osADamos Los Alamos NationalLaboratory Los Alamos,New Mexico 87545 July 24, 1986 Q-DO/TR-86-88 Energy Division Mr. E. H. Johnson Reactor Project Branch 1 US Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76011
Dear Mr. Johnson:
1
SUBJECT:
MONTHLY BUSINESS LETTER REPORTS FOR REGION IV--FIN A7552 (TECHNICAL ASSISTANCE TO REGION IV--FORT ST. VRAIN) i Enclosed are the monthly progress reports for May-June 1986. The purpose of these reports is to apprise you of any problems, delays, or scheduling constraints that we currently have or anticipate, in j
addition to keeping you informed about the progress and costs.
j Please do not hesitate to call if you have any questions or requests regarding these reports.
j Sincerely your f
i John R.
Ireland Project Manager for Reactor Safety Programs i
j JRI:ke i
Enc.
Letter Reports cy:
R. E.
Ireland, Region IV D. M. Meyer, Region IV W. H. Poster, Region IV
[
C. A. Anderson, 0-13, MS J576 S. W. Moore, Q-13, MS J576 CRM-4, MS A150 (2) i 8608010206 860724:
l DR ADOCK 05000267
- PDR,
[f l
_.,e,-,_...m..,._,_.,....c.,,,,.
d l
1 t
LOS ALAMOS NATIONAL LABORATORY MONTHLY REPORT Project
Title:
Technical Assistance to Region IV (Fort St. Vrain)
FIN NO.:
A-7552 NRC 189 Proposal Date:
January 11, 1985 Revision No.: NRC Project Manager E. H. Johnson, Reactor Project Branch 1 NRC Technical Monitors:
R. E. Ireland, Special Projects and Engineering Section Los Alamos Principal Investigator S. W. Moore (FTS 843-2228)
Period of Performance:
October 1, 1985 to May 31, 1986 Reporting Period:
May, 1986 A.
PROJECT STATUS SECTION 1.
Summary of Effort and Progress Project 1: Review and Assessment of CRDM Refurbishment Placed on hold until more information and data are received.
Project 2: Technical Support of Lono-Term Issues Placed on hold.
2.
Problems and Delays Project 1:
Review and Assessment of CRDM Refurbishment Placed on hold until more information and data are received.
Project 2: Technical Support of Lono-Term Issues Placed on hold.
i l
c e
3.
Summary of Progress to Date Project Percentaae of Completion 1
30 2
0 4.
Plans for Next Reporting Period Project 1:
Meet or coordinate with NRC/PSC to establish information channel.
Project 2:
Initiate subcontract and coordination when appropriate.
B.
FINANCIAL STATUS SECTION 1.
The total cost (value) of the FSV project as reflected in the proposal (NRC Form 189), the total amount of funds obligated to date, and the balance of funds required to complete the work by end of FY 86 are as follows:
Total Funds Balance of Funds Projected Obligated Required to Complete Tasks Project Cost To Date By End of FY 86
$ 65.0 K
$ 65.0 K
$ 0.0 K 2.
The total direct staff use and amount of funds expended (costed) during the period and the total cumulative to date in the following categories are:
May 1986 Cumulative a.
Direct Staff Effort 0.0 0.2 b.
Funds ($000)
May 1986 FY 86 Direct Salaries 0.0 K 11.6 K Material and Services (excluding ADP) 0.0 1.8 ADP Support 0.0 0.8 Subcontracts 0.0 0.0 Travel Expenses 0.0 0.0 Indirect Labor Costs 0.0 9.2 Other (specify) General Administrative TOTAL 0.0 K 23.4 K C~
o 3.
Total amount of funds expended during the period and cumulative to date for the FSV project is as follows:
Project May 1986 Cumulative Fort St. Vrain 0.0 K 23.4 K 4.
Expenditure Sumnary May 1986 Cumulative Project 1: Review and Assessment CRDM Refurbishment 0.0 23.4 Project 2: Technical Support on Long Term Issues 0.0 0.0 l l
LOS ALAMOS NATIONAL LABORATORY MONTHLY REPORT Project
Title:
Technical Assistance to Region IV (Fort St. Vrain)-
FIN NO.:
A-7552 NRC 189 Proposal Date:
January 11, 1985 Revision No.: NRC Project Manager E. H. Johnson, Reactor Project Branch 1 NRC Technical Monitors:
R. E. Ireland, Special Projects and Engineering Section Los Alamos Principal Investigator S. W. Moore (FTS 843-2228)
Period of Performance:
October 1, 1985 to June 31, 1986 Reporting Period:
June, 1986 A.
PROJECT STATUS SECTION 1.
Sun. mary of Ef fort and Progress Project 1: Review and Assessment of CRDM Refurbishment Placed on hold until more information and data are received.
Project 2: Technical Support of Lona-Term Issues l
Placed on hold.
l 2.
Problems and Delays l
Project 1:
Review and Assessment of CROM Refurbishment Placed on hold until more information and data are received.
Project 2: Technical Support of Lona-Term Issues l
Placed on hold.
L
m 3.
Summary of Progress to Date Project Percentage of Completion 1
30 2
0 4.
Plans for Next Reporting Period Project 1:
Meet or coordinate with NRC/PSC to establish information channel.
Project 2:
Initiate subcontract and coordination when appropriate.
B.
FINANCIAL STATUS SECTION 1.
The total cost (value) of the FSV project as reflected in the proposal (NRC Form 189), the total amount of funds obligated to date, and the balance of funds required to complete the work by end of FY 86 are as follows:
Total Funds Balance of Funds Projected Obligated Required to Complete Tasks Project Cost To Date By End of FY 86
$ 65.0 K
$ 65.0 K
$ 0.0 K 2.
The total direct staff use and amount of funds expended (costed) during the period and the total cumulative to date in the following categories are:
l June 1986 Cumulative l
a.
Direct Staff Effort 0.0 0.2 b.
Funds ($000)
June 1986 FY 86 Direct Salaries 0.0 K 11.6 K Material and Services (excluding ADP) 0.0 1.8 ADP Support 0.0 0.8 Subcontracts 0.0 0.0 Travel Expenses 0.0 0.0 Indirect Labor Costs 0.0 9.2 Other (specify) General Administrative TOTAL 0.0 K 23.4 K e
3.
Total amount of funds expended during the period and cumulative to date for the FSV project is as follows:
Project June 1986 Cumulative Fort St. Vrain 0.0 K 23.4 K 4.
Expenditure Summary June 1986 Cumulative Project 1: Review and Assessment CRDM Refurbishment 0.0 23.4 Project 2: Technical Support on Long Term Issues 0.0 0.0 -. _ -