©2021 Nuclear Energy Institute AJ Clore Development of NEI Guidance for Determining Adversary Timelines June 24, 2021
©2021 Nuclear Energy Institute 2 Presentation Purpose Overview of Adversary Timelines Desired Outcome, Current Practice, and Basis for Change Industry Approach Data Collection Initial Findings Example Licensee Implementation Proposed Path Forward Topic Areas
©2021 Nuclear Energy Institute 3 This presentation provides an overview of NEIs effort to conduct performance-based testing as means to develop defined adversary travel speeds based on the number of engaging officers as permitted by Regulatory Guide (RG) 5.81, Target Set Identification and Development for Nuclear Power Reactors, Revision 1 (dated December 2019).
Use of adversary timelines is discussed in RG 5.81, Revision 1 (dated December 2019).
The project goal is to create uniform adversary travel speeds that may be used to support development of site-specific protective strategies.
Presentation Purpose
©2021 Nuclear Energy Institute 4 Adversary timelines are a key factor in the development of a sites protective strategy. Adversary timelines drive responder timelines, which are used:
To inform the location of officer fighting positions (e.g., bullet resistant enclosures), placement of barriers, and implementation of other strategy features to ensure defense-in-depth In protective strategy assessments to ensure security officers can interdict adversaries with a high likelihood of success Development of adversary timelines are necessary to meet the physical protection program requirements contained in 10 CFR 73.55 Overview of Adversary Timelines
©2021 Nuclear Energy Institute 5 NRC-approved guidance that:
Establishes defined adversary travel speeds based on the number of engaging security officers.
Desired Outcome
©2021 Nuclear Energy Institute 6 RG 5.81, dated November 2010, made no allowance for considering interdiction effects on adversary timelines To date, adversary timelines have typically been based on two factors:
Travel Speed - how quickly a DBT adversary can sprint without a break
15 feet per second travel speed is the historical standard for a mock adversary Breaching Time - time taken to cut a fence, breach a door/barrier, etc.
Consistent with Regulatory Issue Summary (RIS) 2003-06 Current Practice
©2021 Nuclear Energy Institute 7 Section 5.5.3 of RG 5.81, Revision 1, describes considerations for Adversary Interference and states:
As an alternative method, licensees can perform an assessment to compare the timeframe associated with the delays to the adversary provided by implementation of the licensees entire physical protection program, including the delays provided by both the physical barriers and the response of the licensee security personnel, to the time required for the operator to arrive at the location.
Basis for Change
©2021 Nuclear Energy Institute 8 Conduct performance-based testing to provide the technical basis to incorporate the delay to the adversary that results from the interdiction of licensee security response force into timelines Develop defined adversary travel speeds based on the number of engaging security responders Industry Approach
©2021 Nuclear Energy Institute 9 Forty-two drills were conducted at three nuclear power reactor sites Testing protocols were consistent with the attributes of the Design Basis Threat The sites mock adversary force was used The adversary carry weight was consistent with the chosen target set/element A variety of travel paths were tested Varied to assess a range of barriers and responder engagement(s)
Consistent with RG 5.81, Revision 1, the testing only considered physical barriers and responders with engagement opportunities Data Collection
©2021 Nuclear Energy Institute 10 Adversaries ran multiple runs for each target element pathway Each pathway was ran an average of three times for each travel path Elapsed times started at the first point of credited detection (e.g.,
Early-Warning System (EWS) or Protected Area Intrusion Detection System (PIDS)) and terminated at the outer edge of the building where the target set element is located Adversaries were moved in a phased approach to ensure distance and speed could be documented and calculated in segments Data Collection
©2021 Nuclear Energy Institute 11 With no engaging responders, the adversary travel speed was determined to be 17 feet per second (ft/s)
Adversary(s) travel speeds slowed as responders engaged Adversary travel speed as a function of the number of engaging responders was relatively consistent across all three sites With a large number of engaging responders, adversary movement was too slow to reasonably incorporate Timelines developed using performance-based adversary travel speeds were longer than those developed using the current practice (i.e., assumed speed of 15 ft/s)
Initial Findings
©2021 Nuclear Energy Institute 12 Example Using Travel Speeds Identified Through Testing
©2021 Nuclear Energy Institute 13 Site Example Legend Solid Red Line Nuisance Fence Black Dotted Line Intrusion Detection System (IDS)
Blue Line Protected Area Fence (10 second breach time)
Green Line Delay Fence (20 second breach time)
Yellow Square Bullet Resistant Enclosure Yellow X Defensive Fighting Position Red X Target (20 second task time)
©2021 Nuclear Energy Institute 14 The guidance may be used to support:
Changes to a site protective strategy through revisions of required responder timelines; or The addition of an operator action to a target set This guidance does not preclude licensees from using other approaches to develop adversary timelines Site-specific changes would be evaluated and documented in accordance with 10 CFR 50.54(p) and 10 CFR 50.90, as applicable Licensee Implementation
©2021 Nuclear Energy Institute 15 Incorporate changes resulting from this public meeting Submit for NRC review and approval - 2Q2021 NRC observation of methodology at site - 3Q2021 Conduct, if necessary, testing at a fourth site - 3Q2021 Revised document submitted (if applicable) - 3Q2021 Conduct implementation workshop - 1Q2022 Proposed Path Forward
©2021 Nuclear Energy Institute 16 Questions?
AJ Clore Dustin ONeill Senior Project Manager Senior Project Manager Nuclear Energy Institute Pacific Gas & Electric/NEI 202.285.2085 805.503.0785 ajc@nei.org djo9@pge.com or djo@nei.org