Vermont Yankee July 2008 Evidentiary Hearing - Applicant Exhibit E3-13-VY, VY 2004 Dryer Inspection Results Summary
ML082530213
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 12/31/2004
From:
Entergy Nuclear Operations, Entergy Nuclear Vermont Yankee
To:
NRC/SECY/RAS
SECY RAS
References
06-849-03-LR, 50-271-LR, Entergy-Applicant-E3-13-VY, RAS M-313
Download: ML082530213 (2)


Text

VERMONT YANKEE 2004 REFUELING OUTAGE RFO-24 DRYER EXAMINATION

SUMMARY

AND RESULTS The steam dryer examination scope at Vermont Yankee for the twenty-fourth refueling outage ("RFO-24),

conducted in the Spring of 2004, is summarized as follows:

Location Examination Method Number of Discrete Exams Dryer OD Horizontal Welds VT-I 24 Dryer OD Vertical Welds VT-i 42 OD Covers and Penetrations VT-I 3

Lifting Rods VT-I 4 Outer Plenum VT-I 32.

Dryer Leveling Screws VT-I part of 2004 modification Dryer Repair Hardware VT-I part of 2004 modification Dryer Tie Bars VT-I part of 2004 modification Steam Dam Gussets VT-i part of 2004 modification Steam Dryer Hood Cover Plates VT-I part of 2004 modification Steam Dryer Hood End Plates VT-I part of 2004 modification Welded Dryer Bank Support Hardware at VT-1 Lifting Lugs part of 2004 modification Dryer Vane Bank Outlet Fillet Welds VT-I part of 2004 modification Drain Channel Welds VT-1 22 Dryer ID Vertical Welds VT-1 27 Dryer ID Horizontal Welds VT-I 55 Dryer ID Struts VT-I 22 Dryer Plate Exams VT-3 52 OD General Condition VT-3 2 ID General Condition VT-3 2 TotAý]Vtker of Exams U.S. NUOLEAF( kEU&QKf6If 287 USNRC i Inthe Matter of * .';&_

August 12, 2008 (11:00am)

Docket No. 60 -7Z71 Official Exhibit No.

OFFICE OF SECRETARY _

RULEMAKINGS AND OFFERED by- ýscaticseee Intervenor, ADJUDICATIONS STAFF NRC Staff Other IDENTIFIED on 08i21 Witness/Panel I..J*C .

Action Taken: ITTREEJECTED WffHIRAWN

-0 ReIoortelfClerk- "AC,

S This summary scope resulted in approximately 300 individually identified examinations.

Four Indication Notification Reports (INR) were initiated, describing a total of 20 relevant (recordable) indications. Two of these indications, which were identified on Indication Notification Report INR-VYR24-0 1, were weld repaired. The remaining 18 indications was dispositioned "use-as-is," based on evaluation and recommendation by vendor and Entergy engineering personnel.

In RFO-24, a stiffening modification was made to the dryer, in anticipation of extended power uprate (EPU).

These modifications were examined in RFO-25 and RFO-26, and the results of those examinations are found in the exhibits related to those outages.

INR Location Comments 04-01 Vertical Weld V02-90 & Outer Plenum Weld 2 Indications, each approx. 3 inches long; both OP-V9-0; were weld repaired in 2004. Subsequent exams Vertical Weld V02-270 & Outer Plenum Weld show no new indications.

OP V19-180 04-02 Interior Vertical Welds HB-V04, HC-V06-180, 16 Indications HC-V06-000, HD-VO 1 04-03 Surface Deposits Originally reported as possible erosion.

Determined to be NRI 04-04 Drain Channel Vertical Weld DC-V04C; Weld 2 Indications Indication @ 1850 Drain Pipe