Letter Sequence RAI |
---|
|
|
MONTHYEARML0708200032007-03-29029 March 2007 Kansas State University - Request for Additional Information and Assurance of Decommissioning Funding License R-88 Renewal Project stage: RAI ML0716303282007-06-0404 June 2007 Correction to May 2007 Response to Request for Additional Information Regarding Proposed Technical Specifications for the K-State Triga Mark II Nuclear Research Reactor Project stage: Response to RAI ML0723900062007-09-11011 September 2007 Kansas State University - Request for Additional Information License R-88 Renewal Project stage: RAI ML0726804712007-09-12012 September 2007 Kansas State University, Response to September 11, 2007 Request for Additional Information Project stage: Request ML0729706242007-10-16016 October 2007 Supplemental Information Response to September 11, 2007 Request for Additional Information and Assurance of Decommissioning Funding License R-88 Renewal Project stage: Supplement ML0805003662008-02-0606 February 2008 Response to Request for Additional Information of 01/14/2008 Related to Decommissioning Funding Assurance of Kansas State University Project stage: Response to RAI ML0631901722008-02-20020 February 2008 Kansas State University Triga Mark II Nuclear Reactor Environmental Assessment Regarding Amendment for Renewal and Power Uprate Project stage: Other 2007-09-11
[Table View] |
|
---|
Category:Letter
MONTHYEARML24281A0322024-10-0404 October 2024 Kansas State University (Ksu), License R-88, Docket 50-188, License Requirements Exemption Request Additional Supplemental Information IR 05000188/20242012024-07-11011 July 2024 Kansas State University - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000188/2024201 ML24164A0922024-06-11011 June 2024 Kansas State University, License Requirements Exemption Request Supplemental Information ML24085A8082024-03-0707 March 2024 Kansas State University 10 CFR 55.59 License Requirements Exemption Request ML24009A0632024-02-23023 February 2024 Confirmatory Action Letter - Kansas State University Commitment to Operational Practices ML24036A0332024-02-0909 February 2024 Kansas State University - Withdrawal of Requested Licensing Action Regarding Use of 12 Weight Percent Uranium Fuel Elements ML24018A1042023-12-21021 December 2023 Kansas State Univ, Manhattan, License Amendment Request IR 05000188/20232022023-08-0101 August 2023 Kansas State University - U.S. Nuclear Regulatory Commission Security Inspection Report No. 05000188/2023202 (Public) IR 05000188/20232012023-06-0505 June 2023 Kansas State University – U.S. Nuclear Regulatory Commission Safety Inspection Report 05000188/2023201 ML23088A1992023-02-28028 February 2023 2022 Annual Operating Report for the Kansas State University Triga Mark II Nuclear Reactor ML23053A1162023-01-31031 January 2023 Kansas State University Request for Additional Information (Acc. ML19128A342) Response Time Extension IR 05000188/20222012022-07-0606 July 2022 Kansas State University - U.S. Nuclear Regulatory Commission Routine Inspection Report No 05000188-2022201 ML22153A5192022-06-27027 June 2022 Kansas State Univ, Response to Request for Extension of Time to Respond to RAI Regarding Lic Amend Request ML22172A0102022-05-27027 May 2022 Kansas State Univ., Request for Additional Information (Acc. ML19128A342) Response Time Extension ML22091A1742022-03-0101 March 2022 2021 Annual Operating Report for the Kansas State University Triga Mark II Nuclear Reactor ML21347A8332021-12-13013 December 2021 Examination Report Letter No. 50-188/OL-21-01, Kansas State University IR 05000188/20212012021-07-14014 July 2021 Kansas State University, Us Nuclear Regulatory Commission Routine Inspection Report 05000188/2021201 - Cover Letter and Enclosure ML21166A3332021-07-0808 July 2021 Kansas State University - Response to Request for Extension of Time to Respond to Request for Additional Information Regarding License Amendment Request for the Use of 12 Percent by Weight Uranium Fuel Elements ML21180A4502021-07-0707 July 2021 Examination Confirmation Letter No. 50-188/OL-21-01, Kansas State University ML21188A2092021-06-0909 June 2021 Kansas State Univ., Request for Additional Information (Acc. ML19128A342) Response Time Extension ML21070A0102021-04-15015 April 2021 Kansas State University, Response to Request for Extension of Time ML21105A4852021-03-0808 March 2021 Kansas State Univ., Response to Request for Additional Information (Acc. ML19128A342) Response Time Extension ML21070A1862021-02-26026 February 2021 2020 Annual Operating Report for the Kansas State University Triga Mark II Nuclear Reactor (Facility License R-88, Facility Docket 50-188) ML21013A5402021-01-26026 January 2021 Kansas State University, Response to Request for Extension of Time to Respond to Request for Additional Information Regarding License Amendment Request for the Use of 12 Weight Percent Uranium Fuel Elements ML20366A0462020-12-0808 December 2020 Kansas State University, Response to Request for Additional Information (Acc. ML19128A342) Re Response Time Extension ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards IR 05000188/20202022020-10-0505 October 2020 Kansas State University - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000188/2020202 - Cover Letter and Enclosure ML20253A2352020-10-0505 October 2020 Kansas State University, Response to Request for Extension of Time to Respond to Request for Additional Information Regarding License Amendment Request for the Use of 12 Weight Percent Uranium Fuel Elements ML20269A2472020-09-0808 September 2020 Kansas State Univ. Manhattan, Request for Additional Information (Acc. ML19128A342) Response Time Extension ML20167A3062020-06-23023 June 2020 Kansas State University, Response to Request for Extension of Time to Respond to Request for Additional Information Regarding License Amendment Request for the Use of 12 Weight Percent Uranium Fuel Elements ML20070H6742020-03-30030 March 2020 Kansas State University, Response to Request for Extension of Time to Respond to Request for Additional Information Regarding License Amendment Request for the Use of 12 Weight Percent Uranium Fuel Elements ML20083G1942020-03-0909 March 2020 Kansas State University - Request for Additional Information (Acc. ML19128A342) Response Time Extension ML20065H1502020-02-28028 February 2020 Kansas State University - 2019 Annual Operating Report for the Triga Mark II Nuclear Reactor ML20008D3522020-01-13013 January 2020 Kansas State University, Response to Request for Extension of Time to Respond to Request for Additional Information Regarding License Amendment Request for the Use of 12 Weight Percent Uranium Fuel Elements ML20013F6802020-01-0707 January 2020 Kansas State Univ., Request for Additional Information (Acc. Fl MU9128A34~) Response Time Extension ML19352E1522019-12-13013 December 2019 Reportable Occurrence on December 4, 2019 at the Kansas State University Triga Mark II Nuclear Reactor Facility ML19337A4362019-11-29029 November 2019 Reply to a Notice of Violation - 2019 NRC Annual Inspection of the Kansas State University Triga Mark II Nuclear Reactor (Facility License # R-88, Facility Docket# 50-188) ML19337B0542019-11-28028 November 2019 Kansas State Univ., Manhattan - 2018 Annual Operating Report IR 05000188/20192012019-10-30030 October 2019 Kansas State University - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 50-188/2019-201 and Notice of Violation ML19290H5932019-10-24024 October 2019 Kansas State University, Response to Request for Extension of Time to Respond to Request for Additional Information Regarding License Amendment Request for the Use of 12 Weight Percent Uranium Fuel Elements, and Acknowledgement of Operation ML19295D7272019-10-0707 October 2019 Kansas State University - Response to 06/05/2019 Request for Additional Information, and Teleconferences Summary ML19248C8342019-09-18018 September 2019 Kansas State University, Summary of Teleconference Related to License Amendment Request for the Use of 12 Weight Percent Uranium Fuel Elements ML19190A0892019-07-0202 July 2019 Personnel Changes at Ksu Triga Reactor - License # R-88, Docket 50-188 ML19128A3422019-06-0505 June 2019 Kansas State University, Request for Additional Information Related to License Amendment Request for the Use of 12 Weight Percent Uranium Fuel Elements IR 05000188/20182012019-03-20020 March 2019 Kansas State University U.S. Nuclear Regulatory Commission Routine, Announced Inspection Report No. 50-188/2018201 ML19074A0702019-03-18018 March 2019 Kansas State University, Examination Report 50-188/OL-18-02 ML18360A5782019-01-0707 January 2019 Kansas State University - Change of Facility Project Manager ML19007A0492019-01-0101 January 2019 Kansas State Univ., Reportable Occurrence on December 22, 2018 ML19007A0502018-12-31031 December 2018 Kansas State Univ., Manhattan - Submittal of 2017 Annual Operating Report ML18347A2092018-11-30030 November 2018 Kansas State Univ., Manhattan - Technical Specifications and Safety Analysis Report Changes Related to License Amendment Request No. 18 2024-07-11
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23060A0172023-02-28028 February 2023 NRR E-mail Capture - Kansas State University, Response to RAI Extension Request ML20008D3522020-01-13013 January 2020 Kansas State University, Response to Request for Extension of Time to Respond to Request for Additional Information Regarding License Amendment Request for the Use of 12 Weight Percent Uranium Fuel Elements ML19128A3422019-06-0505 June 2019 Kansas State University, Request for Additional Information Related to License Amendment Request for the Use of 12 Weight Percent Uranium Fuel Elements ML19108A3152019-04-18018 April 2019 Kansas State University, Draft Request for Additional Information Related to License Amendment Request for 12 Wt% Uranium Fuel ML17038A2722017-03-28028 March 2017 Kansas State University - Request for Additional Information Regarding License Amendment Request for Facility Operating License No. R-88, for the Kansas State University Nuclear Reactor (CAC No. A11010) ML16189A1942016-08-11011 August 2016 Kansas State University - Request For Additional Information Regarding License Amendment Request of Facility Operating License No. R-88, for the Kansas State University Nuclear Reactor ML14065A5392014-03-19019 March 2014 Kansas State University - Request for Additional Information Regarding License Amendment Request of Facility Operating License No. R-88, for the Kansas State University Nuclear Reactor ML1026703212011-02-24024 February 2011 Kansas State University- Request for Additional Information Regarding the Request for Possession Limit Increase for the Kansas State University Triga MK-II Nuclear Reactor Facility ML0723900062007-09-11011 September 2007 Kansas State University - Request for Additional Information License R-88 Renewal ML0708200032007-03-29029 March 2007 Kansas State University - Request for Additional Information and Assurance of Decommissioning Funding License R-88 Renewal ML0527103672005-10-0707 October 2005 RAI Letter - Security Measures - Whaley 2023-02-28
[Table view] |
Text
March 29, 2007 Mr. Michael Whaley, Manager Nuclear Reactor Facility Department of Mechanical and Nuclear Engineering 112 Ward Hall Kansas State University Manhattan, KS 66506-5204
SUBJECT:
KANSAS STATE UNIVERSITY - REQUEST FOR ADDITIONAL INFORMATION AND ASSURANCE OF DECOMMISSIONING FUNDING RE: LICENSE R-88 RENEWAL (TAC NO. MC9031)
Dear Mr. Whaley:
We are continuing our review of your request for license renewal for the Kansas State University research reactor which you submitted on September 12, 2002. During our review of your license renewal request, questions have arisen for which we require additional information and clarification. Please provide responses to the enclosed request for additional information (RAI) within 30 days of the date of this letter.
In addition, your license renewal application included financial information pertaining to operation and decommissioning of the reactor. This letter does not satisfy the requirements for assurance of decommissioning funding for license renewal. The position of the NRC is that KSU has assurance from the State of Kansas for decommissioning funding under the current license, but updated assurance of decommissioning funding is required for license renewal.
Title 10 of the Code of Federal Regulations, Part 50.75(e)(iv) permits State licensees to provide assurance of decommissioning funding by a statement of intent containing a cost estimate for decommissioning, and indicating that funds for decommissioning will be obtained when necessary. The statement of intent must be signed by an official who has the authority to commit to spending the necessary funds to accomplish decommissioning, and it should be clearly asserted in the statement of intent that the signing official has that authority. In addition, the statement of intent should contain a statement that funding will be provided sufficiently in advance of decommissioning to prevent delay of required activities. If decommissioning funding is to continue to be assured by the State of Kansas, submit an updated statement of intent to this effect, signed by an appropriate State official. Otherwise, 10 CFR 50.75(e) provides alternate options for assurance of decommissioning funding. Please provide the necessary documentation within 30 days of the date of this letter.
Mr. Whaley In accordance with 10 CFR 50.30(b), your responses and the statement of intent must be executed in a signed original under oath or affirmation.
If you have any questions regarding this review, please contact me at 301-415-1631.
Sincerely,
/RA/
Daniel E. Hughes, Project Manager Research and Test Reactors Branch A Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-188
Enclosure:
As stated cc w/ enclosure: Please see next page
Kansas State University Docket No. 50-188 cc:
Office of the Governor State of Kansas Topeka, KS 66612 Mayor of Manhattan P.O. Box 748 Manhattan, KS 66502 Thomas A. Conley, RRPJ, CHP, Section Chief Radiation and Asbestos Control KS Dept of Health & Environment 1000 SW Jackson, Suite 320 Topeka, KS 66612-1366 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611
Mr. Whaley In accordance with 10 CFR 50.30(b), your responses and the statement of intent must be executed in a signed original under oath or affirmation.
If you have any questions regarding this review, please contact me at 301-415-1631.
Sincerely,
/RA/
Daniel E. Hughes, Project Manager Research and Test Reactors Branch A Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-188
Enclosure:
As stated cc w/ enclosure: Please see next page DISTRIBUTION:
PUBLIC PRTA r/f DHughes OGC MVoth MCase DCollins EHylton ADAMS ACCESSION NO: ML070820003 TEMPLATE #: NRR-088 OFFICE PRTA:PM PRTA:LA PRTA:BC PRTA:PM NAME DHughes:cah EHylton DCollins DHughes DATE 03/27/2007 03/29/2007 03/29/2007 03 /29/2007 OFFICIAL RECORD COPY
REQUEST FOR ADDITIONAL INFORMATION KANSAS STATE UNIVERSITY RESEARCH REACTOR DOCKET NO. 50-188
- 1. Safety limit for aluminum-clad fuel, TS 2.1.3(2), is not discussed in SAR. The bases refer to SAR Section 3.5.1 but there is no discussion there for Al-clad. Please provide a basis statement.
- 2. The bases for TS 2.2.3(1) refers to a LSSS for power of 1,250 kW. If this is to be a scram setpoint, how then is the reactor operated at full licensed power of 1,250 kW?
(The LSSS is a scram setpoint that should take into account calibration error, instrument error, instrument response time, and scram time.)
- 3. TS 3.2.3(1) - Is operation above 1,250 kW prevented by this LCO as well as the LSSS in 2.2.3(1)?
TS 3.2.3(2) - Is the LCO of 250 kW if there are aluminum-clad fuel elements in the core.
Is this an administrative limit? Should this not be an LSSS also?
- 4. TS 3.2.3(2) - Is the application of air to the transient rod prevented by an interlock or is it administratively prevented? (See Table II of present TSs.)
- 5. TS 3.4.3(2) -The SAR describes the startup countrate interlock at 2 cps. Since the SAR is more conservative than the TS, justify the inconsistency. The conditions for allowing a bypassing of the interlock should be specified in the TS. (See Table II of the present TSs.) The description of neutron induced counts seems more precise since it assures that the signal and not the noise is observed.
- 6. TS 3.4.4G - Does a Startup Count rate < 1 cps mean the channel is not operating? The bases should describe why the 1 (or 2) cps is acceptable.
- 7. TS 3.5.3 - Table 2 indicates that the startup count rate interlock is a required safety system channel, but the startup channel is not listed as a required measuring channel (Table 1, TS 3.4.3). Please add this to the list of required measuring channels or, alternatively, provide a justification for not including this channel in TS 3.4.3, Table 1.
- 8. TS 3.5.3 - Table 2 does not include the simultaneous rod withdrawal interlock, the control rod position interlock (see last paragraph of TS 3.5.5), or the 10 kW pulse interlock. (See Table II of the present TSs.) The action statement, TS 3.5.4.C, includes the Transient Control Rod interlock. Is that the same as the control rod position interlock mentioned in the bases?
- 9. TS 3.5.5 - In the first paragraph, the fuel temperature safety limit stated as 1000EC is not consistent with specification TS 2.1.3 (1).
Second paragraph: Again, there is some confusion with regard to power level (1,250 kW) and LSSS.
ENCLOSURE
- 10. TS 3.6.5 - First paragraph references an exposure rate for Ar-41 of 1.84E-4 microcuries h/mL in SAR Chapter 11, Appendix A. We cant find this number (either in the original Appendix A or the March 2006 update.)
- 11. TS 3.7.5 refers to a fuel temperature LSSS. You have not specified a fuel temperature LSSS, in the TSs, only a power LSSS. Please provide a correct bases.
- 12. TS 3.9.4B has a typo. The water conductivity Condition statement should read ..shall be less than 5 micromho/cm and the Required Action statement B.2 should read Restore conductivity to less than 5 micromho/cm.
- 13. TS 3.9.3(3) reads: Water level above the core shall be at least 13 feet from the top of the core. Are you only taking credit for 13 ft of water for shielding during operation?
What Tsat are you using for the CHFR calculations? Is it based on 13 ft or 16 ft of water?
- 14. TS 3.9.4C -There is a number missing in the Condition statement.
- 15. TS 3.9.3 - It may well be true that, with 16 feet of water above the core, the contribution to pool surface dose rates from N-16 located below 13 feet of water is negligible. But what if there is only 13 feet of water above the core? Are the dose rates still negligible?
The 13 foot level needs to be justified.
- 16. TS 3.9.5 -There is a verb missing from the last sentence (.........the requirement
_verified prior.......).
- 17. TS 4.5.2 - The surveillances described in the Table do not include the simultaneous rod withdrawal interlock or the 10 kW interlock. Please add these surveillances to TS 4.5.2 or, alternatively, provide a justification for not including them.
- 18. TS 4.7.2 and TS 4.7.3 - Should the reactivity worth of $0.40 be an absolute value?
- 19. TS 4.9.2 - Does the requirement to measure pool water conductivity at least every 20 days also apply if the reactor is shut down? This is not clear from specification.
Provide a justification for not including a surveillance requirement for pool water activity to ensure that the total activity released can be determined if a release of pool water occurs.
- 20. TS 6.1a) -The SAR has undergone several versions. Please provide an organization chart to TS 6.1 or, alternatively, provide a justification for not including it?
- 21. TS 6.1a) and 6.1b) - One section refers to the University Radiation Safety Officer as URSO and the other refers to the same as RSO. Please make the TS consistent.
- 22. TS 6.2b)4 - The present version of 10 CFR 50.59 no longer talks about unreviewed safety questions. The wording should conform to 10 CFR 50.59(c)(1).
- 23. TS 6.4b)4 -Same comment as above.
- 24. TS 6.4c)2- Same comment as above.
- 25. TS 6.11c) - (Note typo, should be c, not d) Initial notification should also be made to Region, in accordance with 50.36(7)(ii). Also, TS 6.11(d) address should be changed to Director, Division of Policy and Rulemaking (ZIP 20555).
- 26. TS 3.8 does not allow a fuel element in the core with bend or elongation > 1/8 inch.
Please include surveillance in TS 4.8.3 to ensure that TS 3.8 is not violated.
- 27. TS 5.3.3 - Explain why Experiment Reactivity limits are not absolute values.
- 28. There should be a TS on fuel storage specifying < 0.9 Keff (see ANS 15.1, Sect.5.4).
Also see G.1 and G.2 of the present TSs.
- 29. TS 5.3 does not specify any limits on explosives (Section 2.d of Reg Guide 2.2). Please provide one or, alternatively, provide a justification for not including it.
- 30. TS 3.5.3 contains a typo (3" should be 2"). There is no action statement or basis for this specification. Please explain.
- 31. The thermal hydraulic analysis in the SAR uses 83 fuel elements, with the statement that this is conservative because more fuel elements will result in less heat production per element. If so, should there not be a TS specifying a minimum of 83 elements?
- 32. TS 6.4c)1 references section 3.8. Should this be sections 3.7, 4.7, and 5.3?
- 33. Are the equivalent of D.4 and D.5 of the present TSs in the new TSs?
- 34. Is there the equivalent of the last two sentences of D.6 of the present TSs in the new TSs?
- 35. Is there the equivalent of E.3 of the present TSs in the new TSs? How are the limits on pulsing handled if not by the maximum reactivity of the pulse rod?
- 36. Is there the equivalent of E.11.a of the present TSs in the new TSs?
- 37. Is there the equivalent of E.4 of the present TSs in the new TSs? TS 4.6.2 is not equivalent.
- 38. Are the equivalent of I.4 and I.5 of the present TSs in the new TSs?