MONTHYEARLR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 LR-N23-0005, License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-06-23023 June 2023 License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0033, Core Operating Limits Report Cycle 272023-04-26026 April 2023 Core Operating Limits Report Cycle 27 LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations LR-N23-0019, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2023-03-21021 March 2023 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums LR-N23-0016, and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments2023-02-28028 February 2023 and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments LR-N23-0012, Annual Property Insurance Status Report2023-02-24024 February 2023 Annual Property Insurance Status Report LR-N23-0014, Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.7172023-02-23023 February 2023 Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.717 LR-N23-0003, Response to Requests for Additional Information Salem Unit 2 Relief Request S2-I4R-2112023-02-0101 February 2023 Response to Requests for Additional Information Salem Unit 2 Relief Request S2-I4R-211 LR-N22-0096, and Salem Generating Station, Units 1 and 2 - Request for Threshold Determination2023-01-0505 January 2023 and Salem Generating Station, Units 1 and 2 - Request for Threshold Determination LR-N22-0095, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 20222022-12-20020 December 2022 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2022 LR-N22-0094, Emergency Plan Document Revisions Implemented November 21, 20222022-12-14014 December 2022 Emergency Plan Document Revisions Implemented November 21, 2022 LR-N22-0092, Response to Final Iolb Request for Additional Information for Salem LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG2022-12-0909 December 2022 Response to Final Iolb Request for Additional Information for Salem LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG LR-N22-0091, Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments2022-12-0202 December 2022 Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments LR-N22-0084, Response to Final Request for Additional Information for Salem LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG (EPID L- 2022-LLA-0095)2022-11-17017 November 2022 Response to Final Request for Additional Information for Salem LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG (EPID L- 2022-LLA-0095) LR-N22-0090, Supplement to Submittal of Salem Generating Station Updated FSAR, Revision 33, 10 CFR 71.106 Review Results and 10 CFR 54.37(b) Review Results for Salem2022-11-10010 November 2022 Supplement to Submittal of Salem Generating Station Updated FSAR, Revision 33, 10 CFR 71.106 Review Results and 10 CFR 54.37(b) Review Results for Salem LR-N22-0065, Submittal of Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations2022-09-27027 September 2022 Submittal of Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations LR-N22-0074, Emergency Plan Evacuation Time Estimate2022-09-15015 September 2022 Emergency Plan Evacuation Time Estimate LR-N22-0066, License Amendment Request (LAR) to Relocate Technical Specifications (TS) Requirements for Reactor Head Vents to the Technical Requirements Manual (TRM)2022-08-31031 August 2022 License Amendment Request (LAR) to Relocate Technical Specifications (TS) Requirements for Reactor Head Vents to the Technical Requirements Manual (TRM) LR-N22-0063, Spent Fuel Cask Registration2022-08-10010 August 2022 Spent Fuel Cask Registration LR-N22-0068, In-Service Inspection Activities - 90-Day Report2022-08-10010 August 2022 In-Service Inspection Activities - 90-Day Report LR-N22-0012, License Amendment Request to Amend the Technical Specifications to Revise and Relocate the Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to a Pressure and Temperature2022-08-0707 August 2022 License Amendment Request to Amend the Technical Specifications to Revise and Relocate the Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to a Pressure and Temperature LR-N22-0062, Spent Fuel Cask Registration2022-07-21021 July 2022 Spent Fuel Cask Registration LR-N22-0006, License Amendment Request (LAR) to Amend Salem Unit 1 and Unit 2 Technical Specifications (TS) to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator from 72 Hours to 14 Days2022-06-29029 June 2022 License Amendment Request (LAR) to Amend Salem Unit 1 and Unit 2 Technical Specifications (TS) to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator from 72 Hours to 14 Days LR-N22-0051, License Amendment Request to Relocate Technical Specification Facility/Unit Staff Qualification Requirements to Quality Assurance Topical Report2022-06-22022 June 2022 License Amendment Request to Relocate Technical Specification Facility/Unit Staff Qualification Requirements to Quality Assurance Topical Report LR-N22-0044, Emergency Plan Document Revisions Implemented November, 20212022-05-19019 May 2022 Emergency Plan Document Revisions Implemented November, 2021 LR-N22-0043, Core Operating Limits Report - Cycle 292022-05-0909 May 2022 Core Operating Limits Report - Cycle 29 LR-N22-0041, 2021 Annual Radioactive Effluent Release Report (Rerr)2022-04-28028 April 2022 2021 Annual Radioactive Effluent Release Report (Rerr) LR-N22-0040, 2021 Annual Radiological Environmental Operating Report2022-04-28028 April 2022 2021 Annual Radiological Environmental Operating Report LR-N22-0039, Emergency Plan Document Revisions Implemented March 24, 20222022-04-21021 April 2022 Emergency Plan Document Revisions Implemented March 24, 2022 LR-N21-0052, Request for Relief from ASME Code Defect Removal for Service Water Buried Piping2022-04-0707 April 2022 Request for Relief from ASME Code Defect Removal for Service Water Buried Piping LR-N22-0023, Guarantees of Payment of Deferred Premiums2022-03-21021 March 2022 Guarantees of Payment of Deferred Premiums LR-N22-0022, Response to Request for Additional Information Relief Request S1-14R-210, Alternative Examination of Welds2022-03-21021 March 2022 Response to Request for Additional Information Relief Request S1-14R-210, Alternative Examination of Welds LR-N22-0017, Submittal of 2021 Annual Report of Fitness for Duty (FFD) Performance Data2022-02-25025 February 2022 Submittal of 2021 Annual Report of Fitness for Duty (FFD) Performance Data LR-N22-0016, Radiological Survey of Site Property to Be Used for Offshore Wind Port Facility2022-02-24024 February 2022 Radiological Survey of Site Property to Be Used for Offshore Wind Port Facility LR-N22-0013, In-Service Inspection Activities - 90-Day Report2022-02-10010 February 2022 In-Service Inspection Activities - 90-Day Report LR-N22-0007, Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty Programs2022-01-0505 January 2022 Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty Programs LR-N21-0061, Annual Report of Specific Activity Analysis - TS 6.9.1.5c2021-12-0909 December 2021 Annual Report of Specific Activity Analysis - TS 6.9.1.5c LR-N21-0083, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2021 & 30 Day Report for Salem Unit 2 Upflow Conversion2021-11-24024 November 2021 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2021 & 30 Day Report for Salem Unit 2 Upflow Conversion LR-N21-0078, Hope and Creek Generating Station, Supplement to License Amendment Request to Revise Technical Specifications (TS) to Delete Definitions Found in 10 CFR Part 20 and Delete Figures of the Site and Surrounding Areas from TS2021-11-18018 November 2021 Hope and Creek Generating Station, Supplement to License Amendment Request to Revise Technical Specifications (TS) to Delete Definitions Found in 10 CFR Part 20 and Delete Figures of the Site and Surrounding Areas from TS LR-N21-0066, Submittal of Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations2021-11-10010 November 2021 Submittal of Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations 2023-09-08
[Table view] |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, NJ 08038-0236 PSEG Order EA-12-051 LR-N14-0186 AUG 2 6 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Salem Generating Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-70 and DPR-75 NRC Docket Nos. 50-272 and 50-311
Subject:
PSEG Nuclear LLC's Third Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
References:
- 1. NRC Order Number EA-12-051, "Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012
- 2. PSEG Letter LR-N13-0020, "PSEG Nuclear LLC's Overall Integrated Plan for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051 ) , " dated February 28, 2013
- 3. PSEG Letter LR-N13-0176, "PSEG Nuclear LLC's First Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051 )," dated August 25, 2013
- 4. PSEG Letter LR-N14-0033, "PSEG Nuclear LLC's Second Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), " dated February 25, 2014
AUG 2 6 2014 Order EA-12-051 LR-N14-0186 Page 2 On March 12, 2012, the Nuclear Regulatory Commission (NRG) issued Order EA-12-051 (Reference 1) to PSEG Nuclear LLC (PSEG). Reference 1 was immediately effective and required submission of an Overall Integrated Plan (OIP) pursuant to Condition IV.C.1.a of the Order. Reference 2 provided the Salem Generating Station (SGS) Units 1 and 2 spent fuel level instrumentation OIP. Condition IV.C.2 of NRG Order EA-12-051 requires six-month status reports to delineate progress made in implementing the requirements of the Order. References 3 and 4 provided the first and second six-month status reports, respectively, for SGS. Enclosure 1 to this letter provides the third six-month status report of progress made in implementing the requirements of NRG Order EA-12-051 at SGS as of July 31, 2014. There are no changes in compliance method or issues requiring relief identified in Enclosure 1.
There are no regulatory commitments contained in this letter.
If you have any questions or require additional information, please do not hesitate to contact Mr. Brian Thomas at 856-339-2022.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on -=- /-;;. G /
<'?- - 1 _..._
d-t'/t(
(D ate)
Sincerely, C,e;:;
ln F. Perry (/
Vice President - Salem Enclosure 1 - Salem Generating Station Third Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation cc: Director of Office of Nuclear Reactor Regulation Administrator, Region I, NRG Project Manager, NRG NRC Senior Resident Inspector, Salem Mr. P. Mulligan, Manager IV, NJBNE Salem Commitment Tracking Coordinator PSEG Corporate Commitment Coordinator
AUG 2 6 2014 Order EA-12-051 LR-N14-0186 Page 3 (The bee list should not be submitted as part of the DCD submittal - remove this page prior to submittal and make the bee distribution accordingly) bee: President and Chief Nuclear Officer Senior Vice President and Chief Operating Officer Vice President - Salem Vice President, Operations Support Director - Nuclear Oversight Director - Regulatory Affairs Plant Manager - Salem Manager - Regulatory Assurance - Salem Senior Project Manager - Fukushima Site Improvements Project Manager - Licensing Document Control
ENCLOSURE 1 LR-N14-0186 Salem Generating Station Third Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Salem Generating Station Units 1 and 2 PSEG Nuclear LLC
ENCLOSURE 1 LR-N14-0186
- 1. Introduction PSEG developed an Overall Integrated Plan (OIP) (Reference 1) for Salem Generating Station (SGS) Units 1 and 2, documenting the plan to meet the requirements to install reliable spent fuel pool instrumentation (SFPI) in response to NRC Order EA-12-051 (Reference 2). In References 3 and 4, respectively, PSEG provided the first and second six-month status reports associated with implementation of the requirements of NRC Order EA-12-051. This report is the third six month status report, which provides implementation status as of July 31, 2014. This status report follows the guidance in Appendix A to Nuclear Energy Institute (NEI) Report 12-02, Revision 1 (Reference 5),
which states that the six-month status reports should include any changes to the compliance method, schedule, and the need for relief and the basis for relief, if applicable. Sections 2 and 3 of this status report include milestone accomplishments and milestone schedule status, respectively. There are no changes to compliance method or requests for relief associated with this report.
- 2. Milestone Accomplishments As of July 31, 2014, the following milestones have been completed since the development of the SGS SFPI OIP.
- Submit Integrated Plan: PSEG submitted the SGS SFPI OIP to the NRC.
- Issue SFPI Equipment Purchase Order: PSEG issued a material purchase order to the SFPI vendor.
- Begin Installation -SFPI installation activities have begun at Salem Units 1 and 2.
- 3. Milestone Schedule Status The following table provides an update of the milestone schedule provided in Section 3 of the SGS SFPI OIP, as well as additional milestones (e.g., six-month status reports, procedures, training and a completion report) that have been included for completeness. The table provides the activity status of each item, and the expected completion date noting any changes. The dates are planning dates subject to change as design and implementation details are finalized. Activities apply to both SGS Units 1 and 2, unless indicated otherwise.
Page 1 of 3
ENCLOSURE 1 LR-N14-0186 Revised Target Activity Target Milestone Completion Status Completion Date Date Conceptual Design Dec 2012 Complete Submit Overall Integrated Plan Feb 2013 Complete Aug 2013 Complete Feb 2014 Complete Six-Month Status Updates Aug 2014 Complete Feb 2015 Not Started Aug 2015 Not Started Issue SFPI Equipment Purchase 202013 Complete Order Design Change Package Complete Detailed Design - SGS Unit 1 102014 Started 302014 (Note 1)
Complete Detailed Design - SGS Unit 2 102015 Started 302014 (Note 1)
Begin Installation - SGS Unit 1 202014 Complete Begin Installation - SGS Unit 2 202015 Complete Installation Complete, SFPI 402014 Not Started Channels Fully Functional - Unit 1 Installation Complete, SFPI 402015 Not Started Channels Fully Functional - Unit 2 Implementation Outage - Unit 1 402014 Not Started Implementation Outage - Unit 2 402015 Not Started Procedures Issue Procedures - Unit 1 Nov 2014 Not Started Issue Procedures - Unit 2 Nov 2015 Not Started Training Complete Training - Unit 1 Nov 2014 Started Complete Training - Unit 2 Nov 2015 Started Submit Final Completion Report -
Feb 2016 Not Started Feb 2015 Unit 1 Submit Final Completion Report -
Feb 2016 Not Started Unit 2 Section 3 Table Notes:
- 1) The design change package for SGS Units 1 and 2 has been issued and is being revised pending finalization and PSEG approval of vendor documentation.
Page 2 of 3
ENCLOSURE 1 LR-N14-0186
- 4. Changes to Compliance Method There are no changes to the compliance method as documented in the SGS SFPI OIP.
- 5. Need for Relief/Relaxation and Basis for the Relief/Relaxation PSEG expects to fully comply with the order implementation date and no relief or relaxation is requested at this time.
- 6. Open Items from Overall Integrated Plan and Draft Safety Evaluation Open items from the NRC's Interim Staff Evaluation (Reference 6) are being addressed as part of the NRC audit process.
- 7. Potential Draft Safety Evaluation Impacts There are no potential draft safety evaluation impacts at this time.
- 8. References
- 1. PSEG Letter LR-N13-0020, "PSEG Nuclear LLC's Overall Integrated Plan for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051),"dated February 28, 2013
- 2. NRC Order Number EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012
- 3. PSEG Letter LR-N13-0176, "PSEG Nuclear LLC's First Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051),"dated August 25, 2013
- 4. PSEG Letter LR-N14-0033, "PSEG Nuclear LLC's Second Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051 ),"dated February 25, 2014
- 5. NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"'
Revision 1, August 2012
- 6. NRC Letter to PSEG, "Salem Nuclear Generating Station, Units 1 and 2 - Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC NOS. MF0913 and MF0914),"dated October 17, 2013 Page 3 of 3