-02-0404 February 1987 Evaluation of Long-Term Effects of Moisture Ingress in Fort St Vrain Nuclear Reactor ML20210P6451987-01-31031 January 1987 Draft Evaluation of Confinement Environ Temps Following High Energy Line Breaks Proposed for Fort St Vrain Environ Qualification Program, Technical Evaluation Rept ML20245B3401986-12-31031 December 1986 Technical Assistance for Fort St Vrain Task Ii:Pcrv & Pcrv Tendon Evaluation, Final Technical Evaluation Rept ML20207K4701986-12-31031 December 1986 Final Review of Convection Heat Transfer Coefficients Utilized in Fort St Vrain Main Steam Line Break Analysis, Technical Evaluation Rept ML20212B7321986-11-30030 November 1986 Evaluation of Proposed CRD & Orifice Assembly 300 F Temp Limits,Fort St Vrain Nuclear Generating Station ML20197C5981986-10-31031 October 1986 Review of Convection Heat Transfer Coefficients Utilized in Fort St Vrain Main Steam Line Break Analyses, Technical Evaluation Rept ML20213D8251986-10-31031 October 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Progress Rept for Sept 1986 ML20214W4521986-10-16016 October 1986 Review of Proposed Tech Spec Change:Core Inlet Orifice Valves/Min Helium Flow & Max Core Region Temp Rise, Technical Evaluation Rept ML20214P4681986-09-30030 September 1986 Conformance to NRR Generic Ltrs 83-36 & 83-37 by Fort St Vrain Nuclear Generating Station, Informal Rept ML20211A6091986-09-26026 September 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr Rept for Aug 1986 ML20236D3811986-09-24024 September 1986 Technical Evaluation of Dcrdr Info Supplementing Summary Rept for Fort St Vrain Nuclear Generating Station ML20209F1021986-09-0505 September 1986 Technical Assistance to Region IV (Fort St Vrain), Monthly Business Ltr for Jul 1986 ML20212Q1011986-08-31031 August 1986 Conformance to Reg Guide 1.97,Fort St Vrain Nuclear Generating Station, Informal Rept ML20213G5811986-08-0707 August 1986 Draft Review of Fort St Vrain Onsite AC 'Standby' Power Sys W/Regards to Compliance to Single Failure Criterion & Ser ML20205E3711986-07-31031 July 1986 Conformance to Generic Ltr 83-28,Item 2.1 (Part 1), Equipment Classification (Reactor Trip Sys Components) Fort Calhoun,Millstone Unit 2,Nine Mile Point 2 & Fort St Vrain, Technical Evaluation Rept 1997-03-31 |
Text
.
,} a g ggg oAre: April 13, 1987 IN REPLY REFER TO: N-D0/NRC-87-2N LosAlamos NationalLaboratory um stoP: K560 Los Alamos,New Mexico 87545 rettewoaa: (505) 667-2180 (FTS) 843-2180 rg : 7:,.... -
W&ss:- . ..
~
):)
1 l APR I 61987 Mr. E. H. Johnson u L im i Reactor Project Branch 1 _J US Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76011
Dear Mr. Johnson:
SUBJECT:
MONTHLY BUSINESS LETTER REPORT FOR REGION IV-FIN A7552 (TECHNICAL ASSISTANCE TO REGION IV-FORT ST. VRAIN)
Enclosed is the nonthly progress report for February 1987. The purpose of this report is to apprise you of any problems, delays, or scheduling constraints that we currently have or anticipate, in addition to keeping you informed about the progress and costs.
Please do not hesitate to call if you have any questions or requests regarding these reports.
Sincerely yours, s C.
p'CLgger-c Richard J. Bohl NRC Programs Coorinator abg Enc. Ietter Report ;
I cy: R. E. Ireland, Region IV D. M. Meyer, Region IV W. H. Foster, Region IV -
C. A. Anderson, MEE-13, MS J576 S. W. Moore, MEE-13, MS J576 CRM-4, MS A150 (2)
File c7 G705050077 870413 7 PDR ADOCK 05000267 I R PDR l I g.h] An Equal opportunrty Emptoyer/ operated by the University of Califorrue
c e LOS ALAMOS NATIONAL LA8 ORATORY MONTHLY REPORT
- Project
Title:
Technical Assistance to Region IV (Fort St. Vrain)
FIN NO.: A-7552 NRC 189 Proposal Date: January 11, 1985 Revision No.: NRC Project Manager E. H. Johnson, Reactor Project Branch 1 NRC Technical Monitors: R. E. Ireland, Special Projects and Engineering Section j Los Alamos Principal Investigator S. H. Moore (FTS 843-2228)
! Period of Performance: October 1, 1985 to
{ February 28, 1987 Reporting Period: February, 1987 l A. PROJECT STATUS SECTION
- 1. Summary of Effort and Progress Project 1: Review and Assessment of CRDM Refurbishment 1
i Placed on hold until more information and data are received. !
Project 2: Technical Sucoort of Lona-Term Issues Placed on hold.
- 2. Problems and Delays Project 1: Review and Assessment of CRDH Refurbishment Placed on hold until more information and data are received.
Project 2: Technical Suonort of Lona-Term Issues
- Placed on hold.
. 3. Summary of Progress to Date Project Percentaae of Comoletion 1 30 2 0
- 4. Plans for Next Reporting Period Project 1:
Meet or coordinate with NRC/PSC to establish information channel.
Proiect 2:
Initiate subcontract and coordination when appropriate.
! B. FINANCIAL STATUS SECTION
- 1. The total cost (value) of the FSV project as reflected in the proposal (NRC
! Form 189), the total amount of funds obligated to date, and the balance of funds required to complete the work by end of FY 86 are as follows:
Total Funds Balance of Funds Projected Obligated Required to Complete Tasks
- Proiect Cost To Date By End of FY 87 i
$ 65.0 K $ 65.0 K $ 0.0 K 1
- 2. The total direct staff use and amount of funds expended (costed) during the period and the total cumulative to date in the following categories are:
February 1987 Cumulative
- a. Direct Staff Effort 0.0 0.2
- b. Funds ($000) February 1987 FY 67*
Direct Salaries 0.0 K 11.6 K Material and Services (excluding ADP) 0.0 1.8 ,
ADP Support 0.0 0.8 '
Subcontracts 0.0 0.0 Travel Expenses 0.0 0.0 Indirect Labor Costs 0.0 9.2 Other (specify) General Administrative TOTAL 0.0 K 23.4 K
', 3. Total amount of funds expended during the period and cumulative to date for the FSV project is as follows:
Proiect February 1987 Cumulative Fort St. Vrain 0.0 K 23.4 K
- 4. Expenditure Summary February 1987 Cumulative Proiect 1: Review and Assessment CRDM Refurbishment 0.0 23.4 K Proiect 2: Technical Support on Long Term Issues 0.0 0.0 l
l l
I