Application to Amend License NPF-4,changing Tech Specs to Reflect Addition & Deletion of Containment Isolation Valves
ML20054K457
Person / Time
Site: North Anna Dominion icon.png
Issue date: 06/25/1982
From: Leasburg R
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Clark R, Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20054K458 List:
References
373, NUDOCS 8207020166
Download: ML20054K457 (3)


Text

e, -o VINGINIA ELECTmIC ann Powna COMPANY Hacsimosn, VINGINIA 20261

":%sta

" Psamammer June 25 1982 e

News. nam Urseassons Mr. Harold R. Denton, Director Serial No. 373 Office of Nucicar Reactor Regulation N0/JHL:ba Attn: Mr. Robert A. Clark, Chief Docket No. 50-338 Operating Reactors Branch No. 3 License No. NPF-4 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Gentlemen:

AMENDMENT TO OPERATIN LICENSE NPF-4 NORTH ANNA POWER STATION UNIT NO. 1 PROPOSED TECHNICAL SPECIFICATION CHANGE Pursuant to 10 CFR 50.90, the Virginia Electric and Power Company requests an amendment in the form of changes to the Technical Specifications, to Operating-License NPF-4 for North Anna Power Station, Unit No. 1. The proposed Technical Specification change is enclosed.

This proposed change is to modify Technical Specification 3/4.6.3.1, Table 3.6-1 for North Anns Unit No. I to reflect the addition and deletion of containment isolation valves. One nimual isolation valve and one check valve have been added to provide increased isolation for the Fire Protection System.

Six manual isolation valves have been added to provide forced circulation capabilities for the Steam Generator Wet Layup Circulation System. Two direct-acting solenoid valves are being added to replace two air-operated trip valves in the RHR Sample Lines to provide increased assurance of reliable operation during accident conditions. Two air-operated trip valves are being installed to provide containment integrity for the Post-Accident Sampling System Containment Return Lines. Four manual isolation valves in the Hydrogen Recombiner and Analyzer System are being replaced with sixteen remote-manual valves to upgrade the Hydrogen Recombiner and Analyzer System.

The upgrade and installation of these containment isolation valves meet the requirements for containment isolation integrity as specified in the FSAR and also satisfies the seismic design criteria for safety related systems. The proposed Technical Specification change is enclosed in Attachment 1. The corresponding overleaf pages are also provided in Attachment I to provide document completeness. A discussion of the proposed change is enclosed in Attachment 2.

This request has been reviewed and approved by the Station Nuclear Safety and Operating Committee and portions were reviewed and approved by the System Nuclear Safety and Operating Committee and the Safety Evaluation and Control Staff. It has been determined that this request does not involve an unreviewed safety question as defined in 10 CFR 50.59. I_

8207020166 820625 PDR ADOCK 05000338 0 05 6 PDR P

(J)IhE{ h e8

visoin 4 r.tecraic no rowra cour4w to Mr. Harold R. Denten We have evaluated this request in accordance with the criteria in 10 CFR 170.22. Since this request involves a safety issue which the staff should be abic to determine does not pose a significant hazard consideration for Unit 1, a Class III license amendment fee is required for Unit 1. Accordingly, a voucher check in the amount of $4000.00 is enclosed in payment of the required fees.

Very tru y ours, I

R. . Leasburg Attachments

1. Proposed Technical Specification Change
2. Discussion of Proposed Technical Specification Change
3. Voucher Check No. 32531 for $4000.00 cc: Mr. James P. O'Reilly Regional Administrator Region II l

COMMONWEALTH OF VIRGINIA )

)

CITY OF RICHMOND )

The foregoing document was acknowledged before me, in and for the City and Commonwealth aforesaid, today by R. H. Leasburg, who is Vice President-Nuclear Operations, of the Virginia Electric and Power Company. He is duly authorized to execute and file the foregoing document in behalf of that Company, and the statements in the document are true to the best of his knowledge and belief.

Acknowledged before me this Jf ). r day of u , 19 8A .

My Commission expires: -R - A lo , 19 >[.

O.N"A Notary Public (SEAL)