Technical Assistance to Region IV (Fort St.Vrain), Monthly Business Ltr Rept for Oct 1987
ML20234D629
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 12/14/1987
From: Bohl R
LOS ALAMOS NATIONAL LABORATORY
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
CON-FIN-A-7552 N-DO-SNP-87-2N, NUDOCS 8801070114
Download: ML20234D629 (4)


Text

_ _ _ . _ _ _ _ _ _ _ _ __

4 #  %

6

~

IN REPLY. REFER T .

- ~

2 Los Alamos NationalLaboratory uutstop; K560 Los Alamos,New Mexico 87545 retersone (505) 667-2180 (FTS) 843-2180 Mr. E. H. Johnson mim22.gl Reactor Project Branch 1 a US Nuclear Regulatory Commission Region IV l 611 Ryan Plaza Drive, Suite 1000 l Arlington, TX 76011 l

l

Dear Mr. Johnson:

SUBJECT:

MONTHLY BUSINESS LETTER REPORT FOR REGION IV--FIN A7552 (TECHNICAL ASSISTANCE TO REGION IV--FORT ST. VRAIN)

Enclosed is the monthly progress report for October 1987. The purpose of this report is to apprise you of any problems, delays, or scheduling constraints that the Los Alamos National Laboratory currently hus or anticipates, in addition to keeping you informed about the progress and costs.

Please do not hesitate to call if you have any questions or requests regarding these reports.

Sincerely yourg,

'I

./ { / -

Richard J. Bohl NRC Programs Coorinator abg Enc. Letter Report cy: R. E. Ireland, Region IV D. M. Meyer, Region IV W. H. Foster, Region IV T. J. Hirons, N-DO, MS E561 C. A. Anderson, MEE-13, MS J576 S. W. Moore, MEE-13, MS J576 CRM-4, MS A150 (2)

File f

I)I b -

4 'lE 5I e HR' nase nasa 6

~ ~ ~ ~ ~ -

N R PMag

4 I LOS ALAMOS NATIONAL LABORATORY MONTHLY REPORT Project

Title:

Technical Assistance to Region IV (Fort St. Vrain)

FIN NO.: A-7552 NRC 189 Proposal Date: January 11, 1985 Revision No.: NRC Project Manager E. H. Johnson, Reactor Project Branch 1 l

NRC Technical Monitors: R. E. Ireland, Special Projects and Engineering Section Los Alamos Principal Investigator S. H. Moore (FTS 843-2228)

Period of Performance: October 1, 1985 to I i

October 31, 1987 l

Reporting Period: October, 1987 A. PROJECT STATUS SECTION

1. Summary of Effort and Progress Proiect 1: Review and Assessment of CRDM Refurbishment Placed on hold until more information and data are received.

Project 2: Technical Succort of Lona-Term Issues  !

Placed on hold.

2. Problems and Delays l l l Proiect 1: Review and Assessment of CRDM Refurbishment l

Placed on hold until more information and data are received.

Proiect 2: Technical Sucoort of Lona-Term Issues Placed on hold.

)

3. Summary of Progress to Date Proiect Percentaae of Comoletion 1 30 2 0 '!
4. Plans for Next Reporting Period Proiect 1:

Heet or coordinate with NRC/PSC to establish information channel.

Proiect 2:

Initiate subcontract and coordination when appropriate.

1 B. FINANCIAL STATUS SECTION

1. The total cost (value) of the FSV project as reflected in the proposal (NRC Form 189), the total amount of funds obligated to date, and the balance of 3 funds required to complete the work by end of FY 86 are as follows:

Total Funds Balance of Funds Projected Obligated Required to Complete Tasks q Project Cost To Date By End of FY 87

)

i

$ 65.0 K $ 65.0 K $ 0.0 K l l

1

2. The total direct staff use and amount of funds expended (costed) during the period and the total cumulative to date in the following categories are:

October 1987 Cumulative

a. Direct Staff. Effort 0.0 0.2
b. Funds ($000) October 1987 FY 87*

Direct Salaries 0.0 K 11.6 K Haterial and Services (excluding ADP) 0.0 1.8 ADP Support 0.0 0.8 Subcontracts 0.0 0.0 Travel Expenses 0.0 0.0 Indirect Labor Costs 0.0 9.2 Other (specify) General Administrative TOTAL 0.0 K 23.4 K j

3. Total amount of funds expended during the period and cumulative to date for the rSV project is as follows:

Proiect October 1987 Cumulative Fort St. Vrain 0.0 K 23.4 K

4. Expenditure Summary 1 1

October 1987 Cumulative )

Proiect 1: Review and Assessment CRDM Refurbishment 0.0 23.4 K Proiect 2: Technical Support on Long Term Issues 0.0 0.0 l l

i l

l l

1 l

l l