MONTHYEARML1104505832011-02-10010 February 2011 Units 1 & 2 - Request for Exemption from Certain Requirements of the Fitness for Duty Rule for Managing Fatigue Project stage: Request ML1107404422011-03-10010 March 2011 Unit 1 & 2, Requests for Exemption from Certain Requirements of the Fitness for Duty Rule for Managing Fatigue, Severe Weather Response Procedures Project stage: Other ML1114702652011-05-26026 May 2011 Stations, Units 1 and 2 - Request for Exemption from Certain Requirements of the Fitness for Duty Rule for Managing Fatigue Project stage: Request ML11137A2072011-08-11011 August 2011 Environmental Assessment and Finding of No Significant Impact Project stage: Other ML11236A2142011-08-25025 August 2011 Environmental Assessment and Finding of No Significant Impact Project stage: Other ML11236A2132011-08-25025 August 2011 Environmental Assessment and Finding of No Significant Impact Project stage: Other ML11235A8532011-09-13013 September 2011 Federal Register Notice, Exemption Project stage: Other ML11235A8522011-09-13013 September 2011 Letter, Request for Exemption from Certain Requirements of 10 CFR 26.205(C) and (D) Work Hour Controls During Periods Immediately Prior and Subsequent to Severe Wind Conditions Project stage: Approval NRC-2011-0185, Federal Register Notice, Exemption2011-09-13013 September 2011 Federal Register Notice, Exemption Project stage: Other ML11228A0202011-09-20020 September 2011 Exemption from Part 26, Severe Weather Project stage: Approval ML11220A0112011-09-20020 September 2011 Exemption from the Requirements of 10 CFR, Part 26 Work Hour Controls During Periods of Severe Weather Conditions Project stage: Approval 2011-08-11
[Table View] |
|
---|
Category:Federal Register Notice
MONTHYEARML24215A2662024-09-0404 September 2024 SLR - FRN for SLR ML24208A0202024-07-26026 July 2024 Final Environmental Impact Statement - Notice of Availability Federal Register Notice ML24114A3102024-05-0303 May 2024 Monthly (28-Day) Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 14, 2024 ML24086A4312024-04-0505 April 2024 Monthly (28-day) Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: April 16, 2024 ML24067A0372024-03-20020 March 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - February 2024 ML22294A1892022-11-0808 November 2022 Federal Register Notice - Notice of Intent to Prepare EIS and to Conduct EIS Scoping for North Anna Power Station ML21222A1632021-08-19019 August 2021 Subsequent License Renewal Draft SEIS NOA FRN ML21153A2112021-07-0707 July 2021 Individual Notice of Consideration of Issuance of Amendment(S) to (Renewed) Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, Opportunity for Hearing (EPID L-2021-LLA-0082) LTR ML21153A2122021-07-0707 July 2021 Individual Notice of Consideration of Issuance of Amendment(S) to (Renewed) Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, Opportunity for Hearing (EPID L-2021-LLA-0082)FRN ML20091L9792021-05-0404 May 2021 Federal Register Notice ML20274A1982020-10-19019 October 2020 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process (EPID No. L-2020-SLE-0000) - Federal Register Notice ML20271A0002020-10-13013 October 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for September 2020 ML20252A0042020-09-23023 September 2020 Request for Relief Request Fifth 10-Year Interval ML20224A1052020-09-17017 September 2020 SLRA - Receipt and Availability Letter ML20177A6452020-07-15015 July 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for June 2020 ML20099E4212020-04-21021 April 2020 Federal Register Notice for Part 73 Exemption ML20105A4652020-04-16016 April 2020 Virginia Electric and Power Company; Surry Power Station, Unit 2 - Federal Register Notice ML20071D3662020-04-0606 April 2020 Federal Register Notice - Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 ML19220A0652019-10-17017 October 2019 Federal Register Notice - Surry Power Station Unit Nos 1 and 2 Notice of Availability of Surry SLR Draft SEIS ML19169A2612019-07-31031 July 2019 Federal Register Notice: Virginia Electric and Power Company, Dominion Energy Kewaunee, Inc. and Dominion Nuclear Connecticut, Inc. North Anna ISFSI: Environmental Assessment and Finding of No Significant Impact; Issuance ML19168A0842019-06-26026 June 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 07/02/2019 ML18340A2672018-12-17017 December 2018 Federal Register Notice - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 ML18345A2442018-12-12012 December 2018 Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent Lice NRC-2018-0247, Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent2018-12-12012 December 2018 Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent Lice ML18320A2352018-12-0303 December 2018 Acceptance Scheduling and Opportunity for Hearing FRN - v2 ML18297A0942018-10-26026 October 2018 Federal Register Notice - Receipt and Availability of the Subsequent License Renewal Application for the Surry Power Station, Unit Nos 1 and 2 ML18278A2802018-10-10010 October 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 10/23/2018 ML18173A1792018-08-0707 August 2018 OEDO-17-00070 - Notice of Issuance of Director'S Decision, 2.206 Petition for Emergency Enforcement Action Per 10 CFR 2.206 at Listed U.S. Reactors with Forged Components and Parts Manufactured at France'S AREVA-Le Creusot Forge and Japan C ML18127B7232018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 NRC-2018-0096, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 20182018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 ML18036B1302018-02-12012 February 2018 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: March 6, 20 ML18031A2312018-02-0808 February 2018 Federal Register Notice - Notice of Issuance for License Renewal (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) ML17312A6062018-01-29029 January 2018 Federal Register Notice for the Final Environmental Assessment for the North Anna ISFSI License Renewal NRC-2015-0237, Enclosufederal Register Notice-Notice of Issuance of Amendment Request to Materials License No. SNM-25072017-09-13013 September 2017 Enclosufederal Register Notice-Notice of Issuance of Amendment Request to Materials License No. SNM-2507 ML17236A2102017-09-13013 September 2017 Enclosufederal Register Notice-Notice of Issuance of Amendment Request to Materials License No. SNM-2507 ML17200A0652017-08-30030 August 2017 OEDO-17-00070 - Acknowledgement FRN, Paul Gunter, Beyond Nuclear, 2.206 Petition for Emergency Enforcement Action Per 10 CFR 2.206 at Listed U.S. Reactors with Forged Components and Parts Manufactured at France'S AREVA-Le Creusot Forge and ML17198A3292017-08-30030 August 2017 OEDO-17-00070 - Acknowledgement Letter, Paul Gunter, Beyond Nuclear, Petition for Emergency Enforcement Action Per 10 CFR 2.206 at Listed U.S. Reactors with Forged Components and Parts Manufactured at France'S AREVA-Le Creusot Forge and Jap ML17213A1842017-08-0404 August 2017 Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 2017 NRC-2017-0175, Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 20172017-08-0404 August 2017 Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 2017 ML16271A0922016-09-28028 September 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: October 11, 2016 ML16228A3192016-08-16016 August 2016 Federal Register Notice Correction Use of Areva'S M5 Alloy Fuel Rod Clodding Material NRC-2016-0105, Federal Register Notice Correction Use of Areva'S M5 Alloy Fuel Rod Clodding Material2016-08-16016 August 2016 Federal Register Notice Correction Use of Areva'S M5 Alloy Fuel Rod Clodding Material ML16195A5252016-07-27027 July 2016 Exemption Notice for Fr - Surry Power Station, Unit Nos. 1 and 2, Use of M5 Advanced Zirconium Fuel Cladding ML16195A5162016-07-27027 July 2016 Exemption for Use of M5 Advanced Zirconium Fuel Cladding from the Requirements of 10 CFR Part 50, Section 50.46 ML16124B1542016-05-23023 May 2016 Draft Environmental Assessment Fr Notice ML16061A3012016-03-0202 March 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: March 15, 2016 ML15293A4542015-10-30030 October 2015 Revised Director'S Decision Letter (G20110757) NRC-2012-0258, Unit 2 - Federal Register Notice Director'S Decision 15-092015-10-30030 October 2015 Unit 2 - Federal Register Notice Director'S Decision 15-09 ML15293A4892015-10-30030 October 2015 Unit 2 - Federal Register Notice Director'S Decision 15-09 ML15176A6282015-08-21021 August 2015 G20110757 - Petition Federal Register Notice (Enclosure 2) 2024-09-04
[Table view] |
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[NRC-2011-0185]
Virginia Electric and Power Company Docket Nos. 50-338 and 50-339, North Anna Power Station, Unit Nos. 1 and 2 Docket Nos. 50-280 and 50-281, Surry Power Station, Unit Nos. 1 and 2 Environmental Assessment and Finding of No Significant Impact The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an exemption from Title 10 of the Code of Federal Regulations (10 CFR) Part 26, Fitness for Duty Programs, for Facility Operating License Nos. NPF-4 and NPF-7, issued to Virginia Electric Power Company (the licensee), for operation of the North Anna Power Station (NAPS) Unit Nos.
1 and 2, located in Louisa County, Virginia; and Facility Operating License Nos. DPR-32 and DPR-37, issued to the licensee, for operation of the Surry Power Station, Unit Nos. 1 and 2, located in Surry County, Virginia. Therefore, as required by 10 CFR 51.21, the NRC performed an environmental assessment. Based on the results of the environmental assessment, the NRC is issuing a finding of no significant impact.
ENVIRONMENTAL ASSESSMENT Identification of the Proposed Action:
The proposed action would provide exemption from the work hour control requirements of 10 CFR 26.205(c) and (d) during declarations of severe weather conditions involving tropical storm or hurricane force winds.
The proposed action is in accordance with the licensee=s application dated February 10, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No.
ML110450583), as supplemented by letters dated March 10, 2011 (ADAMS Accession No. ML110740442) and May 26, 2011 (ADAMS Accession No. ML111470265).
The Need for the Proposed Action:
The proposed action extends the exception provided by 10 CFR 26.207(d) to include pre-defined entry and exit conditions related to hurricane events because the sequestering of plant personnel and related staff resource limitations may occur at times prior to and following the current entry and exit conditions (i.e., emergency declaration) specified in 10 CFR 26.207(d). Entry into a severe weather situation involving tropical storm or hurricane force winds can impose conditions similar to entry into the site emergency plan where the imposition of work hour controls on vital personnel could impede the ability to focus on plant safety and security, and may be detrimental to the health and safety of the public.
Environmental Impacts of the Proposed Action:
The NRC has completed its environmental assessment of the proposed action and concludes that extending the exception provided by 10 CFR 26.207(d) to include pre-defined entry and exit conditions related to hurricane events would not significantly affect plant safety, as it does not change the Technical Specification-required shift staffing. Additionally, the time from entry into the condition in which the work hour control exemption applies, to exiting the condition, is limited to severe weather situations involving tropical storm or hurricane force winds. The licensee states that the Hurricane Response Plan (Nuclear) and other plant-specific procedures ensure that adequate resources and guidance are in place to prepare for, respond to, and recover from severe weather conditions associated with tropical storm or hurricane force winds.
The proposed action will not significantly increase the probability or consequences of accidents. The proposed action would not result in an increased radiological hazard beyond those previously analyzed in the Final Safety Analysis Report. No changes are being made in
the types of effluents that may be released offsite. There is no significant increase in the amount of any effluent released offsite. There is no significant increase in occupational or public radiation exposure. No changes will be made to plant buildings or site property.
Therefore, there are no significant radiological environmental impacts associated with the proposed action.
The proposed action does not result in changes to land use or water use, or result in changes to the quality or quantity of non-radiological effluents. No changes to the National Pollution Discharge Elimination System permits are needed. No effects on the aquatic or terrestrial habitat in the vicinity of the plant, or to threatened, endangered, or protected species under the Endangered Species Act, or impacts to fish habitat covered by the Magnusen-Stevens Act are expected. There are no impacts to the air or ambient air quality. There are no impacts to historical or cultural resources. There would be no noticeable effect on socioeconomic conditions in the region. Therefore, no changes or different types of non-radiological environmental impacts are proposed as a result of the proposed action.
Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action.
Environmental Impacts of the Alternatives to the Proposed Action:
As an alternative to the proposed action, the staff considered denial of the proposed action (i.e., the Ano-action@ alternative). Denial of the application would result in no change in current environmental impacts. Other alternatives to the proposed action include entry and exit conditions, other than those proposed by the licensee, which would change the duration in which the exemption is effective. The staff concludes that these alternatives would not have a significant impact. The environmental impacts of the proposed action and the alternative actions are similar.
Alternative Use of Resources:
The action does not involve the use of any different resources than those previously considered in the Final Environmental Statement Related to the Continuation of Construction and the Operation for NAPS dated April 1973, and Surry dated May 1972 and June 1972, respectively, as supplemented through NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplements 6 and 7, dated November 2002.
Agencies and Persons Consulted:
In accordance with its stated policy, on May 12, 2011, the staff consulted with the Virginia State official, Leslie Foldesi of the Department of Health, regarding the environmental impact of the proposed action. The State official had no comments.
FINDING OF NO SIGNIFICANT IMPACT On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action.
For further details with respect to the proposed action, see the licensee=s letter dated February 10, 2011, as supplemented by letters dated March 10 and May 26, 2011. Documents may be examined, and/or copied for a fee, at the NRC=s Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available documents created or received at the NRC in the Agencywide Documents Access and Management System (ADAMS) are available online in the NRC Library at http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the
NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or send an e-mail to pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 25th day of August 2011.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Robert E. Martin, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation