MONTHYEARML24016A2372024-01-17017 January 2024 NEI Environmental Reviews Slides Public Meeting 1-17-24 ML24010A0202024-01-11011 January 2024 Public Meeting on SLR Efficiencies - NEI Presentation ML24008A0442024-01-0909 January 2024 NEI - Slides for NRC Workshop 1 on Revision to RG 1.183 R1 - Final - ML24008A044 ML23342A0262023-12-14014 December 2023 December 14, 2023, Presentation on NEI 23-01 Operator Cold Licensing Training Plan for Advanced Nuclear Reactors ML23347A1782023-12-13013 December 2023 12-14 NEI EPRI Presentation NRC Public Meeting 16-03 R1 ML23303A1922023-10-30030 October 2023 NEI Slides for SLR Public Meeting - Oct 31 2023 ML23324A2392023-10-24024 October 2023 S1P6 - Hilary Lane - NRC AMT Workshop - Oct. 2023 ML23261C3792023-09-27027 September 2023 NEI 22-04 Pre-Submittal Meeting with NRC - September 27, 2023 ML23258A1992023-09-20020 September 2023 NEI 99-02 Draft Rev. 8 Update for Sept 2023 ROP Public Meeting ML23242A0782023-08-30030 August 2023 Hbu Workshop IV Industry Presentation: Drive to Deploy ATF with Increased Enrichment and Higher Burnup ML23242A1662023-08-30030 August 2023 the Future of Nuclear Power: 2023 Baseline Survey (Slides) ML23230A0142023-08-22022 August 2023 Industry Slide Presentation for 8-22-23 Meeting on ARCAP-TICAP and DG-1404 Guidance Documents ML23228A0042023-08-18018 August 2023 NEI Slides for Public Meeting to Discuss Possible Efficiencies on the Subsequent License Renewal Review - August 18, 2023 ML23191A0162023-07-11011 July 2023 NEI Comments on Risk-Informed Process for Evaluation (RIPE) DORL TSG - 7/11/23 Public Meeting Slides from NEI ML23191A0632023-07-0707 July 2023 NEI Cybersecurity Presentation for July 2023 ROP Public Meeting ML23191A0662023-07-0707 July 2023 NEI 99-02 Draft Rev. 8 Update for July 2023 ROP Public Meeting ML23160A1512023-06-15015 June 2023 25 - Industry - Industry Perspectives on ASME III and XI Pre-Service Inspection ML23160A1422023-06-15015 June 2023 20 - Industry - Industry Perspective on Performance Monitoring ML23116A1892023-05-31031 May 2023 Industry Observations of NRC Licensing Program (NEI Slides May 2023) ML23136A5912023-05-18018 May 2023 NEI Safety Culture Presentation for May 2023 ROP Public Meeting ML23125A3192023-05-0909 May 2023 NEI Presentation for May 9, 2023, Public Meeting on NEI 22-05, Revision a ML23117A3712023-05-0202 May 2023 NEI Lessons Learned Meeting Slides, May 2, 2023 ML23115A0302023-04-27027 April 2023 NEI Perspective on Performance Monitoring in Use of Probabilistic Fracture Mechanics for Optimizing Inspections of Non-RPV Pressure Vessels, April 27, 2023 ML23088A0822023-03-30030 March 2023 NEI Presentation - March 30, 2023 PRA Configuration Control Public Meeting ML23082A0572023-03-28028 March 2023 Proposal to Establish Alternate Requirements for Components Commensurate with Safety and Risk ML23079A2642023-03-23023 March 2023 General Visual Examination of Containment Surfaces Covered by Insulation - March 23, 2023 Public Meeting Slides from NEI ML23210A0042023-03-15015 March 2023 Destination: Termination, NRC Regulatory Information Conference ML23045A2892023-03-14014 March 2023 RIC 2023 - 03/14/2023 to 03/16/2023 Regulatory Information Conference (Ric).Operational and Safety Benefits of Risk Informed Applications ML23061A0292023-03-0202 March 2023 NEI Presentation - Advanced Reactor Digital I&C Licensing Workshop 1 ML23013A0782023-01-13013 January 2023 PI&R Inspection Discussion for January 2023 ROP Public Meeting ML23012A1382023-01-12012 January 2023 General Visual Examination of Containment Surfaces Covered by Insulation - 1/19/23 Public Meeting Slides from NEI ML23041A4342022-12-15015 December 2022 NEI Presentation for December 15, 2022 Industry Spent Fuel Activities Prioritization Meeting ML22333A7192022-11-29029 November 2022 NEI-Presentation-Seismic Hazards Public Meeting - November 2022 - Final Presentation to NRC ML22318A3032022-11-16016 November 2022 NEI-22-01 License Termination Process Pre-Submittal Meeting November 16, 2022 (Presentation) ML22291A4442022-10-11011 October 2022 NEI 22-01 License Termination Plan Process Presentation at October 11 2022 Meeting on NUREG-1757 Vol. 2 ML22250A7122022-09-21021 September 2022 NEI 22-03 Presentation Slides for NRC Public Meeting (Sept. 21, 2022) ML22235A7032022-08-24024 August 2022 NEI Presentation for Aug 26, 2022 Public Meeting - Source Terms and Radiological Consequence Analyses ML22216A1152022-08-0404 August 2022 August 4, 2022 Rislr Public Meeting Presentation by Nuclear Energy Institute ML22194A0682022-07-18018 July 2022 NEI Presentation for NEI 22-02 Rsi Response ML22174A2822022-06-22022 June 2022 NEI Presentation for Public Meeting with NMMSS Users Community to Discuss Foreign Obligation Reporting Requirements for Low Enriched Uranium ML22172A1352022-06-21021 June 2022 NEI Presentation for Public Meeting Industry Perspectives on Rulemaking for Greater than 5 Percent Enrichment ML22152A0942022-06-0202 June 2022 NEI Slides - Risk Insights for Aging Management Presentation June 2, 2022 ML22143A8542022-05-20020 May 2022 Nuclear Energy Institue (NEI) Presentation Slides to ACRS Subcommittee on CCF Secy Paper, May 20, 2022 ML22164A0182022-05-18018 May 2022 Fuel Cycle Industry NRC Fcf Stakeholders Mtg May 2022 ML22124A2072022-05-13013 May 2022 Public Meeting Slides for May 13 2022 CRGR Meeting Regarding RIS on Operating Leakage ML22136A1162022-05-11011 May 2022 Presentation 5 - Utilizing the Nuclear Energy Institute (NEI) 07-07 Industry Groundwater Protection Initiative as a Foundation for Addressing Subsurface Site Assessments ML22102A2022022-04-12012 April 2022 NEI Presentation Related to the Development of Adversary Timelines NRC Comment Resolution ML22053A2802022-03-31031 March 2022 Regulatory Information Conference (RIC) RIC 2022 Technical Session T8 - True D - NEI Presentation RIDM Greater than Sum of Its Parts ML22088A0342022-03-29029 March 2022 Public Meeting Presentation by NEI Regarding Part 53 Rulemaking: Selected Topics ML22077A4012022-03-23023 March 2022 NEI INL Presentation March 23, 2022, NRC Workshop Isv Hfe Issue 2024-01-09
[Table view] Category:Meeting Briefing Package/Handouts
MONTHYEARML24016A2372024-01-17017 January 2024 NEI Environmental Reviews Slides Public Meeting 1-17-24 ML24008A0442024-01-0909 January 2024 NEI - Slides for NRC Workshop 1 on Revision to RG 1.183 R1 - Final - ML24008A044 ML23342A0262023-12-14014 December 2023 December 14, 2023, Presentation on NEI 23-01 Operator Cold Licensing Training Plan for Advanced Nuclear Reactors ML23347A1782023-12-13013 December 2023 12-14 NEI EPRI Presentation NRC Public Meeting 16-03 R1 ML23303A1922023-10-30030 October 2023 NEI Slides for SLR Public Meeting - Oct 31 2023 ML23324A2392023-10-24024 October 2023 S1P6 - Hilary Lane - NRC AMT Workshop - Oct. 2023 ML23258A1992023-09-20020 September 2023 NEI 99-02 Draft Rev. 8 Update for Sept 2023 ROP Public Meeting ML23242A0782023-08-30030 August 2023 Hbu Workshop IV Industry Presentation: Drive to Deploy ATF with Increased Enrichment and Higher Burnup ML23230A0142023-08-22022 August 2023 Industry Slide Presentation for 8-22-23 Meeting on ARCAP-TICAP and DG-1404 Guidance Documents ML23191A0632023-07-0707 July 2023 NEI Cybersecurity Presentation for July 2023 ROP Public Meeting ML23191A0662023-07-0707 July 2023 NEI 99-02 Draft Rev. 8 Update for July 2023 ROP Public Meeting ML23160A1512023-06-15015 June 2023 25 - Industry - Industry Perspectives on ASME III and XI Pre-Service Inspection ML23160A1422023-06-15015 June 2023 20 - Industry - Industry Perspective on Performance Monitoring ML23116A1892023-05-31031 May 2023 Industry Observations of NRC Licensing Program (NEI Slides May 2023) ML23136A5912023-05-18018 May 2023 NEI Safety Culture Presentation for May 2023 ROP Public Meeting ML23125A3192023-05-0909 May 2023 NEI Presentation for May 9, 2023, Public Meeting on NEI 22-05, Revision a ML23115A0302023-04-27027 April 2023 NEI Perspective on Performance Monitoring in Use of Probabilistic Fracture Mechanics for Optimizing Inspections of Non-RPV Pressure Vessels, April 27, 2023 ML23088A0822023-03-30030 March 2023 NEI Presentation - March 30, 2023 PRA Configuration Control Public Meeting ML23082A0572023-03-28028 March 2023 Proposal to Establish Alternate Requirements for Components Commensurate with Safety and Risk ML23079A2642023-03-23023 March 2023 General Visual Examination of Containment Surfaces Covered by Insulation - March 23, 2023 Public Meeting Slides from NEI ML23210A0042023-03-15015 March 2023 Destination: Termination, NRC Regulatory Information Conference ML23045A2892023-03-14014 March 2023 RIC 2023 - 03/14/2023 to 03/16/2023 Regulatory Information Conference (Ric).Operational and Safety Benefits of Risk Informed Applications ML23061A0292023-03-0202 March 2023 NEI Presentation - Advanced Reactor Digital I&C Licensing Workshop 1 ML23013A0782023-01-13013 January 2023 PI&R Inspection Discussion for January 2023 ROP Public Meeting ML23041A4342022-12-15015 December 2022 NEI Presentation for December 15, 2022 Industry Spent Fuel Activities Prioritization Meeting ML22291A4442022-10-11011 October 2022 NEI 22-01 License Termination Plan Process Presentation at October 11 2022 Meeting on NUREG-1757 Vol. 2 ML22266A2632022-09-28028 September 2022 Session 2 - Advanced Reactor Developers Perspectives on Codes and Standards ML22250A7122022-09-21021 September 2022 NEI 22-03 Presentation Slides for NRC Public Meeting (Sept. 21, 2022) ML22235A7032022-08-24024 August 2022 NEI Presentation for Aug 26, 2022 Public Meeting - Source Terms and Radiological Consequence Analyses ML22194A0682022-07-18018 July 2022 NEI Presentation for NEI 22-02 Rsi Response ML22174A2822022-06-22022 June 2022 NEI Presentation for Public Meeting with NMMSS Users Community to Discuss Foreign Obligation Reporting Requirements for Low Enriched Uranium ML22172A1352022-06-21021 June 2022 NEI Presentation for Public Meeting Industry Perspectives on Rulemaking for Greater than 5 Percent Enrichment ML22143A8542022-05-20020 May 2022 Nuclear Energy Institue (NEI) Presentation Slides to ACRS Subcommittee on CCF Secy Paper, May 20, 2022 ML22136A1162022-05-11011 May 2022 Presentation 5 - Utilizing the Nuclear Energy Institute (NEI) 07-07 Industry Groundwater Protection Initiative as a Foundation for Addressing Subsurface Site Assessments ML22088A0342022-03-29029 March 2022 Public Meeting Presentation by NEI Regarding Part 53 Rulemaking: Selected Topics ML22077A4012022-03-23023 March 2022 NEI INL Presentation March 23, 2022, NRC Workshop Isv Hfe Issue ML22070B1212022-03-16016 March 2022 Industry Perspective on IEEE Std -1819 ML22140A3612022-03-10010 March 2022 mccullumr- hv-th29 ML22060A0022022-03-0101 March 2022 Dt Public Meeting - NEI Slides ML22042A0092022-02-11011 February 2022 NEI Presentation Slides for February 15, 2022, Public Meeting on Common-Cause-Failure (CCF) Policy ML22031A2612022-01-31031 January 2022 NEI Feb 2022 PRA Configuration Control Inspection Workshop ML22027A3922022-01-27027 January 2022 NEI 50.59 Risk Insights Presentation ML21350A2122021-12-17017 December 2021 Slide Presentation: ACRS Future Plant Designs Subcommittee Meeting, 10 CFR Part 53, Licensing and Regulation of Advanced Nuclear Reactors - Presentation by Nuclear Energy Institute and Us Nuclear Industry Council ML21335A2602021-12-0202 December 2021 ROP Public Meeting Gtg PI 12022021 ML21334A3562021-11-29029 November 2021 Fire Protection-ROP Public Meeting-120221 ML21223A1002021-08-11011 August 2021 NEI Slides for Public Meeting on Reg Guide 1.9, Rev.5 - Revised 8-11 ML21221A2962021-08-11011 August 2021 NEI Slide Presentation on Regulatory Guide 1.9, Revision 5 for Public Meeting August 11, 2021 ML21187A0572021-07-0707 July 2021 July 7 Public Mtg Slides for Pre-application of NEI 16-03 & EPRI i-LAMP ML21173A0562021-06-22022 June 2021 NEI Presentation - Adversary Timeline Methodology (Final- 6.24.21) - Updated ML21173A2862021-06-21021 June 2021 NEI 20-07 Systematic Approach to CCF NRC 2024-01-09
[Table view] |
Text
Moving Towards more Realistic Cabinet Damage Rob Cavedo
Potential Realism Improvement All trains and functions that can be affected by a fire are assumed to occur at the cabinet ignition frequency.
For most cabinets, this is a mildly conservative assumption (e.g. breaker goes open/breaker goes closed).
For cabinets that control multiple trains from different power supplies, this can be overly conservative.
Industry events of cabinets with multiple trains do not show the loss of all trains (e.g. single alarm card damaged others functional, single HS malfunction, etc.).
1 Moving towards more Realistic Cabinet Damage
Identification of Relevant Guidance NUREG/CR-6850 Section 8.5.1.2 (pg. 8-10) 2 Moving towards more Realistic Cabinet Damage
Proposed Approach to Enhance Realism Use a 25% chance all functions in a cabinet are lost and a 75% chance a single function is lost. This is based on a review of the sixteen control cabinet scenarios in the Fire Events Database (FEDB) only three are considered to represent broad damage to the cabinet.
A train is defined as any equipment in the cabinet powered from the same ultimate external power supply to the cabinet.
If all equipment in the cabinet is powered from the same external source, then this method cannot be applied.
This would only apply to scenarios with NO EXTERNAL damage. If the fire is large enough to damage external equipment, then larger internal losses are expected.
3 Moving towards more Realistic Cabinet Damage
Data for Proposed Approach to Enhance Realism Data (3-of-16 is wide spread damage):
Specific Challenging FireID Component Determination Event Date Fire Characterization Fire Characterization Type Extent Source Damage Power Effect 69 Control Cabinet 4 U(NC-PC) 8/29/1994 Fire damaged cables in control cabinet (located in the Switchyard). Other (specify) Unknown Scram Fire caused by breakdown of insulation in a control cable. The insulation breakdown was located where the insulation came in contact with a protruding tap of a wire wound power resistor.
Insulation breakdown due to aging (25 years) and water intrusion.
98 Control Cabinet 2-PC 10/8/1998 During a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> post maintenance run of the EDG Smoldering combustion - internal Confined to the object of origin Entered an LCO to component 187 Control Cabinet 2-PC 8/16/1999 thick grey smoke observed Flaming combustion - internal to Confined to the object of origin None component (broad/extensive damage) 303 Control Cabinet 2-PC 3/1/2000 Electrical short resulting in burning insulation and paint in Plant Flaming combustion - external to Confined to the object of origin None Heating Boiler Control Cabinet. component (broad/extensive damage) 20272 Relay Rack 4 U(NC-PC) 9/10/1990 Unknown Other (specify) Confined to the object of origin Unknown 30276 Other 2-PC 7/24/2006 Lighting battery box smoking, flames observed coming out near Flaming combustion - internal to Confined to the object of origin None transformer component 30281 Relay Rack 1-CH 6/5/2008 Failed relay in controm room cabinet due to overheating. Smoldering combustion - external Confined to the object of origin None Evidence of smoke, opened panel and saw relay with failed to component (localized/single subcomponent) insulation. No flaming observed.
30338 Control Cabinet 2-PC 3/30/2006 Discovered fire in blower. Extinguished using CO2. Contacted Flaming combustion - internal to Confined to the object of origin None electricians to investigate problem. Electricians disconnected the component (localized/single subcomponent) blower from its power source and removed the blower from the cabinet. Blower found to be full of dust and dirt. Smoke detecter in cabinet did not alarm while the area inside the panel was hazy with smoke.
30478 Control Cabinet 2-PC 9/9/2005 Source of fire a bunch of relays, wiring sustained significant Flaming combustion - internal to Confined to the object of origin None damage to insulation component (broad/extensive damage) 30513 Control Cabinet 2-PC 5/27/2008 Voltage transformer overheated and ignited combustible material Flaming combustion - internal to Confined to the object of origin None located inside transformer housing component 30522 Control Cabinet 2-PC 9/12/2000 fire kept to electrical cabinet. Damage to internals with noticable Flaming combustion - internal to Confined to the object of origin None charring and smoke damage, external box had some heat and component smoke damage.
50473 Wall Mounted 2-PC 6/26/2000 small flames from relay with smoke, water intrusion, sparking and Flaming combustion - internal to Confined to the object of origin None smoke before power removed component 50784 Relay Rack 2-PC 11/20/2005 Testing relay, started to smoke - fuses pulled and shot with Flaming combustion - external to Confined to the object of origin None extinguisher component (localized/single subcomponent) 50811 Control Cabinet 2-PC 1/9/2001 relay burning, found extinguisher and put out Flaming combustion - internal to Confined to the object of origin None component (localized/single subcomponent) 83-1 Wall Mounted 2-PC 4/4/1996 Smoke was discovered in the back boards area of the control room Flaming combustion - internal to Confined to the object of origin None by a security offer who was performing an hourly fire watch. component (localized/single subcomponent)
Smoke was emitting from the emergency lightning UPS. Damage limited to cabinet involved and adjoining cables 83-2 Wall Mounted 2-PC 4/4/1996 DC EQUP room fire - fire limited to transformer enclosure and Flaming combustion - internal to Confined to the object of origin None involved only internals. component (localized/single subcomponent) 4 Moving towards more Realistic Cabinet Damage
Example Flow controllers for Pump A and B are in Cabinet X.
Given a per panel ignition frequency of 1E-4, the conservative and more realistic results are:
Conservative full Cabinet Improved Cabinet Only Loss Modeling benefit is in Case Description Impact Frequency Frequency the Fire X1 Fire within Cabinet Both FC A and B Lost 7.00E-05 1.75E-05 within a X2 Fire within Cabinet FC A lost; FC B functional N/A 2.63E-05 cabinet X3 Fire within Cabinet FC B lost; FC A functional N/A 2.63E-05 region X4 Fire Damages cabinet and Target FCs A and B Lost and 1st Target 2.80E-05 2.80E-05 X5 Fire Damages whole room Whole Room Lost 2.00E-06 2.00E-06 Sum Check 1.00E-04 1.00E-04 5 Moving towards more Realistic Cabinet Damage
Industry Benefit Maximum site benefit is 20% CDF reduction. The average industry benefit is 2%.
6 Moving towards more Realistic Cabinet Damage
Questions 7 Moving towards more Realistic Cabinet Damage