MONTHYEARML20217F1041999-10-14014 October 1999 Proposed Tech Specs Pages,Revising TS Sections 2.2 & 3.0/4.0,necessary to Support Mod P000224 Which Will Install New Power Range Neutron Monitoring Sys & Incorporate long- Term thermal-hydraulic Stability Solution Hardware ML20216J3471999-09-27027 September 1999 Corrected Tech Specs Page,Modifying Appearance of TS Page 3/4 4-8 as Typo Identified in Section 3.4.3.1 ML20212H5681999-09-27027 September 1999 Proposed Tech Specs Pages,Revising TS to Clarify Several Administrative Requirements,Delete Redundant Requirements & Correct Typos ML20196F5551999-06-22022 June 1999 Proposed Tech Specs Pages to Delete Surveillance Requirement 4.4.1.1.2 & Associated TS Administrative Controls Section 6.9.1.9.h,removing Recirculation Sys MG Set Stop ML20195H0651999-06-0909 June 1999 Revised Bases Pages B 3/4 10-2 & B 3/4 2-4 for LGS Units 1 & 2,in Order to Clarify That Requirements for Reactor Enclosure Secondary Containment Apply to Extended Area Encompassing Both Reactor Enclosure & Refueling Area ML20195E7611999-06-0707 June 1999 Proposed Tech Specs Table 3.6.3-1 & Associated Notations, Reflecting Permanently Deactivated Instrument Reference Leg Isolation Valve HV-61-102 ML20195G0481999-06-0707 June 1999 Proposed Tech Specs Section 3/4.4.3, RCS Leakage,Leakage Detection Systems, Clarifying Action Statement Re Inoperative Reactor Coolant Leakage Detection Systems ML20195B8431999-05-26026 May 1999 Proposed Tech Specs Section 4.1.3.5.b,removing & Relocating Control Rod Scram Accumulators Alarm Instrumentation to UFSAR & TS Section 3.1.3.5,allowing Alternate Method for Determining Whether Control Rod Drive Pump Is Operating ML20207L6591999-03-11011 March 1999 Proposed Tech Specs Section 2.1, Safety Limits, Revising MCPR Safety Limit ML20199G2021999-01-12012 January 1999 Proposed Tech Specs Section 3/4.4.2 & TS Bases Sections B 3/4.4.2,B 3/4.5.1 & B 3/4.5.2 to Increase Allowable as-found Main Steam SRV Code Safety Function Lift Setpoint Tolerance from +1% to +3% ML20199A7271999-01-0404 January 1999 Proposed Tech Specs Revising Administrative Section of TS Re Controlled Access to High Radiation Areas & Rept Dates for Annual Ore Rept & Annual Rer Rept ML20155H6401998-10-30030 October 1998 Proposed Tech Specs Pages Revising TS SRs 4.8.4.3.b.1, 4.8.4.3.b.2 & 4.8.4.3.b.3 in Order to Reflect Relay Setpoint Calculation Methodology ML20154Q8941998-10-15015 October 1998 Proposed Tech Specs Re Addition of Special Test Exception for IST & Hydrostatic Testing ML20154L3971998-10-13013 October 1998 Revised Tech Spec Bases Pages,Clarifying Thermal Overload Operation for Motor Operated Valves with Maintained Contact Control Switches ML20151Z4721998-09-14014 September 1998 Proposed Tech Specs Revising Table 4.4.6.1.3-1,re Withdrawal Schedule for Reactor Pressure Vessel Matl Surveillance Program Capsules ML20151V0951998-09-0404 September 1998 Proposed Tech Specs Ensuring Fidelity Between TS Pages & 970324 Submittal ML20236M1221998-07-0202 July 1998 Proposed Tech Specs Change Request 96-06-0,modifying FOL Page 8 ML20217K5291998-04-24024 April 1998 Proposed Tech Specs Page 6-18a Revising MCPR Safety Limit for Lgs,Unit 1,cycle 8 ML20202G7871998-02-0909 February 1998 Proposed TS Section 2.1, Safety Limits, Revising MCPR Safety Limit.Nonproprietary Supporting Info Encl ML20199G7771998-01-27027 January 1998 Proposed Tech Specs Pages,Removing Maximum Isolation Time for HPCI Turbine Exhaust Containment Isolation Valve HV-055-1(2)F072 from TS ML20198M7861998-01-12012 January 1998 Proposed Tech Specs Table 4.4.6.1.3-1 Re Surveillance Specimen Program Evaluation for Limerick Generating Station, Unit 1 ML20199H5971997-11-18018 November 1997 Proposed Tech Specs Re Affected Unit 1 FOL Page 8 ML20212D1851997-10-24024 October 1997 Proposed Tech Specs Revising Section 3/4.1.3.6 to Exempt Control Rod 50-27 from Coupling Test for Remainder for Cycle 7 at LGS Unit 1,provided Certain Conditions Are Met ML20216H1101997-09-0808 September 1997 Proposed Tech Specs,Supplementing Change Request 96-06-0 by Adding Three Addl TS Pages Containing Typos Discovered Since 970225 Submittal ML20210T9231997-09-0202 September 1997 Proposed Tech Specs,Revising TS Section 4.0.5 & Bases Sections B 4.0.5 & B 3/4.4.8 Re SRs Associated W/Isi & IST of ASME Code Class 1,2 & 3 Components ML20138A2311997-04-21021 April 1997 Proposed Tech Specs,Providing New Pp B 3/4 8-2a to Accomodate Overflow of Text from TS Bases Pp B 3/4 8-2 ML20137X8101997-04-0909 April 1997 Proposed Tech Specs Re Battery Specific Gravity Changes ML20137G6751997-03-24024 March 1997 Proposed Tech Specs Deleting Drywell & Suppression Chamber Purge Sys Operational Time Limit & Add SR to Ensure Purge Sys Large Supply & Exhaust Valves Are Closed as Required ML20135D0961997-02-25025 February 1997 Proposed Tech Specs Changing Corporate Name from PA Electric Co to PECO Energy Co & Removing Obsolete Info & Correcting Typos ML20133L2141997-01-15015 January 1997 Proposed Tech Specs Pp 3/4 5-5 mark-up Rev for Unit 1 Revising TS by Eliminating in-situ Functional Testing of ADS Valves Requirement as Part of start-up Testing Activities ML20135F0961996-12-0606 December 1996 Proposed Tech Specs 2.1 Re Safety Limits ML20135A4491996-11-25025 November 1996 Proposed Tech Specs Change Request 96-22-0,revising TS SR 4.8.1.1.2.e.2 & Supporting TS Bases Section 3/4.8,to Clarify Requirements Associated W/Single Load Rejection Testing of EDGs ML20134L7571996-11-0505 November 1996 Proposed Tech Specs Revising Same Pp Contained in TS Change Request 95-14-0 Re Adoption of Performance Based 10CFR50, App J,Option B Testing ML20128N7761996-09-27027 September 1996 Proposed Tech Specs 3/4.6.5 Re Secondary Containment & 4.6.5.1.1 Re Surveillance Requirements ML20116L2701996-08-0808 August 1996 Proposed Tech Specs,Revising TS Sections 3/4.3.1,3/4.3.2, 3/4.3.3 & Associated TS Bases Sections 3/4.3.1 & 3/4.3.2 to Eliminate Selected Response Time Testing Requirements ML20116H6511996-08-0505 August 1996 Proposed Tech Specs Section 2.1, Safety Limits, to Revise Min Critical Power Ratio Safety Limit ML20116E6191996-08-0101 August 1996 Proposed Tech Specs 3/4.4.6 Re Addition of Two Hydroset Curves,Effective for 6.5 & 8.5 Efpy,To Existing Ptol Curves ML20115A9111996-06-28028 June 1996 Proposed Tech Specs,Performing Containment leakage-rate Testing Per 10CFR50,App J, Primary Reactor Containment Leakage Testing for Water-Cooled Power Reactors, Option B ML20117H2621996-05-20020 May 1996 Proposed Tech Specs Sections 3/4.4.9.2,3/4.9.11.1,3/4.9.11.2 & Associated TS Bases 3/4.4.9 & 3/4.9.11 to More Clearly Described RHR Sys Shutdown Cooling Mode Operation ML20117D7801996-05-0303 May 1996 Proposed Tech Specs,Revising TS SRs to Change Surveillance Test Frequency for Performing Flow Testing of SGTS & RERS from Monthly to Quarterly ML20107M5141996-04-25025 April 1996 Proposed Tech Specs 3/4.3.7.7 Re Relocation of Traversing in-core Probe LCO ML20101L9211996-03-29029 March 1996 Proposed Tech Specs,Revising TS SR 4.5.1.d.2.b to Delete Requirement to Perform Functional Testing of ADS Valves as Part of start-up Testing Activities ML20095K5681995-12-22022 December 1995 Proposed Tech Specs Re Increase of Drywell & Suppression Chamber Purge Sys Operating Time Limit from 90 H Each 365 Days to 180 H Each 365 Days ML20094D2381995-10-27027 October 1995 Proposed TS Pages 1-6 & 1-7,revising Definitions 1.33, Reactor Enclosure Secondary Containment Integrity & 1.35, Refueling Floor Secondary Containment Integrity.' ML20093E5711995-10-10010 October 1995 Revised TS Page Re Primary Containment Isolation Valves ML20092J3961995-09-18018 September 1995 Proposed TS Table 4.3.1.1-1, RPS Instrumentation SRs & TS Bases 3/4.3.1,changing Calibr Frequency for LPRM Signal from Every 1,000 EFPH to Every 2,000 Megawatt Days Per Std Ton ML20092J3281995-09-14014 September 1995 Proposed Tech Specs,Removing Secondary Containment Isolation Valve Tables ML20087F9611995-08-10010 August 1995 Revised TS Pages 6-6 & 6-7 ML20087C9531995-08-0101 August 1995 Proposed Tech Specs in Order to Provide Alternate Actions to Allow Continuation of Core Alterations in Event Certain RMCS & Refueling Interlocks Are Inoperable ML20086S6131995-07-28028 July 1995 Proposed Tech Specs Reflecting Changes to Surveillance Test Frequency Requirements for Various RPS Instrumentation 1999-09-27
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20217F1041999-10-14014 October 1999 Proposed Tech Specs Pages,Revising TS Sections 2.2 & 3.0/4.0,necessary to Support Mod P000224 Which Will Install New Power Range Neutron Monitoring Sys & Incorporate long- Term thermal-hydraulic Stability Solution Hardware ML20212H5681999-09-27027 September 1999 Proposed Tech Specs Pages,Revising TS to Clarify Several Administrative Requirements,Delete Redundant Requirements & Correct Typos ML20216J3471999-09-27027 September 1999 Corrected Tech Specs Page,Modifying Appearance of TS Page 3/4 4-8 as Typo Identified in Section 3.4.3.1 ML20196F5551999-06-22022 June 1999 Proposed Tech Specs Pages to Delete Surveillance Requirement 4.4.1.1.2 & Associated TS Administrative Controls Section 6.9.1.9.h,removing Recirculation Sys MG Set Stop ML20195H0651999-06-0909 June 1999 Revised Bases Pages B 3/4 10-2 & B 3/4 2-4 for LGS Units 1 & 2,in Order to Clarify That Requirements for Reactor Enclosure Secondary Containment Apply to Extended Area Encompassing Both Reactor Enclosure & Refueling Area ML20195E7611999-06-0707 June 1999 Proposed Tech Specs Table 3.6.3-1 & Associated Notations, Reflecting Permanently Deactivated Instrument Reference Leg Isolation Valve HV-61-102 ML20195G0481999-06-0707 June 1999 Proposed Tech Specs Section 3/4.4.3, RCS Leakage,Leakage Detection Systems, Clarifying Action Statement Re Inoperative Reactor Coolant Leakage Detection Systems ML20195B8431999-05-26026 May 1999 Proposed Tech Specs Section 4.1.3.5.b,removing & Relocating Control Rod Scram Accumulators Alarm Instrumentation to UFSAR & TS Section 3.1.3.5,allowing Alternate Method for Determining Whether Control Rod Drive Pump Is Operating ML20207L6591999-03-11011 March 1999 Proposed Tech Specs Section 2.1, Safety Limits, Revising MCPR Safety Limit ML20199G2021999-01-12012 January 1999 Proposed Tech Specs Section 3/4.4.2 & TS Bases Sections B 3/4.4.2,B 3/4.5.1 & B 3/4.5.2 to Increase Allowable as-found Main Steam SRV Code Safety Function Lift Setpoint Tolerance from +1% to +3% ML20199A7271999-01-0404 January 1999 Proposed Tech Specs Revising Administrative Section of TS Re Controlled Access to High Radiation Areas & Rept Dates for Annual Ore Rept & Annual Rer Rept ML20195J1651998-11-16016 November 1998 Rev D to LGS Emergency Preparedness NUMARC Eals ML20155H6401998-10-30030 October 1998 Proposed Tech Specs Pages Revising TS SRs 4.8.4.3.b.1, 4.8.4.3.b.2 & 4.8.4.3.b.3 in Order to Reflect Relay Setpoint Calculation Methodology ML20154Q8941998-10-15015 October 1998 Proposed Tech Specs Re Addition of Special Test Exception for IST & Hydrostatic Testing ML20154L3971998-10-13013 October 1998 Revised Tech Spec Bases Pages,Clarifying Thermal Overload Operation for Motor Operated Valves with Maintained Contact Control Switches ML20151Z4721998-09-14014 September 1998 Proposed Tech Specs Revising Table 4.4.6.1.3-1,re Withdrawal Schedule for Reactor Pressure Vessel Matl Surveillance Program Capsules ML20151V0951998-09-0404 September 1998 Proposed Tech Specs Ensuring Fidelity Between TS Pages & 970324 Submittal ML20236M1221998-07-0202 July 1998 Proposed Tech Specs Change Request 96-06-0,modifying FOL Page 8 ML20217K5291998-04-24024 April 1998 Proposed Tech Specs Page 6-18a Revising MCPR Safety Limit for Lgs,Unit 1,cycle 8 ML20202G7871998-02-0909 February 1998 Proposed TS Section 2.1, Safety Limits, Revising MCPR Safety Limit.Nonproprietary Supporting Info Encl ML20199G7771998-01-27027 January 1998 Proposed Tech Specs Pages,Removing Maximum Isolation Time for HPCI Turbine Exhaust Containment Isolation Valve HV-055-1(2)F072 from TS ML20198M7861998-01-12012 January 1998 Proposed Tech Specs Table 4.4.6.1.3-1 Re Surveillance Specimen Program Evaluation for Limerick Generating Station, Unit 1 ML20203H2501997-12-31031 December 1997 Rev 19 to Odcm ML20198N8061997-12-31031 December 1997 NPDES Permit PA-0052221 Study Plan for Fecal Coliform Bacteria in Pont Pleasant Water Diversion Sys During May- Sept 1998 ML20199H5971997-11-18018 November 1997 Proposed Tech Specs Re Affected Unit 1 FOL Page 8 ML20212D1851997-10-24024 October 1997 Proposed Tech Specs Revising Section 3/4.1.3.6 to Exempt Control Rod 50-27 from Coupling Test for Remainder for Cycle 7 at LGS Unit 1,provided Certain Conditions Are Met ML20211P9471997-10-15015 October 1997 Revised MSRV Tailpipe Temp Action Plan ML20216H1101997-09-0808 September 1997 Proposed Tech Specs,Supplementing Change Request 96-06-0 by Adding Three Addl TS Pages Containing Typos Discovered Since 970225 Submittal ML20210T9231997-09-0202 September 1997 Proposed Tech Specs,Revising TS Section 4.0.5 & Bases Sections B 4.0.5 & B 3/4.4.8 Re SRs Associated W/Isi & IST of ASME Code Class 1,2 & 3 Components ML20141K9461997-05-27027 May 1997 PECO Nuclear Limerick Generating Station Unit 2 Startup Test Rept Cycle 5 ML20203H2701997-04-30030 April 1997 Rev 18 to Odcm ML20138A2311997-04-21021 April 1997 Proposed Tech Specs,Providing New Pp B 3/4 8-2a to Accomodate Overflow of Text from TS Bases Pp B 3/4 8-2 ML20137X8101997-04-0909 April 1997 Proposed Tech Specs Re Battery Specific Gravity Changes ML20137G6751997-03-24024 March 1997 Proposed Tech Specs Deleting Drywell & Suppression Chamber Purge Sys Operational Time Limit & Add SR to Ensure Purge Sys Large Supply & Exhaust Valves Are Closed as Required ML20135D0961997-02-25025 February 1997 Proposed Tech Specs Changing Corporate Name from PA Electric Co to PECO Energy Co & Removing Obsolete Info & Correcting Typos ML20133L2141997-01-15015 January 1997 Proposed Tech Specs Pp 3/4 5-5 mark-up Rev for Unit 1 Revising TS by Eliminating in-situ Functional Testing of ADS Valves Requirement as Part of start-up Testing Activities ML20135F0961996-12-0606 December 1996 Proposed Tech Specs 2.1 Re Safety Limits ML20135A4491996-11-25025 November 1996 Proposed Tech Specs Change Request 96-22-0,revising TS SR 4.8.1.1.2.e.2 & Supporting TS Bases Section 3/4.8,to Clarify Requirements Associated W/Single Load Rejection Testing of EDGs ML20134L7571996-11-0505 November 1996 Proposed Tech Specs Revising Same Pp Contained in TS Change Request 95-14-0 Re Adoption of Performance Based 10CFR50, App J,Option B Testing ML20128N7761996-09-27027 September 1996 Proposed Tech Specs 3/4.6.5 Re Secondary Containment & 4.6.5.1.1 Re Surveillance Requirements ML20116L2701996-08-0808 August 1996 Proposed Tech Specs,Revising TS Sections 3/4.3.1,3/4.3.2, 3/4.3.3 & Associated TS Bases Sections 3/4.3.1 & 3/4.3.2 to Eliminate Selected Response Time Testing Requirements ML20116H6511996-08-0505 August 1996 Proposed Tech Specs Section 2.1, Safety Limits, to Revise Min Critical Power Ratio Safety Limit ML20116E6191996-08-0101 August 1996 Proposed Tech Specs 3/4.4.6 Re Addition of Two Hydroset Curves,Effective for 6.5 & 8.5 Efpy,To Existing Ptol Curves ML20113E0491996-06-28028 June 1996 Technical Basis & Description of Approach for Review Method Selection ML20115A9111996-06-28028 June 1996 Proposed Tech Specs,Performing Containment leakage-rate Testing Per 10CFR50,App J, Primary Reactor Containment Leakage Testing for Water-Cooled Power Reactors, Option B ML20117H2621996-05-20020 May 1996 Proposed Tech Specs Sections 3/4.4.9.2,3/4.9.11.1,3/4.9.11.2 & Associated TS Bases 3/4.4.9 & 3/4.9.11 to More Clearly Described RHR Sys Shutdown Cooling Mode Operation ML20112C1691996-05-17017 May 1996 Startup Rept Cycle 7 ML20117D7801996-05-0303 May 1996 Proposed Tech Specs,Revising TS SRs to Change Surveillance Test Frequency for Performing Flow Testing of SGTS & RERS from Monthly to Quarterly ML20107M5141996-04-25025 April 1996 Proposed Tech Specs 3/4.3.7.7 Re Relocation of Traversing in-core Probe LCO ML20101L9211996-03-29029 March 1996 Proposed Tech Specs,Revising TS SR 4.5.1.d.2.b to Delete Requirement to Perform Functional Testing of ADS Valves as Part of start-up Testing Activities 1999-09-27
[Table view] |
Text
_____ ___ _ -_
. ELL'CTRICAL POWER SYSTEMS REACTOR PROTECTION SYSTEM ELECTRICAL POWER MONITORING LIMITING CONDITION FOR OPERATION 3.8.4.3 Two reactor protection system (RPS) electric power monitoring channels for each inservice RPS Inverter or alternate power supply shall be OPERABLE.
APPLICABILITY: At all times. .
ACTION:
- a. With one RPS electric power monitoring channel for an inservice RPS Inverter or alternate power supply inoperable, restore the inoperable power monitoring channel to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or remove the associated RPS Inverter or alternate power supply from service,
- b. With both RPS electric power monitoring channels for an inservice RPS Inverter or alternate power supply inoperable, restore at least one electric power monitoring channel to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or remove the associated RPS Inverter or alternate power supply from service.
SURVEILLANCE REQUIREMENTS 4.8.4.3 The above specified RPS electric power monitoring channels shall be determined OPERABLE:
- a. By performance of a CHANNEL FUNCTIONAL TLST each time the plant is in COLD SHUTDOWN for a period of more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, unless performed in the previous 6 months.
- b. At least once per 24 months by demonstrating the OPERABILITY of overvoltage, undervoltage, and underfrequency protective instrumenta -
tion by performance of a CHANNEL CALIBRATION including simulated automatic actuation of the protective relays, tripping logic, and output circuit breakers and verifying the following setpoints.
- 1. Overvoltage s 127.6 VAC, l
- 2. Undervoltage a 110.7 VAC, l
- 3. Underfrequency a 57.05 Hz.
l 9911100213 981030 r" gDR ADOCK 05000352-PDR LIMERICK - UNIT 1 3/4 8-28
. ELECTRICAL POWER SYSTEMS REACTOR PROTECTf0N SYSTEM ELECTRfCAL POWER MONITORING ,, - l LIMITING CONDITION FOR OPERATION 3.8.4.3 for each inservice RPS Inverter or alternate power supply shall be O APPLICABILITY: At all times.
ACTION:
a.
With one RPS electric power monitoring channel for an inservice RPS Inverter or alternate power supply inoperable, restore the inoperable power monitoring channel to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or remove the associated RPS Inverter or alternate power supply from service.
b.
With both RPS electric power monitoring channels for an inservice RPS Inverter or alternate power supply inoperable, restore at least one electric power monitoring channel to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or remove the associated RPS Inverter or alternate power supply from service.
SURVEILLANCE REOUTREMENTS 4.8.4.3 The above specified RPS electric power monitoring channels shall be determined OPERABLE:
l
- a. By performance of a CHANNEL FUNCTIONAL TEST each time the plant is in COLD SHUTCC'AN fer a period cf more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, uniass !
performed in the previous 6 months.
- b. At least once per 24 months by demonstrating the OPERABILITY of I overvoltage, undervoltage, and underfrequency protective instrumenta-tion by performance of a CHANNEL CALIBRATION including simulated automatic actuatien of the protective relays, tripping logic, and output circuit breakers and verifying the following setpoints.
I. Overvoltage s @ VAC, /27,6 l/g
- 2. Undervoltage 2 @ 1l07 t/M
- 3. Underfrequency 2 @ 67,05NS I
3p os @
L8MERICK - UNIT 2 3/4 8-28 Amencment No. 34, 39
1 INSERTA:
. 1 Add per ECR 98-01410; The RPS Electnc Power Monitoring System is provided to isolate the RPS bus from the RPS /
UPS inverter or an altemate power supply in the event of overvoltage, undervoltage, or underfrequency. This system protects the loads connected to the RPS bus from unacceptable voltage and frequency conditions. The essential equipment powered from the RPS buses includes the RPS logic, scram solenoids, and valve isolation logic.
The Allowable Values are derived from equipment design limits, corrected for calibration and instrument errors. The trip setpoints are then determined, accounting for the remaining instrument errors (e.g., drift). The trip setpoints derived in this manner provide adequate l protection and include allowances for instrumentation uncertainties, calibration tolerances, and j instrument drift.
The Allowable Values for the instrument settings are based on the RPS providing power within the design ratings of the associated RPS components (e.g., RPS logic, scram solenoids). The most limiting voltage requirement and associated line losses determine the settings of the l electric power monitoring instrument channels.
l l
l I
l l
l t
I i
i
. g l INSERT A:
A'dd per ECR 98-01410:
The RPS Electric Power Monitoring System is provided to isolate the RPS bus from the RPS /
UPS inverter or an attemate power supply in the event of overvoltage, undervoltage, or underfrequency. This system protects the loads connected to the RPS bus from unacceptable voltage and frequency conditions. The essential equipment powered from the RPS buses includes the RPS logic, scram solenoids, and valve isolation logic.
The Allowable Values are derived from equipment design limits, corrected for cabbration and instrument enors. The trip setpomts are then determmed, accounting for the remaining instrument enors (e.g., drift). The trip setponts derived in this manner provide adequate protechon and include allowances for instrumentation uncertainties, calibration tolerances, and instrument drift.
The Allowable Values for the instrument settings are based on the RPS providing power within the design ratings of the associated RPS components (e.g., RPS logic, scram solenoids). The most limiting voltage requirement end associated line losses determine the settings of 'he electric power monitoring instrument channels.