MONTHYEARML21299A0032021-10-28028 October 2021 and Waterford Steam Electric Station, Unit 3 - Approval of Request for Alternative EN-20-RR-003 from Certain Requirements of the ASME Code ML21054A3302021-02-24024 February 2021 Approval of Alternative IP3-ISI-RR-16 to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement CNRO-2020-00016, Entergy Nuclear Operations, Inc - Relief Request EN-RR-20-002: Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv)2020-08-12012 August 2020 Entergy Nuclear Operations, Inc - Relief Request EN-RR-20-002: Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv) ML19254A6032019-09-19019 September 2019 Units 2 and 3; Palisades Nuclear Plant; River Bend; and Waterford Steam Electric Station, Unit 3 - Relief Request No. EN-19-RR-1, Use of ASME Code Case N-831-1 ML19039A1492019-02-25025 February 2019 Issuance of Relief Request IP3-ISI-RR-14 Alternative Examination Required by ASME Code Case N-724-4 CNRO-2019-00002, Relief Request Number EN-19-RR-1, Proposed Alternative to Use ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 12019-01-31031 January 2019 Relief Request Number EN-19-RR-1, Proposed Alternative to Use ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 1 ML18251A0042018-09-18018 September 2018 Safety Evaluation for Relief Request IP3-ISI-RR-11, RR-12, RR-15 Approval of Alternative Associated with Extension of Fourth Interval Reactor Vessel and Piping Weld Inspections (EPID: L-2017-LLR-0124,0127) ML18193B0302018-07-18018 July 2018 Safety Evaluation for Relief Request IP3-ISI-RR-13 Fourth Ten-year Inservice Inspection Interval Extension ML18128A0672018-06-0808 June 2018 Arkansas, Units 1 and 2; Grand Gulf, Unit 1; Indian Point Unit Nos. 2 and 3; Palisades; Pilgrim; River Bend Station, Unit 1; and Waterford, Unit-3 Relief Request No. EN-17-RR-1, Alternative to Use ASME Code Case N-513-4 ML18099A3732018-04-0909 April 2018 04/09/2018 E-mail from R. Guzman to R. Walpole, Verbal Authorization for Relief Request IP2-ISI-RR-06 ML18059A1562018-03-0606 March 2018 Safety Evaluation for Relief Request IP2-ISI-RR-05 Alternative Examination Volume Required by ASME Code Case N-729-4 ML18005A0662018-01-23023 January 2018 Safety Evaluation of Relief Requests ISI-RR-20, ISI-RR-21, and ISI-RR-22 Regarding the Fourth 10-Year Interval of the Inservice Inspection Program CNRO-2017-00022, Relief Request Number EN-17-RR-1 - Proposed Alternative to Use ASME Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate-Energy Class 2 or 3 Piping, Section XI, Division 12017-11-17017 November 2017 Relief Request Number EN-17-RR-1 - Proposed Alternative to Use ASME Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate-Energy Class 2 or 3 Piping, Section XI, Division 1 ML17174B1442017-07-12012 July 2017 Relief Request for EN-ISI-16-1 Regarding Use of Later Edition and Addenda of the ASME Code ML17069A2832017-03-16016 March 2017 Relief Request No. IP3-ISI-RR-09, for Alternative to the Depth Sizing Qualification Requirement ML16358A4442017-01-11011 January 2017 Relief from the Requirements of the ASME Code Regarding Alternate IP3-RR-10 to the Full Circumferential Inspection Requirement of Code Case N-513-3 ML16167A0812016-07-15015 July 2016 Request for Alternative IP2-ISI-RR-03 to Weld Reference System Examination Required by ASME Code Subarticle IWA-2600 ML16096A2692016-06-0606 June 2016 Arkansas; Grand Gulf; James A. Fitzpatrick; Indian Point; Palisades; Pilgrim; River Bend; and Waterford - Relief Request RR-EN-15-2, Proposed Alternative to Use ASME Boiler and Pressure Vessel Code Case N-786-1 ML16053A0252016-03-0303 March 2016 IP2-ISI-44-18, Relief from the Requirements of the ASME Code CNRO-2015-00017, Entergy Submits Relief Request RR EN-15-1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Waster Service, Section XI, D2015-06-0505 June 2015 Entergy Submits Relief Request RR EN-15-1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Waster Service, Section XI, Division ML14198A3312014-07-23023 July 2014 Safety Evaluation for Relief Request IP3-ISI-RR-06 for Reactor Vessel Weld Examinations (Tac No. MF3345) NL-13-041, Relief Request IP2-ISI-RR-17: Code Case N-770-1 Weld Inspection Frequency Extension2013-02-20020 February 2013 Relief Request IP2-ISI-RR-17: Code Case N-770-1 Weld Inspection Frequency Extension ML12334A3172012-12-0303 December 2012 Relief Request IP2-ISI-RR-15 - Proposed Alternative to the Use of a Weld Reference System NL-12-065, 2012 Summary Report for In-Service Inspection and Repairers and Replacements2012-06-13013 June 2012 2012 Summary Report for In-Service Inspection and Repairers and Replacements NL-12-069, Unit Number 2, Relief Request IP2-1SI-RR-15 - Proposed Alternative to the Use of a Weld Reference System2012-05-23023 May 2012 Unit Number 2, Relief Request IP2-1SI-RR-15 - Proposed Alternative to the Use of a Weld Reference System ML11105A1222011-04-25025 April 2011 Relief from the Requirements of the ASME Code to Perform Essentially 100 Percent Volumetric Examination of the Weld and Adjacent Base Material for the Third 10-Year Inservice Inspection ML11109A0162011-04-25025 April 2011 Relief Request No. IP2-ISI-RR-12, Reactor Vessel Shell-To-Flange Weld Inspection for the Fourth 10-Year Inservice Inspection Interval (Tac No. ME5180) NL-10-136, Submittal of 10 CFR 50.55a Relief Request IP2-ISI-RR-12 for 4th Ten-Year Inservice Inspection Interval2010-12-14014 December 2010 Submittal of 10 CFR 50.55a Relief Request IP2-ISI-RR-12 for 4th Ten-Year Inservice Inspection Interval ML1017400482010-07-15015 July 2010 Relief Request RR-11 for the Fourth 10-Year Inservice Inspection Interval NL-10-061, CFR 50.55a Relief Requests RR-3-49 and RR-3-50 from Examinations of Component Welds with Less than Essentially 100% Examination Coverage for Third Ten-Year Inservice Inspection Interval2010-07-0505 July 2010 CFR 50.55a Relief Requests RR-3-49 and RR-3-50 from Examinations of Component Welds with Less than Essentially 100% Examination Coverage for Third Ten-Year Inservice Inspection Interval ML1015303122010-06-0707 June 2010 Relief Request RR-02 for the Fourth 10-Year Inservice Inspection Interval NL-09-022, Supplement to Request for Relief 3-48 and 3-47 (I) to Support Refuel Outage 15 Inservice Inspection Program2009-02-0606 February 2009 Supplement to Request for Relief 3-48 and 3-47 (I) to Support Refuel Outage 15 Inservice Inspection Program NL-09-0111, Submittal of Relief Requests No. 3-45, 3-46, 3-47(I) and 3-48 to Support the Unit 3 Refuel Outage 15 Inservice Inspection Program2009-01-22022 January 2009 Submittal of Relief Requests No. 3-45, 3-46, 3-47(I) and 3-48 to Support the Unit 3 Refuel Outage 15 Inservice Inspection Program NL-09-003, Supplemental Response to Request for Additional Information on Request for Relief to Extend the Inservice Inspection Interval for the Reactor Vessel Weld Examination2009-01-20020 January 2009 Supplemental Response to Request for Additional Information on Request for Relief to Extend the Inservice Inspection Interval for the Reactor Vessel Weld Examination NL-08-096, Request for Relief to Extend Inservice Inspection Interval for the Reactor Vessel Weld Examination and Request for License Amendment for Submittal of ISI Information and Analyses2008-07-0808 July 2008 Request for Relief to Extend Inservice Inspection Interval for the Reactor Vessel Weld Examination and Request for License Amendment for Submittal of ISI Information and Analyses ML0721304872007-09-0505 September 2007 Relief Request No. RR-01 NOC-AE-06002031, Request for Relief from ASME Boiler and Pressure Vessel Code, Section XI Requirements for Use of Penetrameters in Radiographic Examinations2006-06-14014 June 2006 Request for Relief from ASME Boiler and Pressure Vessel Code, Section XI Requirements for Use of Penetrameters in Radiographic Examinations ML0602600762006-02-0808 February 2006 Relief Request (RR) No. 74 NL-05-0720, Request for Relief to Extend the Third 10-Year Inservice Inspection Interval for the Reactor Vessel Weld Examination2005-06-0808 June 2005 Request for Relief to Extend the Third 10-Year Inservice Inspection Interval for the Reactor Vessel Weld Examination ML0509401362005-04-0404 April 2005 Relief, Relaxation of First Revised Order on Reactor Vessel Nozzles ML0507700102005-03-18018 March 2005 Relaxation of First Revised Order on Reactor Vessel Nozzles ML0427406642004-10-14014 October 2004 Relief Request Nos. R-33, R-71, R 3-40(A) and R-41, James A. FitzPatrick Nuclear Power Plant, Indian Point Nuclear Generating Unit Nos. 2 and No. 3 and Pilgrim Nuclear Power Station ML0427406282004-10-14014 October 2004 Relief Request Nos. 65, 66, 3-34 and 3-35 Regarding Alternative Nondestructive Examination Qualification Requirements ML0425203922004-10-0505 October 2004 Relief, Requirements of American Society of Mechanical Engineers Boiler & Pressure Vessel Code, Section III, 1965 Edition, & Section XI, 1989 Edition, for Repair & Inspection of Reactor Pressure Vessel Head Penetrations ML0418901542004-07-0707 July 2004 Relief, Relief Request Nos. RR-67 and RR 3-36, TAC Nos. MC1698 and MC1699 ML0410700882004-07-0606 July 2004 Relief Request to Use American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code) Case N-600 ML0408205162004-03-22022 March 2004 Relief Request Nos. RR-68, RR3-37, and PRR-34 (TAC MC1559, MC1560, & MC1561) ML0408506682004-03-19019 March 2004 Relief Request Nos. 70 and 3-39 Regarding Alternative Depth Sizing Criteria.(Tac MC1696 & MC1697) ML0408600062004-03-19019 March 2004 Relief Request No. RR 63 Regarding risk-informed Inservice Inspection Program ML0335000092003-12-16016 December 2003 Inservice Testing Program Relief Request Nos. 47 and 48, MB9111 and MB9112 2021-02-24
[Table view] Category:Safety Evaluation
MONTHYEARML23339A0442023-12-0505 December 2023 Issuance of Amendment No. 68, 301 and 277 Regarding Changes to Implement the Independent Spent Fuel Storage Installation Physical Security Plan ML23326A1322023-12-0505 December 2023 Issuance of Amendment No. 67, 300 & 276 to Implement the Independent Spent Fuel Storage Installation Only Emergency Plan ML23243A8452023-11-30030 November 2023 Enclosure 3: Issuance - IP LAR for SE Renewed Facility Licenses and PDTS to Reflect Permanent Removal of Spent Fuel from SFPs ML23050A0022023-11-17017 November 2023 Enclosure 2 - Safety Evaluation for Indian Point Unit 2 License Amendment Request to Modify Technical Specifications for Staffing Requirements Following Spent Fuel Transfer to Dry Storage ML23100A1172023-11-17017 November 2023 NRC Response - Indian Point Energy Center Generating Units 1, 2, and 3 Letter with Enclosures Regarding Changes to Remove the Cyber Security Plan License Condition ML23064A0002023-11-13013 November 2023 NRC Issuance for Approval-Indian Point EC Units 1, 2 and 3 Emergency Plan and Emergency Action Level Scheme Amendments ML23067A0822023-11-0101 November 2023 Enclosure 2 - Issuance Indian Point Energy Center Generating Units 1, 2, and 3 Safety Exemption Evaluation for Certain Emergency Planning Requirements of 10 CFR 50.47 and Part 50 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML21091A3052022-02-28028 February 2022 Issuance of Amendment No. 272 Revision to Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device (EPID L-2020-LLA-0051) (Non-Proprietary) ML21074A0002021-04-22022 April 2021 Issuance of Amendment No. 270 Permanently Defueled Technical Specifications ML21083A0002021-04-14014 April 2021 Issuance of Amendment No. 63 Permanently Defueled Technical Specifications ML21054A3302021-02-24024 February 2021 Approval of Alternative IP3-ISI-RR-16 to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement ML20297A3332020-11-23023 November 2020 Enclosure 3, Safety Evaluation for Transfer of Renewed Facility Operating Licenses to Holtec International, Owner, and Holtec Decommissioning International, LLC, Operator ML20226A2722020-08-18018 August 2020 Request to Use a Provision of a Later Edition of the ASME BPV Code, Section XI NL-20-050, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-06-24024 June 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline ML20100H9922020-06-0202 June 2020 Issuance of Amendment No. 269 Proposed Technical Specification Changes to City Water Surveillance Requirement and Condensate Storage Tank Required Action A.1 ML20122A2622020-05-0404 May 2020 Correction to Amendment No. 294 Dated April 28, 2020, Permanently Defueled Technical Specifications ML20081J4022020-04-28028 April 2020 Issuance of Amendment No. 294 Permanently Defueled Technical Specifications ML20078L1402020-04-15015 April 2020 Issuance of Amendment Nos. 62, 293, and 268 Changes to Emergency Plan for Post-Shutdown and Permanently Defueled Condition ML20099A1822020-04-13013 April 2020 Issuance of Relief Request IP3-IST-RR-001 - Alternative to Certain Requirements of the ASME Code for Extension of the Fourth 10-Year Inservice Test Interval ML20071Q7172020-04-10010 April 2020 Issuance of Amendment Nos. 292 and No. 267 Changes to Technical Specification Sections 1.1, 4.0, and 5.0 for a Permanently Defueled Condition ML19333B8682019-12-18018 December 2019 Approval of Certified Fuel Handler Training and Retraining Program ML19254A6032019-09-19019 September 2019 Units 2 and 3; Palisades Nuclear Plant; River Bend; and Waterford Steam Electric Station, Unit 3 - Relief Request No. EN-19-RR-1, Use of ASME Code Case N-831-1 ML19175A0422019-09-11011 September 2019 Arkansas Units 1 and 2; Grand Gulf, Unit 1; Indian Point 2 and 3; Palisades; River Bend, Unit 1; Waterford Unit 3 - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules ML19209C9662019-09-0404 September 2019 Issuance of Amendment No. 290 Storage of Fresh and Spent Nuclear Fuel in the Spent Fuel Pool ML19065A1012019-03-21021 March 2019 Issuance of Amendment No. 61 and No. 289 Deletion of License Conditions Related to Decommissioning Trust Provision ML19039A1492019-02-25025 February 2019 Issuance of Relief Request IP3-ISI-RR-14 Alternative Examination Required by ASME Code Case N-724-4 ML18337A4222018-12-20020 December 2018 Issuance of Amendment No. 265 One-Time Extension of 10 CFR Part 50, Appendix J, Type a, Integrated Leakage Rate Test Interval ML18251A0042018-09-18018 September 2018 Safety Evaluation for Relief Request IP3-ISI-RR-11, RR-12, RR-15 Approval of Alternative Associated with Extension of Fourth Interval Reactor Vessel and Piping Weld Inspections (EPID: L-2017-LLR-0124,0127) ML18193B0302018-07-18018 July 2018 Safety Evaluation for Relief Request IP3-ISI-RR-13 Fourth Ten-year Inservice Inspection Interval Extension ML18128A0672018-06-0808 June 2018 Arkansas, Units 1 and 2; Grand Gulf, Unit 1; Indian Point Unit Nos. 2 and 3; Palisades; Pilgrim; River Bend Station, Unit 1; and Waterford, Unit-3 Relief Request No. EN-17-RR-1, Alternative to Use ASME Code Case N-513-4 ML18142A4312018-05-31031 May 2018 Safety Evaluation for Relief Request IP2-ISI-RR-06 Approval of Alternative to Use Embedded Weld Repair ML18059A1562018-03-0606 March 2018 Safety Evaluation for Relief Request IP2-ISI-RR-05 Alternative Examination Volume Required by ASME Code Case N-729-4 ML18005A0662018-01-23023 January 2018 Safety Evaluation of Relief Requests ISI-RR-20, ISI-RR-21, and ISI-RR-22 Regarding the Fourth 10-Year Interval of the Inservice Inspection Program ML17348A6952018-01-11011 January 2018 Issuance of Amendment Connection of Non-Seismic Boric Acid Recovery System to the Refueling Water Storage Tank (CAC No. MF9578; EPID L-2017-LLA-0202) ML17320A3542017-12-22022 December 2017 Issuance of Amendments Amendment of Inter-Unit Transfer of Spent Fuel (CAC Nos. MF8991 and MF8992; EPID L-2016-LLA-0039) ML17315A0002017-12-0808 December 2017 Issuance of Amendments Cyber Security Plan Implementation Schedule (CAC Nos. MF9656, MF9657, and MF9658; EPID: L-2017-LLA-0217) ML17174B1442017-07-12012 July 2017 Relief Request for EN-ISI-16-1 Regarding Use of Later Edition and Addenda of the ASME Code ML17065A1712017-03-27027 March 2017 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML17069A2832017-03-16016 March 2017 Relief Request No. IP3-ISI-RR-09, for Alternative to the Depth Sizing Qualification Requirement ML16336A4922017-01-27027 January 2017 Transmittal Letter: Order Approving Transfer of Master Decommissioning Trust Funds for Indian Point, No. 3 & FitzPatrick Nuclear Plant from the Power Authority of the State of New York to Entergy Nuclear Operations, Inc. ML16358A4442017-01-11011 January 2017 Relief from the Requirements of the ASME Code Regarding Alternate IP3-RR-10 to the Full Circumferential Inspection Requirement of Code Case N-513-3 ML16215A2432016-11-15015 November 2016 Issuance of Amendment Nos. 285 and 261 Conditional Exemption from End-of-Life Moderator Temperature Coefficient ML16179A1782016-09-14014 September 2016 Safety Evaluation for Relief Request IP2-ISI-RR-01, Examination of Upper Pressurizer Welds ML16251A6202016-09-13013 September 2016 Entergy Fleet Request for Approval of Change to the Entergy Quality Assurance Program Manual (CAC Nos. MF7086 - MF7097) ML16167A0812016-07-15015 July 2016 Request for Alternative IP2-ISI-RR-03 to Weld Reference System Examination Required by ASME Code Subarticle IWA-2600 ML16147A5192016-07-14014 July 2016 Safety Evaluation for Relief Request IP2-ISI-RR-02 Alternative Examination Volume Required by Code Case N-729-1 ML16096A2692016-06-0606 June 2016 Arkansas; Grand Gulf; James A. Fitzpatrick; Indian Point; Palisades; Pilgrim; River Bend; and Waterford - Relief Request RR-EN-15-2, Proposed Alternative to Use ASME Boiler and Pressure Vessel Code Case N-786-1 ML16093A0282016-05-31031 May 2016 Entergy Services, Inc., Proposed Alternative to Utilize ASME Code Case N-789-1, Relief Request RR-EN-15-1, Revision 1 ML16064A2152016-04-12012 April 2016 Issuance of Amendments Cyber Security Plan Implementation Schedule 2023-05-01
[Table view] |
Text
June 6, 2003 Mr. Michael R. Kansler, President Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601
SUBJECT:
INSERVICE TESTING PROGRAM RELIEF REQUEST NO. 46 REGARDING RELIEF VALVE TESTING REQUIREMENTS, INDIAN POINT NUCLEAR GENERATING UNIT NO. 2 (TAC NO. MB7993)
Dear Mr. Kansler:
In a letter dated March 11, 2003, Entergy Nuclear Operations, Inc. (ENO), submitted Relief Request No. 46 for Indian Point Nuclear Generating Unit No. 2 (IP2). Relief was requested from the requirements of Section XI, Rules for Inservice Inspection of Nuclear Power Plant Components, of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code) for the Inservice Testing (IST) Program. Specifically, ENO requested a one-time relief from the requirement in Part 1 of the ASME OM Code, Code for Operation and Maintenance of Nuclear Power Plants, 1987 Edition (OM-1 Code), to test a minimum of 20% of Class 2 pressure relief valves within any 48 months. On the basis of this requirement, ENO should have tested one reactor coolant pump (RCP) thermal barrier outlet pressure relief valve during refueling outage 2R15 that ended in November 2002. Since these valves can only be tested when the reactor coolant pumps are not in service, ENO requested to perform the test during the next refueling outage (2R16), currently scheduled for October 2004.
The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the proposed request for one-time relief against the requirements of the 1987 Edition of the OM-1 Code. The results are provided in the enclosed safety evaluation.
The NRC staff finds that compliance with the OM-1 Code requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
Additionally, the licensees proposed alternative provides reasonable assurance that the IP2 RCP thermal barrier outlet pressure relief valves will perform their intended safety function.
Therefore, the NRC staff concludes that the proposed alternative to the IST requirements of the ASME Code is authorized, pursuant to 10 CFR 50.55a(a)(3)(ii), for IP2 until the next refueling outage, currently scheduled for October 2004.
M. Kansler This completes the actions under TAC No. MB7993. If you should have any questions, please contact Patrick Milano, Sr. Project Manager, at 301-415-1457.
Sincerely,
/RA/
Richard J. Laufer, Chief, Section 1 Project Directorate 1 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-247
Enclosure:
Safety Evaluation cc w/encl: See next page
M. Kansler This completes the actions under TAC No. MB7993. If you should have any questions, please contact Patrick Milano, Sr. Project Manager, at 301-415-1457.
Sincerely,
/RA/
Richard J. Laufer, Chief, Section 1 Project Directorate 1 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-247
Enclosure:
Safety Evaluation cc w/encl: See next page DISTRIBUTION:
PUBLIC PDI-1 Reading C. Holden R. Laufer D. Terao C. Hammer P. Milano B. Platchek, R-I S. Little G. Hill (2)
OGC J. Jolicoeur, EDO ACRS ACCESSION Number: ML031570139 OFFICE PDI-1:PM PDI-1:LA EMEB:SC OGC PDI-1:SC NAME PMilano SLittle DTerao RHoefling RLaufer DATE 5/28/03 6/5/03 5/29/03 6/4/03 6/6/03 OFFICIAL RECORD COPY
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO REQUEST FOR RELIEF REGARDING INSERVICE TESTING OF REACTOR COOLANT PUMP THERMAL BARRIER OUTLET RELIEF VALVES INDIAN POINT NUCLEAR GENERATING UNIT NO. 2 DOCKET NO. 50-247
1.0 INTRODUCTION
In a letter dated March 11, 2003, Entergy Nuclear Operations, Inc. (the licensee), submitted a request for relief from certain requirements in the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code) for the Indian Point Nuclear Generating Unit No. 2 (IP2). In its Inservice Testing (IST) Relief Request No. 46, the licensee requested the one-time relief from the requirements pertaining to testing of the reactor coolant pump (RCP) thermal barrier outlet pressure relief valves.
The affected components are the following RCP thermal barrier outlet pressure relief valves:
IST Relief Valve Group 21, Relief Valve Nos.: 783A, 783B, 783C, and 783D These valves are one-inch, Category C, RCP thermal barrier outlet relief valves which open to provide an over-pressure protection path for Containment Penetration O. The valves are installed in the component cooling water lines downstream from each RCP to protect the downstream piping from over-pressure. The licensee states that this over-pressure condition could occur when cooling water return lines from the RCPs are isolated during accident conditions. The set pressure for these relief valves is 2485 psig.
2.0 REGULATORY EVALUATION
Section 50.55a of Part 50 to Title 10 of the Code of Federal Regulations (10 CFR 50.55a) requires that the IST of certain ASME Code, Class 1, 2 and 3 pumps and valves be performed in accordance with Section XI of the ASME Code and applicable addenda, except where relief has been requested and granted or proposed alternatives have been authorized by the Commission pursuant to 10 CFR 50.55a(f)(6)(i), (a)(3)(i), or (a)(3)(ii). In proposing alternatives or requesting relief, the licensee must demonstrate that: (1) conformance is impractical for its facility; (2) the proposed alternative provides an acceptable level of quality and safety; or (3) compliance would result in a hardship or unusual difficulty without a compensating increase in the level of quality and safety. Pursuant to 10 CFR 50.55a, the Commission may authorize alternatives or grant relief from ASME Code requirements upon making the necessary findings.
NRC guidance contained in Generic Letter (GL) 89-04, Guidance on Developing Acceptable Enclosure
Inservice Testing Programs, provides alternatives to the ASME Code requirements that are acceptable to the NRC staff. Further guidance is given in GL 89-04, Supplement 1, and NUREG-1482, Guidelines for Inservice Testing at Nuclear Power Plants.
For IP2, the regulations in 10 CFR 50.55a require that the IST program meets the requirements of the 1989 Edition of the ASME Code,Section XI, which references the Operation and Maintenance (OM) standard, OM-1987, Part 1 (OM-1). Specifically, OM-1, Section 1.3.4.1(b) states, All valves of each type and manufacture shall be tested within each subsequent 10-year interval, with a minimum of 20% of the valves tested within any 48 months. The licensee seeks one-time relief from the OM-1, Section 1.3.4.1(b) requirement, as described below.
3.0 TECHNICAL EVALUATION
3.1 Licensees Basis for Relief The licensee provided the following basis for the requested relief:
One valve (783A) from IST Relief Valve Group 21 (Valves 783A, 783B, 783C, 783D) was tested in June 1998. The next valve should have been tested within 48 months (June 2002) to meet the code frequency requirement. This surveillance, which can only be performed in an outage where the cooling water flow to the RCP thermal barrier can be secured, was not performed within the 48 month period. The purpose of this relief is to extend the surveillance to 76 months to coincide with the next scheduled refueling outage. This one-time extension of relief valve testing is acceptable for the following reasons:
- 1. A review of the as-found setpoint test history for these valves at both Indian Point Units 2 and 3 demonstrates proven relief pressure reliability.
There have been 7 setpoint tests performed in the history of the plants with only one setpoint test failure. For the one failure, the valve failed to lift within the required range (2411-2559 psig). This test occurred in May 1997 after approximately 20 years of plant operation. The valve was subsequently refurbished and successfully retested. The proposed one-time extension of the test frequency from 48 months to 76 months is not expected to affect the proven relief pressure reliability of these valves.
No corrective maintenance work orders were found in the history files for the subject valves.
- 2. These four (4) reactor coolant pump thermal barrier cooling outlet relief valves were added to the inservice testing program scope in 1998 in response to NRC Generic Letter 96-06 evaluations regarding overpressure protection of piping penetrating containment. Operation of any one of the four valves would perform the function of depressurizing the thermal barrier cooling water piping inside containment. Prior to that, these original plant design valves were not tested because they had no
identified safety function under OM-l0, 1.1, Scope. The same valves serve a similar function at Indian Point Unit 3.
Given the proven test reliability and redundancy for these relief valves, there is no compensating increase in the level of quality and safety gained by requiring the plant to shutdown to perform a relief valve test.
3.2 Proposed Alternative Testing As an alternative to the above requirement described OM-1, Section 1.3.4.1(b), the licensee proposed to test one untested valve from IST Relief Valve Group 21 at the next opportunity, but no later than refueling outage 2R16, currently scheduled for October 2004.
3.3 Evaluation The staff has reviewed the licensees alternative and finds that performing the testing required by OM-1, Section 1.3.4.1(b) would result in unusual hardship without a compensating increase in quality or safety. The requirement to test 20% of the valves within any 48-month would necessitate that the plant be shut down so that the cooling water flow through the RCP thermal barrier could be secured. The proposed period of additional time (i.e., from when these valves were required to be tested to meet OM-1 requirements until the next outage in October 2004) is approximately 28 months. In reviewing the licensee's operating experience with these valves and general industry experience with similar valves, significant additional degradation of these components would not be expected to occur during this additional period. Furthermore, there is reasonable assurance that the thermal barrier cooling water piping system would be protected from over-pressurization because any one of the four valves would perform this function. It is also noted that all of the relief valves in this IST group will be tested within the 10-year period, as required by OM-1. Therefore, the staff finds that the licensees alternative to perform the testing of these valves during the next opportunity, but no later than refueling outage 2R16, currently scheduled for October 2004, provides reasonable assurance of operational readiness.
4.0 CONCLUSION
The staff concludes that compliance with these requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
Additionally, the licensees proposed testing provides reasonable assurance that the IP2 RCP thermal barrier outlet pressure relief valves will perform their intended safety function.
Therefore, pursuant to 10 CFR 50.55a(a)(3)(ii), the staff authorizes the licensee's request for a one-time relief from the ASME Code testing requirements as an alternative to the testing interval in ASME Code, OM-1.
Principal Contributor: C. Hammer Date: June 6, 2003
Indian Point Nuclear Generating Station Unit 2 Mr. Gary Taylor White Plains, NY 10601 Chief Executive Officer Entergy Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213 Mr. John Herron Senior Vice President and Chief Operating Officer Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Fred Dacimo Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 295 Broadway, Suite 2 P.O. Box 249 Buchanan, NY 10511-0249 Mr. Christopher Schwarz General Manager, Plant Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 295 Broadway, Suite 2 P.O. Box 249 Buchanan, NY 10511-0249 Mr. Dan Pace Vice President Engineering Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Randall Edington Vice President Operations Support Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. John Kelly Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.
440 Hamilton Avenue
Indian Point Nuclear Generating Station Unit 2 Ms. Charlene Faison Manager, Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Director of Oversight Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. James Comiotes Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.
Indian Point Energy Center 295 Broadway, Suite 2 P.O. Box 249 Buchanan, NY 10511-0249 Mr. John McCann Manager, Licensing Entergy Nuclear Operations, Inc.
Indian Point Energy Center 295 Broadway, Suite 2 P. O. Box 249 Buchanan, NY 10511-0249 Mr. John M. Fulton Assistant General Counsel Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Senior Resident Inspector, Indian Point 2 U. S. Nuclear Regulatory Commission 295 Broadway, Suite 1 P.O. Box 38 Buchanan, NY 10511-0038
Indian Point Nuclear Generating Station Unit 2 Mr. Peter R. Smith, Acting President Mr. William DiProfio New York State Energy, Research, and PWR SRC ConsultaNT Development Authority 139 Depot Road Corporate Plaza West East Kingston, NH 03827 286 Washington Avenue Extension Albany, NY 12203-6399 Mr. Dan C. Poole PWR SRC Consultant Mr. J. Spath, Program Director 20 Captains Cove Road New York State Energy, Research, and Inglis, FL 34449 Development Authority 17 Columbia Circle Mr. William T. Russell Albany, NY 12203-6399 PWR SRC Consultant 400 Plantation Lane Mr. Paul Eddy Stevensville, MD 21666-3232 Electric Division New York State Department Alex Matthiessen of Public Service Executive Director 3 Empire State Plaza, 10th Floor Riverkeeper, Inc.
Albany, NY 12223 25 Wing & Wing Garrison, NY 10524 Mr. Charles Donaldson, Esquire Assistant Attorney General Paul Leventhal New York Department of Law The Nuclear Control Institute 120 Broadway 1000 Connecticut Avenue NW New York, NY 10271 Suite 410 Washington, DC, 20036 Mayor, Village of Buchanan 236 Tate Avenue Karl Copeland Buchanan, NY 10511 Pace Environmental Litigation Clinic 78 No. Broadway Mr. Ray Albanese White Plains, NY 10603 Executive Chair Four County Nuclear Safety Committee Jim Riccio Westchester County Fire Training Center Greenpeace 4 Dana Road 702 H Street, NW Valhalla, NY 10592 Suite 300 Washington, DC 20001 Ms. Stacey Lousteau Treasury Department Entergy Services, Inc.