Joint Status Report
ML20167A335
Person / Time
Site: Pilgrim
Issue date: 06/15/2020
From: Dorfler J, Healey M, Doris Lewis, Lovett A, Raimo S, Schofield S
Balch & Bingham, LLP, Entergy Nuclear Operations, Entergy Services, Holtec Decommissioning International, Holtec, Holtec Pilgrim, Pillsbury, Winthrop, Shaw, Pittman, LLP, State of MA, Office of the Attorney General
To:
NRC/OCM
SECY RAS
References
50-293 LT, 72-1044 LT, License Transfer, RAS 55710
Download: ML20167A335 (3)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )

)

ENTERGY NUCLEAR OPERATIONS, INC., )

ENTERGY NUCLEAR GENERATION )

COMPANY, AND HOLTEC ) Docket Nos. 50-293-LT & 72-1044-LT DECOMMISSIONING INTERNATIONAL, )

LLC )

)

(Pilgrim Nuclear Power Station) )

)

)

JOINT STATUS REPORT Pursuant to the Nuclear Regulatory Commissions June 4, 2020 Order, Holtec International, Holtec Decommissioning International, LLC, Entergy Nuclear Generation Company (now known as Holtec Pilgrim, LLC) and Entergy Nuclear Operations, Inc.

(Applicants) and the Petitioner, the Commonwealth of Massachusetts (Commonwealth or Massachusetts), provide the following status report on the status of their efforts to finalize a settlement agreement. The Holtec Applicants and the Commonwealth have made additional progress toward finalizing a settlement agreement since June 4, 2020, and are pleased to report that, subject to final approvals, they have reached an agreement in principle on the terms of a settlement agreement, which, if approved and executed, will result in the Commonwealth withdrawing its pending Petition.

//

//

//

//

Respectfully submitted this 15th day of June, 2020, HOLTEC INTERNATIONAL, COMMONWEALTH OF MASSACHUSETTS HOTEC DECOMMISSIONING INTERNATIONAL, LLC, By its attorneys, HOLTEC PILGRIM, LLC MAURA HEALEY Executed in accord with 10 C.F.R. 2.304(d) ATTORNEY GENERAL Alan D. Lovett Balch & Bingham LLP Signed (electronically) by 1710 Sixth Avenue North SETH SCHOFIELD Birmingham, AL 35203-2015 Senior Appellate Counsel 205-226-8769 JOSEPH DORFLER alovett@balch.com Assistant Attorney General Energy and Environment Bureau One Ashburton Place, 18th Floor Boston, Massachusetts 02108 617-963-2000 ENTERGY NUCLEAR OPERATIONS, seth.schofield@mass.gov INC. joseph.dorfler@mass.gov Executed in accord with 10 C.F.R. 2.304(d)

Susan H. Raimo Entergy Services, LLC 101 Constitution Avenue, NW Suite 200 East Washington, DC 20001 202-530-7330 sraimo@entergy.com David R. Lewis Pillsbury Winthrop Shaw Pittman, LLP Washington, DC 20036-3006 202-663-8474 David.lewis@pillsburylaw.com UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )

)

ENTERGY NUCLEAR OPERATIONS, INC., )

ENTERGY NUCLEAR GENERATION )

COMPANY, AND HOLTEC ) Docket Nos. 50-293-LT & 72-1044-LT DECOMMISSIONING INTERNATIONAL, )

LLC )

)

(Pilgrim Nuclear Power Station) )

)

)

CERTIFICATION OF SERVICE Pursuant to 10 C.F.R. § 2.305, I certify that copies of the Joint Status Report have been served upon the Electronic Information Exchange, the NRCs e-filing system, in the above-captioned proceeding this 15th day of June 2020.

Signed (electronically) by Seth Schofield Senior Appellate Counsel Energy and Environment Bureau One Ashburton Place, 18th Floor Boston, Massachusetts 02108 617-963-2436 seth.schofield@mass.gov Dated: June 15, 2020