MONTHYEARML15282A0362015-09-30030 September 2015 Exemption for Use of M5 Advanced Zirconium Fuel Cladding and Approval Request for Application of Supporting Analysis Methods Project stage: Request ML16124B1542016-05-23023 May 2016 Draft Environmental Assessment Fr Notice Project stage: Draft Other ML16124B1492016-05-23023 May 2016 Draft Environmental Assessment and Finding of No Significant Impact Related to the Use of M5 Advanced Zirconium Fuel Cladding Material Project stage: Draft Other ML16195A5252016-07-27027 July 2016 Exemption Notice for Fr - Surry Power Station, Unit Nos. 1 and 2, Use of M5 Advanced Zirconium Fuel Cladding Project stage: Other ML16195A5162016-07-27027 July 2016 Exemption for Use of M5 Advanced Zirconium Fuel Cladding from the Requirements of 10 CFR Part 50, Section 50.46 Project stage: Other 2016-05-23
[Table View] |
Similar Documents at Surry |
---|
Category:Exemption from NRC Requirements
MONTHYEARML20339A6452020-12-14014 December 2020 Exemption from Annual Force-on-Force Exercise Requirement of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Subsection VI.C.3(I)(1) (EPID L-2020-LLE-0226 (COVID-19)) ML20271A0002020-10-13013 October 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for September 2020 ML20241A0002020-09-16016 September 2020 Temporary Exemption from Certain Requirements of 10 CFR Part 73 Appendix B, General Criteria for Security Personnel, Section VI (EPID L-2020-LLE-0137 (COVID-19)) ML20098E5722020-04-0909 April 2020 Exemption to 10 CFR Part 73, Appendix B, Section VI.C.2, Subsections (a) and (B) ML20098E6902020-04-0909 April 2020 Exemption Request from the Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel ML16195A5162016-07-27027 July 2016 Exemption for Use of M5 Advanced Zirconium Fuel Cladding from the Requirements of 10 CFR Part 50, Section 50.46 ML16195A5252016-07-27027 July 2016 Exemption Notice for Fr - Surry Power Station, Unit Nos. 1 and 2, Use of M5 Advanced Zirconium Fuel Cladding ML1210404302012-04-12012 April 2012 Ltr. to L. N. Hartz Exemption from Parts of 10 CFR 72.212 - Storage of the Nuhoms Hd Dry Shielded Canisters at Surry Power Station Independent Spent Fuel Storage Installation NRC-2011-0185, Federal Register Notice, Exemption2011-09-13013 September 2011 Federal Register Notice, Exemption ML11235A8522011-09-13013 September 2011 Letter, Request for Exemption from Certain Requirements of 10 CFR 26.205(C) and (D) Work Hour Controls During Periods Immediately Prior and Subsequent to Severe Wind Conditions ML11235A8532011-09-13013 September 2011 Federal Register Notice, Exemption ML0934802022009-12-0707 December 2009 Request for Exemption from 10 CFR 73.55 Power Reactor Security Requirements Final Rule ML0711602872007-06-27027 June 2007 Exemption from the Requirements of 10 CFR Part 50, Appendix G and 10 CFR Part 50 Sec. 50.61 ML0530700052005-12-0909 December 2005 Exemption from the Requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.b and C ML0504603162005-02-0707 February 2005 VEPCO, Surry Power Station, Units 1 and 2 - Withdrawal of Exemption Request for Alternate Material Properties Basis Per 10 CFR 50.60(b) ML0222101752002-09-16016 September 2002 Isfsis, Exemption from Requirements of 10 CFR Part 40, Section 40.64(b) - Foreign Origin Source Material Inventory ML19094A2291998-07-0909 July 1998 Environmental Assessment & Finding of No Significant Impact 2020-09-16
[Table view] Category:Federal Register Notice
MONTHYEARML20091L9792021-05-0404 May 2021 Federal Register Notice ML20271A0002020-10-13013 October 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for September 2020 ML20099E4212020-04-21021 April 2020 Federal Register Notice for Part 73 Exemption ML20105A4652020-04-16016 April 2020 Virginia Electric and Power Company; Surry Power Station, Unit 2 - Federal Register Notice ML20071D3662020-04-0606 April 2020 Federal Register Notice - Virginia Electric and Power Company; Dominion Energy Virginia: Surry Power Station, Unit Nos. 1 and 2 ML19220A0652019-10-17017 October 2019 Federal Register Notice - Surry Power Station Unit Nos 1 and 2 Notice of Availability of Surry SLR Draft SEIS ML19168A0842019-06-26026 June 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 07/02/2019 ML18340A2672018-12-17017 December 2018 Federal Register Notice - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Surry Power Station, Unit Nos. 1 and 2 ML18345A2442018-12-12012 December 2018 Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent Lice NRC-2018-0247, Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent2018-12-12012 December 2018 Federal Register Notice - Surry Power Station, Unit Nos. 1 and 2 - Correction and Extension of Date to Request a Hearing and Petition for Leave to Intervene Regarding the Virginia Electric and Power Company'S Application for Subsequent Lice ML18320A2352018-12-0303 December 2018 Acceptance Scheduling and Opportunity for Hearing FRN - v2 ML18297A0942018-10-26026 October 2018 Federal Register Notice - Receipt and Availability of the Subsequent License Renewal Application for the Surry Power Station, Unit Nos 1 and 2 ML18278A2802018-10-10010 October 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 10/23/2018 ML18173A1792018-08-0707 August 2018 OEDO-17-00070 - Notice of Issuance of Director'S Decision, 2.206 Petition for Emergency Enforcement Action Per 10 CFR 2.206 at Listed U.S. Reactors with Forged Components and Parts Manufactured at France'S AREVA-Le Creusot Forge and Japan C NRC-2018-0096, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 20182018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 ML18127B7232018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 ML17198A3292017-08-30030 August 2017 OEDO-17-00070 - Acknowledgement Letter, Paul Gunter, Beyond Nuclear, Petition for Emergency Enforcement Action Per 10 CFR 2.206 at Listed U.S. Reactors with Forged Components and Parts Manufactured at France'S AREVA-Le Creusot Forge and Jap ML17200A0652017-08-30030 August 2017 OEDO-17-00070 - Acknowledgement FRN, Paul Gunter, Beyond Nuclear, 2.206 Petition for Emergency Enforcement Action Per 10 CFR 2.206 at Listed U.S. Reactors with Forged Components and Parts Manufactured at France'S AREVA-Le Creusot Forge and ML17213A1842017-08-0404 August 2017 Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 2017 NRC-2017-0175, Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 20172017-08-0404 August 2017 Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 2017 ML16271A0922016-09-28028 September 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: October 11, 2016 NRC-2016-0105, Federal Register Notice Correction Use of Areva'S M5 Alloy Fuel Rod Clodding Material2016-08-16016 August 2016 Federal Register Notice Correction Use of Areva'S M5 Alloy Fuel Rod Clodding Material ML16228A3192016-08-16016 August 2016 Federal Register Notice Correction Use of Areva'S M5 Alloy Fuel Rod Clodding Material ML16195A5252016-07-27027 July 2016 Exemption Notice for Fr - Surry Power Station, Unit Nos. 1 and 2, Use of M5 Advanced Zirconium Fuel Cladding ML16195A5162016-07-27027 July 2016 Exemption for Use of M5 Advanced Zirconium Fuel Cladding from the Requirements of 10 CFR Part 50, Section 50.46 ML16124B1542016-05-23023 May 2016 Draft Environmental Assessment Fr Notice ML15120A2272015-05-0101 May 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 12, 2015 NRC-2014-0193, Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 20142014-08-22022 August 2014 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 2014 ML14233A2082014-08-22022 August 2014 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 2014 ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit ML13228A3992013-08-12012 August 2013 Letter to Holders of Independent Spent Fuel Storage Installation (ISFSI) Licenses Re Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit - Rin 3150-AI64 (NRC-2009-0163) EA-02-109 NRC-2013-0172, Units 1 and 2 - FRN - Environmental Assessment and Finding of No Significant Impact (TAC Nos. ME9753, ME9754, ME9755, and ME9756)2013-07-24024 July 2013 Units 1 and 2 - FRN - Environmental Assessment and Finding of No Significant Impact (TAC Nos. ME9753, ME9754, ME9755, and ME9756) ML13205A2192013-07-24024 July 2013 Environmental Assessment and Finding of No Significant Impact ML13205A2232013-07-24024 July 2013 FRN - Environmental Assessment and Finding of No Significant Impact NRC-2012-0241, Units 1 and 2 - Federal Register Notice - Withdrawal of Amendment (TAC Nos. ME7814, ME7815, ME7816, and ME7817)2012-10-10010 October 2012 Units 1 and 2 - Federal Register Notice - Withdrawal of Amendment (TAC Nos. ME7814, ME7815, ME7816, and ME7817) ML12277A3732012-10-10010 October 2012 Federal Register Notice - Withdrawal of Amendment ML12277A3662012-10-10010 October 2012 Withdrawal of Amendment ML12056A0442012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status2012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML11264A0972011-10-24024 October 2011 Letter, Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed Nshcd, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI ML11264A0982011-10-19019 October 2011 Federal Register Notice - Notice of Consideration NRC-2011-0242, Federal Register Notice - Notice of Consideration2011-10-19019 October 2011 Federal Register Notice - Notice of Consideration NRC-2011-0230, FRN: General Notice. Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations2011-09-22022 September 2011 FRN: General Notice. Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations ML1126504892011-09-22022 September 2011 FRN: General Notice. Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations NRC-2011-0185, Federal Register Notice, Exemption2011-09-13013 September 2011 Federal Register Notice, Exemption ML11235A8522011-09-13013 September 2011 Letter, Request for Exemption from Certain Requirements of 10 CFR 26.205(C) and (D) Work Hour Controls During Periods Immediately Prior and Subsequent to Severe Wind Conditions ML11235A8532011-09-13013 September 2011 Federal Register Notice, Exemption ML11236A2132011-08-25025 August 2011 Environmental Assessment and Finding of No Significant Impact ML11236A2142011-08-25025 August 2011 Environmental Assessment and Finding of No Significant Impact NRC-2011-0187, Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/20112011-08-11011 August 2011 Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/2011 2021-05-04
[Table view] |
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-280 and 50-281 NRC-2016-0105]
Virginia Electric Power Company; Surry Power Station, Unit Nos. 1 and 2; Use of AREVAs M5 Alloy Fuel Rod Cladding Material AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption; issuance.
SUMMARY
- The U.S. Nuclear Regulatory Commission (NRC) is issuing an exemption in response to a September 30, 2016, request from Virginia Electric Power Company (Dominion or the licensee) in order to use AREVAs M5 alloy fuel rod cladding material at Surry Power Station, Unit Nos. 1 and 2 (SPS).
DATE: The exemption was issued on July 27, 2016.
ADDRESSES: Please refer to Docket ID NRC-2016-0105 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:
- Federal Rulemaking Web Site: Go to http://www.regulations.gov and search for Docket ID: NRC-2016-0105. Address questions about NRC dockets to Carol Gallagher; telephone: 301-415-3463; e-mail: Carol.Gallagher@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
- NRCs Agencywide Documents Access and Management System (ADAMS):
You may obtain publicly-available documents online in the ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ADAMS Public Documents and then select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced in this document (if that document is available in ADAMS) is provided the first time that a document is referenced.
- NRCs PDR: You may examine and purchase copies of public documents at the NRCs PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Karen R. Cotton, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001; telephone:
301-415-1438, e-mail: Karen.Cotton@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Background Dominion is the holder of Facility Operating License Nos. DPR-32 and DPR-37, which authorize operation of SPS. The licenses provide, among other things, that the facility is subject to all rules, regulations, and orders of the NRC now or hereafter in effect.
The facility consists of two pressurized-water reactors (PWR) located in Surry County, Virginia.
2
II. Request/Action Pursuant to § 50.12 of title 10 of the Code of Federal Regulations (10 CFR), Specific exemptions, the licensee has requested, by letter dated September 30, 2015 (ADAMS Accession No. ML15282A036), an exemption from 10 CFR 50.46, Acceptance criteria for emergency core cooling systems [ECCS] for light-water nuclear power reactors, and 10 CFR part 50, appendix K, ECCS Evaluation Models, to allow the use of fuel rods clad with AREVAs M5 alloy. The regulations in 10 CFR 50.46 require that the calculated cooling performance following postulated loss-of-coolant accidents (LOCAs) at reactors fueled with zircaloy or ZIRLO' cladding conforms to the criteria set forth in 10 CFR 50.46(b). In addition, 10 CFR part 50, appendix K, requires, in part, that the Baker-Just equation be used to predict the rates of energy release, hydrogen concentration, and cladding oxidation from the metal/water reaction.
The Baker-Just equation assumes the use of zircaloy or ZIRLO' materials that have different chemical compositions from AREVAs M5 alloy. As written, these regulations presume only the use of zircaloy or ZIRLO' fuel rod cladding and do not contain provisions for use of fuel rods with other cladding materials. Therefore, an exemption from the requirements of 10 CFR 50.46 and 10 CFR part 50, appendix K, is needed to support the use of a different fuel cladding material. Accordingly, the licensee requested an exemption that would allow the use of fuel rods clad with AREVAs M5 alloy to be loaded into the SPS reactor cores as non-limiting lead test assemblies (LTAs) in up to eight locations.
III. Discussion Pursuant to 10 CFR 50.12, the Commission may, upon application by any interested person or upon its own initiative, grant exemptions from the requirements of 10 CFR part 50 3
when the exemptions are authorized by law, will not present an undue risk to public health or safety, and are consistent with the common defense and security. However, 10 CFR 50.12(a)(2) states that the Commission will not consider granting an exemption unless special circumstances are present as set forth in 10 CFR 50.12(a)(2). Under 10 CFR 50.12(a)(2)(ii),
special circumstances are present when application of the regulation in the particular circumstances would not serve, or is not necessary to achieve, the underlying purpose of the rule.
A. Special Circumstances Special circumstances, in accordance with 10 CFR 50.12(a)(2)(ii), are present whenever application of the regulation in the particular circumstances is not necessary to achieve the underlying purpose of the rule. The underlying purpose of 10 CFR 50.46 and 10 CFR part 50, appendix K, is to establish acceptance criteria for ECCS performance to provide reasonable assurance of safety in the event of a LOCA. The special circumstance that necessitates the request for exemption to 10 CFR 50.46 and 10 CFR 50, appendix K, is that neither of these regulations explicitly allows the use of AREVAs M5 alloy fuel rod cladding material. The ultimate objective of 10 CFR 50.46 is to ensure that nuclear power reactors fueled with uranium oxide pellets within zircaloy or ZIRLO' cladding must be provided with an ECCS that is designed to provide core cooling following a postulated LOCA. AREVA NP, in its NRC-approved Topical Report BAW-10227-A, Evaluation of Advanced Cladding and Structural Material (M5) in PWR Reactor Fuel, February 2000 (ADAMS Accession No. ML003686365),
has demonstrated that the effectiveness of the ECCS will not be affected by a change from zircaloy or ZIRLO' clad fuel to fuel rods clad with AREVAs M5 alloy. Normal reload safety analyses will confirm that there is no adverse impact on ECCS performance.
4
The objective of 10 CFR 50.46(b)(2) and (b)(3), and 10 CFR part 50, appendix K I.A.5, is to ensure that cladding oxidation and hydrogen generation are appropriately limited during a LOCA and conservatively accounted for in the ECCS evaluation model. Appendix K of 10 CFR part 50 requires that the Baker-Just equation be used in the ECCS evaluation model to determine the rate of energy release, cladding oxidation, and hydrogen generation. AREVA NP has shown in an appendix of Topical Report BAW-10227-A that the Baker-Just model is conservative in all post-LOCA scenarios with respect to the use of AREVAs M5 alloy fuel rod cladding material.
Based on the regulatory review of the exemption request, the NRC staff concludes that the intent of 10 CFR 50.46 and 10 CFR part 50, appendix K, will continue to be satisfied for the planned operation of SPS with AREVAs M5 alloy fuel rod cladding material used for non-limiting LTAs and the special circumstance required by 10 CFR 50.12(a)(2)(ii) for granting of an exemption exists.
B. Authorized by Law This exemption would allow the use of fuel rods clad with AREVAs M5 alloy in up to eight fuel assemblies at SPS. The regulations in 10 CFR 50.12 allow the NRC to grant exemptions from the requirements of 10 CFR part 50 provided that the exemptions are authorized by law. The NRC staff determined that special circumstances exist to grant the proposed exemption and that granting the exemption would not result in a violation of the Atomic Energy Act of 1954, as amended. Therefore, the exemption is authorized by law.
5
C. No Undue Risk to Public Health and Safety The provisions of 10 CFR 50.46 establish acceptance criteria for ECCS performance.
Topical Report BAW-10227-A contains the justification to use AREVAs M5 alloy fuel rod cladding material, a proprietary variant of Zr1Nb, to replace Zircaloy-4 in the construction of fuel assembly components such as fuel rod cladding, guide tubes, and spacer grids. This justification is required to support the request by Dominion for an exemption to 10 CFR 50.46 to permit the use of AREVAs M5 alloy fuel rod cladding material, in addition to Zircaloy-4 and ZIRLO'. AREVAs M5 alloy is an AREVA NP proprietary material composed of 1.0 percent niobium, 0.125 percent oxygen, and the balance zirconium. AREVAs M5 alloy fuel rod cladding provides improved performance in fuel cladding corrosion and hydrogen pickup.
An AREVA NP LOCA evaluation showed compliance with 10 CFR 50.46. Topical Report BAW-10227-A has addressed all of the important aspects of AREVAs M5 alloy fuel rod cladding material with respect to ECCS performance requirements, as follows:
- Since the material properties of AREVAs M5 alloy are similar to those of zirconium-based materials, the NRC staff found it appropriately conservative to apply the criteria in 10 CFR 50.46 and 10 CFR part 50, appendix K.
- Material properties of AREVAs M5 alloy, including cladding thermal conductivity, cladding creep, clad swelling, rupture deformation, and temperature, were found to be very similar to those of Zircaloy-4.
- The retention of the Baker-Just equation for the calculation of metal-water reaction rate specified in 10 CFR part 50, appendix K, is justified to be suitably conservative.
Based on the NRC staffs evaluation of the exemption request, the staff concludes that the intent of 10 CFR 50.46 and 10 CFR part 50, appendix K, will continue to be satisfied for the 6
planned operation of SPS, with AREVAs M5 alloy fuel rod cladding material used in up to eight non-limiting LTAs. The probability of postulated accidents is not increased. Also, based on the NRC staffs evaluation of the exemption request, the consequences of postulated accidents are not increased. Therefore, there is no undue risk to public health and safety due to using M5 alloy fuel cladding and fuel assembly material in up to eight non-limiting LTAs.
D. Consistent with the Common Defense and Security The proposed exemption would allow the use of AREVAs M5 alloy fuel rod cladding material at SPS. This change to the plant configuration is adequately controlled by technical specification requirements and is not related to security issues. Because the common defense and security is not impacted by this exemption, the exemption is consistent with the common defense and security.
IV. Conclusions Accordingly, the Commission has determined that, pursuant to 10 CFR 50.12(a), the exemption is authorized by law, will not present an undue risk to the public health and safety, is consistent with the common defense and security, and that special circumstances are present to warrant issuance of the exemption. Therefore, the Commission hereby grants SPS an exemption from the requirements of 10 CFR 50.46 and 10 CFR part 50, appendix K, paragraph I.A.5, to allow the use of AREVAs M5 alloy fuel rod cladding material in up to eight non-limiting LTAs at SPS.
7
Pursuant to 10 CFR 51.32, an environmental assessment and finding of no significant impact related to this exemption was published in the Federal Register on May 31, 2016 (81 FR 34382). Based upon the environmental assessment, the Commission has determined that issuance of this exemption will not have a significant effect on the quality of the human environment.
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 27th day of July 2016.
For the Nuclear Regulatory Commission.
/RA/
Anne T. Boland, Director, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.